Sam is the project manager of a construction project in south Florida. This area of the United States is prone to hurricanes during certain parts of the year. As part of the project plan Sam and the project team acknowledge the possibility of hurricanes and the damage the hurricane could have on the project's deliverables, the schedule of the project, and the overall cost of the project. Once Sam and the project stakeholders acknowledge the risk of the hurricane they go on planning the project as if the risk is not likely to happen.
What type of risk response is Sam using?

  1. Mitigation
  2. Avoidance
  3. Passive acceptance
  4. Active acceptance

Answer(s): C



Fred is the project manager of the PKL project. He is working with his project team to complete the quantitative risk analysis process as a part of risk management planning. Fred understands that once the quantitative risk analysis process is complete, the process will need to be completed again in at least two other times in the project.
When will the quantitative risk analysis process need to be repeated?

  1. Quantitative risk analysis process will be completed again after the plan risk response planning and as part of procurement.
  2. Quantitative risk analysis process will be completed again after the cost management planning and as a part of monitoring and controlling.
  3. Quantitative risk analysis process will be completed again after new risks are identified and as part of monitoring and controlling.
  4. Quantitative risk analysis process will be completed again after the risk response planning and as a part of monitoring and controlling.

Answer(s): D



You are the project manager for a construction project. The project includes a work that involves very high financial risks. You decide to insure processes so that any ill happening can be compensated.
Which type of strategies have you used to deal with the risks involved with that particular work?

  1. Transfer
  2. Mitigate
  3. Accept
  4. Avoid

Answer(s): A



Which of the following are included in Administrative Controls? Each correct answer represents a complete solution. Choose all that apply.

  1. Conducting security-awareness training
  2. Screening of personnel
  3. Monitoring for intrusion
  4. Implementing change control procedures
  5. Developing policy

Answer(s): A,B,D,E



The Phase 2 of DITSCAP C&A is known as Verification. The goal of this phase is to obtain a fully integrated system for certification testing and accreditation.
What are the process activities of this phase?
Each correct answer represents a complete solution. Choose all that apply.

  1. Configuring refinement of the SSAA
  2. Assessment of the Analysis Results
  3. System development
  4. Certification analysis
  5. Registration

Answer(s): A,B,C,D



Share your comments for ISC CAP exam with other users:

D
Diran Ole
9/17/2023 5:15:00 PM

great exam prep

V
Venkata Subbarao Bandaru
6/24/2023 8:45:00 AM

i require dump

D
D
7/15/2023 1:38:00 AM

good morning, could you please upload this exam again,

A
Ann
9/15/2023 5:39:00 PM

hi can you please upload the dumps for sap contingent module. thanks

S
Sridhar
1/16/2024 9:19:00 PM

good questions

S
Summer
10/4/2023 9:57:00 PM

looking forward to the real exam

V
vv
12/2/2023 2:45:00 PM

good ones for exam preparation

D
Danny Zas
9/15/2023 4:45:00 AM

this is a good experience

S
SM 1211
10/12/2023 10:06:00 PM

hi everyone

A
A
10/2/2023 6:08:00 PM

waiting for the dump. please upload.

A
Anonymous
7/16/2023 11:05:00 AM

upload cks exam questions

J
Johan
12/13/2023 8:16:00 AM

awesome training material

P
PC
7/28/2023 3:49:00 PM

where is dump

Y
YoloStar Yoloing
10/22/2023 9:58:00 PM

q. 289 - the correct answer should be b not d, since the question asks for the most secure way to provide access to a s3 bucket (a single one), and by principle of the least privilege you should not be giving access to all buckets.

Z
Zelalem Nega
5/14/2023 12:45:00 PM

please i need if possible h12-831,

U
unknown-R
11/23/2023 7:36:00 AM

good collection of questions and solution for pl500 certification

S
Swaminathan
5/11/2023 9:59:00 AM

i would like to appear the exam.

V
Veenu
10/24/2023 6:26:00 AM

i am very happy as i cleared my comptia a+ 220-1101 exam. i studied from as it has all exam dumps and mock tests available. i got 91% on the test.

K
Karan
5/17/2023 4:26:00 AM

need this dump

R
Ramesh Kutumbaka
12/30/2023 11:17:00 PM

its really good to eventuate knowledge before appearing for the actual exam.

A
anonymous
7/20/2023 10:31:00 PM

this is great

X
Xenofon
6/26/2023 9:35:00 AM

please i want the questions to pass the exam

D
Diego
1/21/2024 8:21:00 PM

i need to pass exam

V
Vichhai
12/25/2023 3:25:00 AM

great, i appreciate it.

P
P Simon
8/25/2023 2:39:00 AM

please could you upload (isc)2 certified in cybersecurity (cc) exam questions

K
Karim
10/8/2023 8:34:00 PM

good questions, wrong answers

I
Itumeleng
1/6/2024 12:53:00 PM

im preparing for exams

M
MS
1/19/2024 2:56:00 PM

question no: 42 isnt azure vm an iaas solution? so, shouldnt the answer be "no"?

K
keylly
11/28/2023 10:10:00 AM

im study azure

D
dorcas
9/22/2023 8:08:00 AM

i need this now

T
treyf
11/9/2023 5:13:00 AM

i took the aws saa-c03 test and scored 935/1000. it has all the exam dumps and important info.

A
anonymous
1/11/2024 4:50:00 AM

good questions

A
Anjum
9/23/2023 6:22:00 PM

well explained

T
Thakor
6/7/2023 11:52:00 PM

i got the full version and it helped me pass the exam. pdf version is very good.

AI Tutor 👋 I’m here to help!