Sam is the project manager of a construction project in south Florida. This area of the United States is prone to hurricanes during certain parts of the year. As part of the project plan Sam and the project team acknowledge the possibility of hurricanes and the damage the hurricane could have on the project's deliverables, the schedule of the project, and the overall cost of the project. Once Sam and the project stakeholders acknowledge the risk of the hurricane they go on planning the project as if the risk is not likely to happen.
What type of risk response is Sam using?

  1. Mitigation
  2. Avoidance
  3. Passive acceptance
  4. Active acceptance

Answer(s): C



Fred is the project manager of the PKL project. He is working with his project team to complete the quantitative risk analysis process as a part of risk management planning. Fred understands that once the quantitative risk analysis process is complete, the process will need to be completed again in at least two other times in the project.
When will the quantitative risk analysis process need to be repeated?

  1. Quantitative risk analysis process will be completed again after the plan risk response planning and as part of procurement.
  2. Quantitative risk analysis process will be completed again after the cost management planning and as a part of monitoring and controlling.
  3. Quantitative risk analysis process will be completed again after new risks are identified and as part of monitoring and controlling.
  4. Quantitative risk analysis process will be completed again after the risk response planning and as a part of monitoring and controlling.

Answer(s): D



You are the project manager for a construction project. The project includes a work that involves very high financial risks. You decide to insure processes so that any ill happening can be compensated.
Which type of strategies have you used to deal with the risks involved with that particular work?

  1. Transfer
  2. Mitigate
  3. Accept
  4. Avoid

Answer(s): A



Which of the following are included in Administrative Controls? Each correct answer represents a complete solution. Choose all that apply.

  1. Conducting security-awareness training
  2. Screening of personnel
  3. Monitoring for intrusion
  4. Implementing change control procedures
  5. Developing policy

Answer(s): A,B,D,E



The Phase 2 of DITSCAP C&A is known as Verification. The goal of this phase is to obtain a fully integrated system for certification testing and accreditation.
What are the process activities of this phase?
Each correct answer represents a complete solution. Choose all that apply.

  1. Configuring refinement of the SSAA
  2. Assessment of the Analysis Results
  3. System development
  4. Certification analysis
  5. Registration

Answer(s): A,B,C,D



Share your comments for ISC CAP exam with other users:

C
Chiranthaka
9/20/2023 11:22:00 AM

very useful!

N
Not Miguel
11/26/2023 9:43:00 PM

for this question - "which three type of basic patient or member information is displayed on the patient info component? (choose three.)", list of conditions is not displayed (it is displayed in patient card, not patient info). so should be thumbnail of chatter photo

A
Andrus
12/17/2023 12:09:00 PM

q52 should be d. vm storage controller bandwidth represents the amount of data (in terms of bandwidth) that a vms storage controller is using to read and write data to the storage fabric.

R
Raj
5/25/2023 8:43:00 AM

nice questions

M
max
12/22/2023 3:45:00 PM

very useful

M
Muhammad Rawish Siddiqui
12/8/2023 6:12:00 PM

question # 208: failure logs is not an example of operational metadata.

S
Sachin Bedi
1/5/2024 4:47:00 AM

good questions

K
Kenneth
12/8/2023 7:34:00 AM

thank you for the test materials!

H
Harjinder Singh
8/9/2023 4:16:00 AM

its very helpful

S
SD
7/13/2023 12:56:00 AM

good questions

K
kanjoe
7/2/2023 11:40:00 AM

good questons

M
Mahmoud
7/6/2023 4:24:00 AM

i need the dumb of the hcip security v4.0 exam

W
Wei
8/3/2023 4:18:00 AM

upload the dump please

S
Stephen
10/3/2023 6:24:00 PM

yes, iam looking this

S
Stephen
8/4/2023 9:08:00 PM

please upload cima e2 managing performance dumps

H
hp
6/16/2023 12:44:00 AM

wonderful questions

P
Priyo
11/14/2023 2:23:00 AM

i used this site since 2000, still great to support my career

J
Jude
8/29/2023 1:56:00 PM

why is the answer to "which of the following is required by scrum?" all of the following stated below since most of them are not mandatory? sprint retrospective. members must be stand up at the daily scrum. sprint burndown chart. release planning.

M
Marc blue
9/15/2023 4:11:00 AM

great job. hope this helps out.

A
Anne
9/13/2023 2:33:00 AM

upload please. many thanks!

P
pepe el toro
9/12/2023 7:55:00 PM

this is so interesting

A
Antony
11/28/2023 12:13:00 AM

great material thanks

T
Thembelani
5/30/2023 2:22:00 AM

anyone who wrote this exam recently

P
P
9/16/2023 1:27:00 AM

ok they re good

J
Jorn
7/13/2023 5:05:00 AM

relevant questions

A
AM
6/20/2023 7:54:00 PM

please post

N
Nagendra Pedipina
7/13/2023 2:22:00 AM

q:42 there has to be a image in the question to choose what does it mean from the options

B
BrainDumpee
11/18/2023 1:36:00 PM

looking for cphq dumps, where can i find these for free? please and thank you.

S
sheik
10/14/2023 11:37:00 AM

@aarun , thanks for the information. it would be great help if you share your email

R
Random user
12/11/2023 1:34:00 AM

1z0-1078-23 need this dumps

L
labuschanka
11/16/2023 6:06:00 PM

i gave the microsoft azure az-500 tests and prepared from this site as it has latest mock tests available which helped me evaluate my performance and score 919/1000

M
Marianne
10/22/2023 11:57:00 PM

i cannot see the button to go to the questions

S
sushant
6/28/2023 4:52:00 AM

good questions

A
A\MAM
6/27/2023 5:17:00 PM

q-6 ans-b correct. https://docs.paloaltonetworks.com/pan-os/9-1/pan-os-cli-quick-start/use-the-cli/commit-configuration-changes

AI Tutor 👋 I’m here to help!