ISACA Certified in Risk and Information Systems Control CRISC Dumps in PDF

Free ISACA CRISC Real Questions (page: 20)

Stephen is the project manager of the GBB project. He has worked with two subject matter experts and his project team to complete the risk assessment technique. There are approximately 47 risks that have a low probability and a low impact on the project. Which of the following answers best describes what Stephen should do with these risk events?

  1. Because they are low probability and low impact, Stephen should accept the risks.
  2. The low probability and low impact risks should be added to a watchlist for future monitoring.
  3. Because they are low probability and low impact, the risks can be dismissed.
  4. The low probability and low impact risks should be added to the risk register.

Answer(s): B

Explanation:

The low probability and low impact risks should be added to a watchlist for future monitoring. Incorrect Answers:
A: The risk response for these events may be to accept them, but the best answer is to first add them to a watchlist.

C: Risks are not dismissed; they are at least added to a watchlist for monitoring.

D: While the risks may eventually be added to the register, the best answer is to first add them to the watchlist for monitoring.



Jenny is the project manager for the NBT projects. She is working with the project team and several subject matter experts to perform the quantitative risk analysis process. During this process she and the project team uncover several risks events that were not previously identified. What should Jenny do with these risk events?

  1. The events should be entered into qualitative risk analysis.
  2. The events should be determined if they need to be accepted or responded to.
  3. The events should be entered into the risk register.
  4. The events should continue on with quantitative risk analysis.

Answer(s): C

Explanation:

All identified risk events should be entered into the risk register.

A risk register is an inventory of risks and exposure associated with those risks. Risks are commonly found in project management practices, and provide information to identify, analyze, and manage risks. Typically a risk register contains:
A description of the risk
The impact should this event actually occur The probability of its occurrence
Risk Score (the multiplication of Probability and Impact)
A summary of the planned response should the event occur
A summary of the mitigation (the actions taken in advance to reduce the probability and/or impact of the event)
Ranking of risks by Risk Score so as to highlight the highest priority risks to all involved.

Incorrect Answers:
A: Before the risk events are analyzed they should be documented in the risk register. B: The risks should first be documented and analyzed.
D: These risks should first be identified, documented, passed through qualitative risk analysis and then it should be determined if they should pass through the quantitative risk analysis process.



You are working on a project in an enterprise. Some part of your project requires e-commerce, but your enterprise choose not to engage in e-commerce. This scenario is demonstrating which of the following form?

  1. risk avoidance
  2. risk treatment
  3. risk acceptance
  4. risk transfer

Answer(s): A

Explanation:

Each business process involves inherent risk. Not engaging in any activity avoids the inherent risk associated with the activity. Hence this demonstrates risk avoidance.

Incorrect Answers:
B: Risk treatment means that action is taken to reduce the frequency and impact of a risk.

C: Acceptance means that no action is taken relative to a particular risk, and loss is accepted when/if it occurs. This is different from being ignorant of risk; accepting risk assumes that the risk is known, i.e., an informed decision has been made by management to accept it as such.

D: Risk transfer/sharing means reducing either risk frequency or impact by transferring or otherwise sharing a portion of the risk. Common techniques include insurance and outsourcing. These techniques do not relieve an enterprise of a risk, but can involve the skills of another party in managing the risk and reducing the financial consequence if an adverse event occurs.



Which of the following are risk components of the COSO ERM framework? Each correct answer represents a complete solution. Choose three.

  1. Risk response
  2. Internal environment
  3. Business continuity
  4. Control activities

Answer(s): A,B,D

Explanation:

The risk components defined by the COSO ERM are internal environment, objective settings, event identification, risk assessment, risk response, control objectives, information and communication, and monitoring.

Incorrect Answers:
C: Business continuity is not considered as risk component within the ERM framework.



Your project team has completed the quantitative risk analysis for your project work. Based on their findings, they need to update the risk register with several pieces of information. Which one of the following components is likely to be updated in the risk register based on their analysis?

  1. Listing of risk responses
  2. Risk ranking matrix
  3. Listing of prioritized risks
  4. Qualitative analysis outcomes

Answer(s): C

Explanation:

The outcome of quantitative analysis can create a listing of prioritized risks that should be updated in the risk register. The project team will create and update the risk register with four key components:
probabilistic analysis of the project
probability of achieving time and cost objectives list of quantified risks
trends in quantitative risk analysis

Incorrect Answers:
A, B, D: These subjects are not updated in the risk register as a result of quantitative risk analysis.



Share your comments for ISACA CRISC exam with other users:

S
Sanjay
10/15/2023 1:34:00 PM

great site to practice for sitecore exam

J
jaya
12/17/2023 8:36:00 AM

good for students

B
Bsmaind
8/20/2023 9:23:00 AM

nice practice dumps

K
kumar
11/15/2023 11:24:00 AM

nokia 4a0-114 dumps

V
Vetri
10/3/2023 12:59:00 AM

great content and wonderful to have the answers with explanation

R
Ranjith
8/21/2023 3:39:00 PM

for question #118, the answer is option c. the screen shot is showing the drop down, but the answer is marked incorrectly please update . thanks for sharing such nice questions.

E
Eduardo Ramírez
12/11/2023 9:55:00 PM

the correct answer for the question 29 is d.

D
Dass
11/2/2023 7:43:00 AM

question no 22: correct answers: bc, 1 per session 1 per page 1 per component always

R
Reddy
12/14/2023 2:42:00 AM

these are pretty useful

D
Daisy Delgado
1/9/2023 1:05:00 PM

awesome

A
Atif
6/13/2023 4:09:00 AM

yes please upload

X
Xunil
6/12/2023 3:04:00 PM

great job whoever put this together, for the greater good! thanks!

L
Lakshmi
10/2/2023 5:26:00 AM

just started to view all questions for the exam

R
rani
1/19/2024 11:52:00 AM

helpful material

G
Greg
11/16/2023 6:59:00 AM

hope for the best

H
hi
10/5/2023 4:00:00 AM

will post exam has finished

V
Vmotu
8/24/2023 11:14:00 AM

really correct and good analyze!

H
hicham
5/30/2023 8:57:00 AM

excellent thanks a lot

S
Suman C
7/7/2023 8:13:00 AM

will post once pass the cka exam

R
Ram
11/3/2023 5:10:00 AM

good content

N
Nagendra Pedipina
7/13/2023 2:12:00 AM

q:32 answer has to be option c

T
Tamer Barakat
12/7/2023 5:17:00 PM

nice questions

D
Daryl
8/1/2022 11:33:00 PM

i really like the support team in this website. they are fast in communication and very helpful.

C
Curtis Nakawaki
6/29/2023 9:13:00 PM

a good contemporary exam review

X
x-men
5/23/2023 1:02:00 AM

q23, its an array, isnt it? starts with [ and end with ]. its an array of objects, not object.

A
abuti
7/21/2023 6:24:00 PM

cool very helpfull

K
Krishneel
3/17/2023 10:34:00 AM

i just passed. this exam dumps is the same one from prepaway and examcollection. it has all the real test questions.

R
Regor
12/4/2023 2:01:00 PM

is this a valid prince2 practitioner dumps?

A
asl
9/14/2023 3:59:00 PM

all are relatable questions

S
Siyya
1/19/2024 8:30:00 PM

might help me to prepare for the exam

T
Ted
6/21/2023 11:11:00 PM

just paid and downlaod the 2 exams using the 50% sale discount. so far i was able to download the pdf and the test engine. all looks good.

P
Paul K
11/27/2023 2:28:00 AM

i think it should be a,c. option d goes against the principle of building anything custom unless there are no work arounds available

P
ph
6/16/2023 12:41:00 AM

very legible

S
sephs2001
7/31/2023 10:42:00 PM

is this exam accurate or helpful?

AI Tutor 👋 I’m here to help!