You work as a project manager for BlueWell Inc. You have declined a proposed change request because of the risk associated with the proposed change request. Where should the declined change request be documented and stored?
Answer(s): A
The change request log records the status of all change requests, approved or declined.The change request log is used as an account for change requests and as a means of tracking their disposition on a current basis. The change request log develops a measure of consistency into the change management process. It encourages common inputs into the process and is a common estimation approach for all change requests. As the log is an important component of project requirements, it should be readily available to the project team members responsible for project delivery. It should be maintained in a file with read-only access to those who are not responsible for approving or disapproving project change requests.Incorrect Answers:B: The project archive includes all project documentation and is created through the close project or phase process. It is not the best choice for this question.C: Lessons learned are not the correct place to document the status of a declined, or approved, change request.D: The project document updates is not the best choice for this to be fleshed into the project documents, but the declined changes are part of the change request log.
Which of the following comes under phases of risk management?
Answer(s): A,B,C,D
Risk management provides an approach for individuals and groups to make a decision on how to deal with potentially harmful situations.Following are the four phases involved in risk management:1. Risk identification: The first thing we must do in risk management is to identify the areas of the project where the risks can occur.This is termed as risk identification. Listing all the possible risks is proved to be very productive for the enterprise as we can cure them before it can occur. In risk identification both threats and opportunities are considered, as both carry some level of risk with them.2. Risk Assessment and Evaluation: Risk assessment use quantitative and qualitative analysis approaches to evaluate each significant risk identified.3. Risk Prioritization and Response: As many risks are being identified in an enterprise, it is best to give each risk a score based on its likelihood and significance in form of ranking. This concludes whether the risk with high likelihood and high significance must be given greater attention as compared to similar risk with low likelihood and low significance. Hence, risks can be prioritized and appropriate responses to those risks are created.4. Risk Monitoring: Risk monitoring is an activity which oversees the changes in risk assessment. Over time, the likelihood or significance originally attributed to a risk may change. This is especially true when certain responses, such as mitigation, have been made.
You are the project manager in your enterprise. You have identified occurrence of risk event in your enterprise. You have pre-planned risk responses. You have monitored the risks that had occurred. What is the immediate step after this monitoring process that has to be followed in response to risk events?
When the risk events occur then following tasks have to done to react to it: Maintain incident response plansMonitor riskInitiate incident responseCommunicate lessons learned from risk events
You are the project manager for GHT project. You need to perform the Qualitative risk analysis process. When you have completed this process, you will produce all of the following as part of the risk register update output except which one?
Probability of achieving time and cost estimates is an update that is produced from the Quantitative risk analysis process. In Qualitative risk analysis probability of occurrence of a specific risk is identified but not of achieving time and cost estimates.
You have been assigned as the Project Manager for a new project that involves building of a new roadway between the city airport to a designated point within the city. However, you notice that the transportation permit issuing authority is taking longer than the planned time to issue the permit to begin construction. What would you classify this as?
Answer(s): D
This is a project issue. It is easy to confuse this as a project risk; however, a project risk is always in the future. In this case, the delay by the permitting agency has already happened; hence this is a project issue. The possible impact of this delay on the project cost, schedule, or performance can be classified as a project risk.Incorrect Answers:A: It is easy to confuse this as a project risk; however, a project risk is always in the future. In this case, the delay by the permitting agency has already happened; hence this is a project issue.B, C: These are options are not valid.
Share your comments for ISACA CRISC exam with other users:
question 75: option c is correct answer
please add this exam
please upoad
has anyone recently attended safe 6.0 certification? is it the samq question from here.
expository experience
52 should be b&c. controller failure has nothing to do with this type of issue. degraded state tells us its a raid issue, and if the os is missing then the bootable device isnt found. the only other consideration could be data loss but thats somewhat broad whereas b&c show understanding of the specific issues the question is asking about.
great help!!!
very useful tools
looks a good platform to prepare az-104
want to pass the exam
good resource
question 11 : d
only the free dumps will be enough for pass, or have to purchase the premium one. please suggest.
good questions. thanks.
good for practice.
great case study
the questions in this exam dumps is valid. i passed my test last monday. i only whish they had their pricing in inr instead of usd. but it is still worth it.
q40 the answer is not d, why are you giving incorrect answers? snapshot consolidation is used to merge the snapshot delta disk files to the vm base disk
thanks, very relevant
wrong answer. it is true not false.
please i need the mo-100 questions
very good use full
very valid questions
will these question help me to clear pl-300 exam?
please provide me with these dumps questions. thanks
in the pdf downloaded is write google cloud database engineer i think that it isnt the correct exam
i think you have the answers wrong regarding question: "what are three core principles of web content accessibility guidelines (wcag)? answer: robust, operable, understandable
these questions are not valid , they dont come for the exam now
question looks valid
good for practice
need more q&a to go ahead
question 59 - a newly-created role is not assigned to any user, nor granted to any other role. answer is b https://docs.snowflake.com/en/user-guide/security-access-control-overview
just passed my exam today. i saw all of these questions in my text today. so i can confirm this is a valid dump.
needed dumps