You are elected as the project manager of GHT project. You have to initiate the project. Your Project request document has been approved, and now you have to start working on the project. What is the FIRST step you should take to initialize the project?

  1. Conduct a feasibility study
  2. Acquire software
  3. Define requirements of project
  4. Plan project management

Answer(s): A

Explanation:

Conducting a feasibility study begins once initial approval has been given to move forward with a project. It includes an analysis to clearly define the need and to identify alternatives for addressing the need.

Incorrect Answers:
B: Acquiring software involves building new or modifying existing hardware or software after final approval by the stakeholder, which is not a phase in the standard SDLC process. If a decision was reached to acquire rather than develop software, this task should occur after feasibility study and defining requirements.

C: Requirements of the project is being defined after conducting feasibility study.

D: This is latter phase in project development process.



John is the project manager of the NHQ Project for his company. His project has 75 stakeholders, some of which are external to the organization. John needs to make certain that he communicates about risk in the most appropriate method for the external stakeholders. Which project management plan will be the best guide for John to communicate to the external stakeholders?

  1. Risk Response Plan
  2. Communications Management Plan
  3. Project Management Plan
  4. Risk Management Plan

Answer(s): B

Explanation:

The Communications Management Plan will direct John on the information to be communicated, when to communicate, and how to communicate with external stakeholders.

The Communications Management Plan aims to define the communication necessities for the project and how the information will be circulated. The Communications Management Plan sets the communication structure for the project. This structure provides guidance for communication throughout the project's life and is updated as communication needs change. The Communication Managements Plan identifies and defines the roles of persons concerned with the project. It includes a matrix known as the communication matrix to map the communication requirements of the project.

Incorrect Answers:
A: The Risk Response Plan identifies how risks will be responded to.

C: The Project Management Plan is the parent of all subsidiary management plans and it is not the most accurate choice for this question

D: The Risk Management Plan defines how risks will be identified, analyzed, responded to, and controlled throughout the project.



Adrian is a project manager for a new project using a technology that has recently been released and there's relatively little information about the technology. Initial testing of the technology makes the use of it look promising, but there's still uncertainty as to the longevity and reliability of the technology. Adrian wants to consider the technology factors a risk for her project. Where should she document the risks associated with this technology so she can track the risk status and responses?

  1. Project scope statement
  2. Project charter
  3. Risk low-level watch list
  4. Risk register

Answer(s): D

Explanation:

A risk register is an inventory of risks and exposure associated with those risks. Risks are commonly found in project management practices, and provide information to identify, analyze, and manage risks. Typically a risk register contains:
A description of the risk
The impact should this event actually occur The probability of its occurrence
Risk Score (the multiplication of Probability and Impact)
A summary of the planned response should the event occur
A summary of the mitigation (the actions taken in advance to reduce the probability and/or impact of the event)
Ranking of risks by Risk Score so as to highlight the highest priority risks to all involved.
It records the initial risks, the potential responses, and tracks the status of each identified risk in the project.

Incorrect Answers:
A: The project scope statement does document initially defined risks but it is not a place that will record risks responses and status of risks.

B: The project charter does not define risks.

C: The risk low-level watch list is for identified risks that have low impact and low probability in the project.



You are the administrator of your enterprise. Which of the following controls would you use that BEST protects an enterprise from unauthorized individuals gaining access to sensitive information?

  1. Monitoring and recording unsuccessful logon attempts
  2. Forcing periodic password changes
  3. Using a challenge response system
  4. Providing access on a need-to-know basis

Answer(s): D

Explanation:

Physical or logical system access should be assigned on a need-to-know basis, where there is a legitimate business requirement based on least privilege and segregation of duties. This is done by user authentication.

Incorrect Answers:
A: Monitoring and recording unsuccessful logon attempts does not address the risk of appropriate access rights. In other words, it does not prevent unauthorized access.

B: Forcing users to change their passwords does not ensure that access control is appropriately assigned.

C: Challenge response system is used to verify the user's identification but does not completely address the issue of access risk if access was not appropriately designed in the first place.



You are the project manager of GHT project. You have identified a risk event on your current project that could save $670,000 in project costs if it occurs. Your organization is considering hiring a vendor to help establish proper project management techniques in order to assure it realizes these savings. Which of the following statements is TRUE for this risk event?

  1. This risk event should be accepted because the rewards outweigh the threat to the project.
  2. This risk event should be mitigated to take advantage of the savings.
  3. This risk event is an opportunity to the project and should be exploited.
  4. This is a risk event that should be shared to take full advantage of the potential savings.

Answer(s): C



Share your comments for ISACA CRISC exam with other users:

H
Hiren Ladva
7/8/2023 10:34:00 PM

yes i m prepared exam

O
oliverjames
10/24/2023 5:37:00 AM

my experience was great with this site as i studied for the ms-900 from here and got 900/1000 on the test. my main focus was on the tutorials which were provided and practice questions. thanks!

B
Bhuddhiman
7/20/2023 11:52:00 AM

great course

A
Anuj
1/14/2024 4:07:00 PM

very good question

S
Saravana Kumar TS
12/8/2023 9:49:00 AM

question: 93 which statement is true regarding the result? sales contain 6 columns and values contain 7 columns so c is not right answer.

L
Lue
3/30/2023 11:43:00 PM

highly recommend just passed my exam.

D
DC
1/7/2024 10:17:00 AM

great practice! thanks

A
Anonymus
11/9/2023 5:41:00 AM

anyone who wrote this exam recently?

K
Khalid Javid
11/17/2023 3:46:00 PM

kindly share the dump

N
Na
8/9/2023 8:39:00 AM

could you please upload cfe fraud prevention and deterrence questions? it will be very much helpful.

S
shime
10/23/2023 10:03:00 AM

this is really very very helpful for mcd level 1

V
Vnu
6/3/2023 2:39:00 AM

very helpful!

S
Steve
8/17/2023 2:19:00 PM

question #18s answer should be a, not d. this should be corrected. it should be minvalidityperiod

R
RITEISH
12/24/2023 4:33:00 AM

thanks for the exact solution

S
SB
10/15/2023 7:58:00 AM

need to refer the questions and have to give the exam

M
Mike Derfalem
7/16/2023 7:59:00 PM

i need it right now if it was possible please

I
Isak
7/6/2023 3:21:00 AM

i need it very much please share it in the fastest time.

M
Maria
6/23/2023 11:40:00 AM

correct answer is d for student.java program

N
Nagendra Pedipina
7/12/2023 9:10:00 AM

q:37 c is correct

J
John
9/16/2023 9:37:00 PM

q6 exam topic: terramearth, c: correct answer: copy 1petabyte to encrypted usb device ???

S
SAM
12/4/2023 12:56:00 AM

explained answers

A
Andy
12/26/2023 9:35:00 PM

plan to take theaws certified developer - associate dva-c02 in the next few weeks

S
siva
5/17/2023 12:32:00 AM

very helpfull

M
mouna
9/27/2023 8:53:00 AM

good questions

B
Bhavya
9/12/2023 7:18:00 AM

help to practice csa exam

M
Malik
9/28/2023 1:09:00 PM

nice tip and well documented

R
rodrigo
6/22/2023 7:55:00 AM

i need the exam

D
Dan
6/29/2023 1:53:00 PM

please upload

A
Ale M
11/22/2023 6:38:00 PM

prepping for fsc exam

A
ahmad hassan
9/6/2023 3:26:00 AM

pd1 with great experience

Ž
Žarko
9/5/2023 3:35:00 AM

@t it seems like azure service bus message quesues could be the best solution

S
Shiji
10/15/2023 1:08:00 PM

helpful to check your understanding.

D
Da Costa
8/27/2023 11:43:00 AM

question 128 the answer should be static not auto

B
bot
7/26/2023 6:45:00 PM

more comments here

AI Tutor 👋 I’m here to help!