ISACA Certified in Risk and Information Systems Control CRISC Dumps in PDF

Free ISACA CRISC Real Questions (page: 68)

You work as a project manager for BlueWell Inc. You have declined a proposed change request because of the risk associated with the proposed change request. Where should the declined change request be documented and stored?

  1. Change request log
  2. Project archives
  3. Lessons learned
  4. Project document updates

Answer(s): A

Explanation:

The change request log records the status of all change requests, approved or declined.

The change request log is used as an account for change requests and as a means of tracking their disposition on a current basis. The change request log develops a measure of consistency into the change management process. It encourages common inputs into the process and is a common estimation approach for all change requests. As the log is an important component of project requirements, it should be readily available to the project team members responsible for project delivery. It should be maintained in a file with read-only access to those who are not responsible for approving or disapproving project change requests.

Incorrect Answers:
B: The project archive includes all project documentation and is created through the close project or phase process. It is not the best choice for this question.

C: Lessons learned are not the correct place to document the status of a declined, or approved, change request.

D: The project document updates is not the best choice for this to be fleshed into the project documents, but the declined changes are part of the change request log.



Which of the following comes under phases of risk management?

  1. Assessing risk
  2. Prioritization of risk
  3. Identify risk
  4. Monitoring risk
  5. Developing risk

Answer(s): A,B,C,D

Explanation:

Risk management provides an approach for individuals and groups to make a decision on how to deal with potentially harmful situations.
Following are the four phases involved in risk management:
1. Risk identification: The first thing we must do in risk management is to identify the areas of the project where the risks can occur.
This is termed as risk identification. Listing all the possible risks is proved to be very productive for the enterprise as we can cure them before it can occur. In risk identification both threats and opportunities are considered, as both carry some level of risk with them.
2. Risk Assessment and Evaluation: Risk assessment use quantitative and qualitative analysis approaches to evaluate each significant risk identified.
3. Risk Prioritization and Response: As many risks are being identified in an enterprise, it is best to give each risk a score based on its likelihood and significance in form of ranking. This concludes whether the risk with high likelihood and high significance must be given greater attention as compared to similar risk with low likelihood and low significance. Hence, risks can be prioritized and appropriate responses to those risks are created.
4. Risk Monitoring: Risk monitoring is an activity which oversees the changes in risk assessment. Over time, the likelihood or significance originally attributed to a risk may change. This is especially true when certain responses, such as mitigation, have been made.



You are the project manager in your enterprise. You have identified occurrence of risk event in your enterprise. You have pre-planned risk responses. You have monitored the risks that had occurred. What is the immediate step after this monitoring process that has to be followed in response to risk events?

  1. Initiate incident response
  2. Update the risk register
  3. Eliminate the risk completely
  4. Communicate lessons learned from risk events

Answer(s): A

Explanation:

When the risk events occur then following tasks have to done to react to it: Maintain incident response plans
Monitor risk
Initiate incident response
Communicate lessons learned from risk events



You are the project manager for GHT project. You need to perform the Qualitative risk analysis process. When you have completed this process, you will produce all of the following as part of the risk register update output except which one?

  1. Probability of achieving time and cost estimates
  2. Priority list of risks
  3. Watch list of low-priority risks
  4. Risks grouped by categories

Answer(s): A

Explanation:

Probability of achieving time and cost estimates is an update that is produced from the Quantitative risk analysis process. In Qualitative risk analysis probability of occurrence of a specific risk is identified but not of achieving time and cost estimates.



You have been assigned as the Project Manager for a new project that involves building of a new roadway between the city airport to a designated point within the city. However, you notice that the transportation permit issuing authority is taking longer than the planned time to issue the permit to begin construction. What would you classify this as?

  1. Project Risk
  2. Status Update
  3. Risk Update
  4. Project Issue

Answer(s): D

Explanation:

This is a project issue. It is easy to confuse this as a project risk; however, a project risk is always in the future. In this case, the delay by the permitting agency has already happened; hence this is a project issue. The possible impact of this delay on the project cost, schedule, or performance can be classified as a project risk.

Incorrect Answers:
A: It is easy to confuse this as a project risk; however, a project risk is always in the future. In this case, the delay by the permitting agency has already happened; hence this is a project issue.

B, C: These are options are not valid.



Share your comments for ISACA CRISC exam with other users:

C
Christian Klein
6/23/2023 1:32:00 PM

is it legit questions from sap certifications ?

A
anonymous
1/12/2024 3:34:00 PM

question 16 should be b (changing the connector settings on the monitor) pc and monitor were powered on. the lights on the pc are on indicating power. the monitor is showing an error text indicating that it is receiving power too. this is a clear sign of having the wrong input selected on the monitor. thus, the "connector setting" needs to be switched from hdmi to display port on the monitor so it receives the signal from the pc, or the other way around (display port to hdmi).

N
NSPK
1/18/2024 10:26:00 AM

q 10. ans is d (in the target org: open deployment settings, click edit next to the source org. select allow inbound changes and save

M
mohamed abdo
9/1/2023 4:59:00 AM

very useful

T
Tom
3/18/2022 8:00:00 PM

i purchased this exam dumps from another website with way more questions but they were all invalid and outdate. this exam dumps was right to the point and all from recent exam. it was a hard pass.

E
Edrick GOP
10/24/2023 6:00:00 AM

it was a good experience and i got 90% in the 200-901 exam.

A
anonymous
8/10/2023 2:28:00 AM

hi please upload this

B
Bakir
7/6/2023 7:24:00 AM

please upload it

A
Aman
6/18/2023 1:27:00 PM

really need this dump. can you please help.

N
Neela Para
1/8/2024 6:39:00 PM

really good and covers many areas explaining the answer.

K
Karan Patel
8/15/2023 12:51:00 AM

yes, can you please upload the exam?

N
NISHAD
11/7/2023 11:28:00 AM

how many questions are there in these dumps?

P
Pankaj
7/3/2023 3:57:00 AM

hi team, please upload this , i need it.

D
DN
9/4/2023 11:19:00 PM

question 14 - run terraform import: this is the recommended best practice for bringing manually created or destroyed resources under terraform management. you use terraform import to associate an existing resource with a terraform resource configuration. this ensures that terraform is aware of the resource, and you can subsequently manage it with terraform.

Z
Zhiguang
8/19/2023 11:37:00 PM

please upload dump. thanks in advance.

D
deedee
12/23/2023 5:51:00 PM

great great

A
Asad Khan
11/1/2023 3:10:00 AM

answer 16 should be b your organizational policies require you to use virtual machines directly

S
Sale Danasabe
10/24/2023 5:21:00 PM

the question are kind of tricky of you didnt get the hnag on it.

L
Luis
11/16/2023 1:39:00 PM

can anyone tell me if this is for rhel8 or rhel9?

H
hik
1/19/2024 1:47:00 PM

good content

B
Blessious Phiri
8/15/2023 2:18:00 PM

pdb and cdb are critical to the database

Z
Zuned
10/22/2023 4:39:00 AM

till 104 questions are free, lets see how it helps me in my exam today.

M
Muhammad Rawish Siddiqui
12/3/2023 12:11:00 PM

question # 56, answer is true not false.

A
Amaresh Vashishtha
8/27/2023 1:33:00 AM

i would be requiring dumps to prepare for certification exam

A
Asad
9/8/2023 1:01:00 AM

very helpful

B
Blessious Phiri
8/13/2023 3:10:00 PM

control file is the heart of rman backup

S
Senthil
9/19/2023 5:47:00 AM

hi could you please upload the ibm c2090-543 dumps

H
Harry
6/27/2023 7:20:00 AM

appriciate if you could upload this again

A
Anonymous
7/10/2023 4:10:00 AM

please upload the dump

R
Raja
6/20/2023 5:30:00 AM

i found some questions answers mismatch with explanation answers. please properly update

D
Doora
11/30/2023 4:20:00 AM

nothing to mention

D
deally
1/19/2024 3:41:00 PM

knowable questions

S
Sonia
7/23/2023 4:03:00 PM

very helpfull

B
binEY
10/6/2023 5:15:00 AM

good questions

AI Tutor 👋 I’m here to help!