ISACA CRISC Exam (page: 19)
ISACA Certified in Risk and Information Systems Control
Updated on: 16-Feb-2026

Viewing Page 19 of 361

You have been assigned as the Project Manager for a new project that involves development of a new interface for your existing time management system. You have completed identifying all possible risks along with the stakeholders and team and have calculated the probability and impact of these risks. Which of the following would you need next to help you prioritize the risks?

  1. Affinity Diagram
  2. Risk rating rules
  3. Project Network Diagram
  4. Risk categories

Answer(s): B

Explanation:

Risk rating rules define how to prioritize risks after the related probability and impact values are calculated. These are generally included in the organizational process assets and are refined for individual projects.

Incorrect Answers:
A: Affinity Diagram is a method of group creativity technique to collect requirements which allows large numbers of ideas to be sorted into groups for review and analysis. This is generally used in Scope Management and not applicable to this option.

C: A Project Network diagram shows the sequencing and linkage between various project tasks and is not applicable to this question

D: Risk categories are an output of the Perform Qualitative Risk Analysis process and not a tool to complete the process.



You are the project manager of a large networking project. During the execution phase the customer requests for a change in the existing project plan. What will be your immediate action?

  1. Update the risk register.
  2. Ask for a formal change request.
  3. Ignore the request as the project is in the execution phase.
  4. Refuse the change request.

Answer(s): B

Explanation:

Whenever the customer or key stakeholder asks for a change in the existing plan, you should ask him/her to submit a formal change request. Change requests may modify project policies or procedures, project scope, project cost or budget, project schedule, or project quality.

Incorrect Answers:
A, C, D: The first action required is to create a formal change request, if a change is requested in the project.



Which of the following is described by the definition given below? "It is the expected guaranteed value of taking a risk."

  1. Certainty equivalent value
  2. Risk premium
  3. Risk value guarantee
  4. Certain value assurance

Answer(s): A

Explanation:

The Certainty equivalent value is the expected guaranteed value of taking a risk. It is derived by the uncertainty of the situation and the potential value of the situation's outcome.

Incorrect Answers:
B: The risk premium is the difference between the larger expected value of the risk and the smaller certainty equivalent value.

C, D: These are not valid answers.



You are the project manager of GHT project. Your hardware vendor left you a voicemail saying that the delivery of the equipment you have ordered would not arrive on time. She wanted to give you a heads-up and asked that you return the call. Which of the following statements is TRUE?

  1. This is a residual risk.
  2. This is a trigger.
  3. This is a contingency plan.
  4. This is a secondary risk.

Answer(s): B

Explanation:

Triggers are warning signs of an upcoming risk event. Here delay in delivery signifies that there may be a risk event like delay in completion of project. Hence it is referred to as a trigger.

Incorrect Answers:
A: Residual risk is the risk that remains after applying controls. But here in this scenario, risk event has not occurred yet.

C: A contingency plan is a plan devised for a specific situation when things go wrong. Contingency plans are often devised by governments or businesses who want to be prepared for anything that could happen. Here there are no such plans.

D: Secondary risks are risks that come about as a result of implementing a risk response. But here in this scenario, risk event has not occurred yet.



There are five inputs to the quantitative risk analysis process. Which one of the following is NOT an input to quantitative risk analysis process?

  1. Risk management plan
  2. Enterprise environmental factors
  3. Cost management plan
  4. Risk register

Answer(s): B

Explanation:

Enterprise environmental factor is not an input to the quantitative risk analysis process. The five inputs to the perform quantitative risk analysis process are: risk register, risk management plan, cost management plan, schedule management plan, and organizational process assets.

Incorrect Answers:
A, C, D: These are the valid inputs to the perform quantitative risk analysis process.



Viewing Page 19 of 361



Share your comments for ISACA CRISC exam with other users:

Satish 11/6/2023 4:27:00 AM

it is very useful, thank you
Anonymous


Chinna 7/30/2023 8:37:00 AM

need safe rte dumps
FRANCE


1234 6/30/2023 3:40:00 AM

can you upload the cis - cpg dumps
Anonymous


Did 1/12/2024 3:01:00 AM

q6 = 1. download odt application 2. create a configuration file (xml) 3. setup.exe /download to download the installation files 4. setup.exe /configure to deploy the application
FRANCE


John 10/12/2023 12:30:00 PM

great material
Anonymous


Dinesh 8/1/2023 2:26:00 PM

could you please upload sap c_arsor_2302 questions? it will be very much helpful.
Anonymous


LBert 6/19/2023 10:23:00 AM

vraag 20c: rsa veilig voor symmtrische cryptografie? antwoord c is toch fout. rsa is voor asymmetrische cryptogafie??
NETHERLANDS


g 12/22/2023 1:51:00 PM

so far good
UNITED STATES


Milos 8/4/2023 9:33:00 AM

question 31 has obviously wrong answers. tls and ssl are used to encrypt data at transit, not at rest.
Serbia And Montenegro


Diksha 9/25/2023 2:32:00 AM

pls provide dump for 1z0-1080-23 planning exams
Anonymous


H 7/17/2023 4:28:00 AM

could you please upload the exam?
Anonymous


Anonymous 9/14/2023 4:47:00 AM

please upload this
UNITED STATES


Naveena 1/13/2024 9:55:00 AM

good material
Anonymous


WildWilly 1/19/2024 10:43:00 AM

lets see if this is good stuff...
Anonymous


Lavanya 11/2/2023 1:53:00 AM

useful information
UNITED STATES


Moussa 12/12/2023 5:52:00 AM

intéressant
BURKINA FASO


Madan 6/22/2023 9:22:00 AM

thank you for making the interactive questions
Anonymous


Vavz 11/2/2023 6:51:00 AM

questions are accurate
Anonymous


Su 11/23/2023 4:34:00 AM

i need questions/dumps for this exam.
Anonymous


LuvSN 7/16/2023 11:19:00 AM

i need this exam, when will it be uploaded
ROMANIA


Mihai 7/19/2023 12:03:00 PM

i need the dumps !
Anonymous


Wafa 11/13/2023 3:06:00 AM

very helpful
Anonymous


Alokit 7/3/2023 2:13:00 PM

good source
Anonymous


Show-Stopper 7/27/2022 11:19:00 PM

my 3rd test and passed on first try. hats off to this brain dumps site.
UNITED STATES


Michelle 6/23/2023 4:06:00 AM

please upload it
Anonymous


Lele 11/20/2023 11:55:00 AM

does anybody know if are these real exam questions?
EUROPEAN UNION


Girish Jain 10/9/2023 12:01:00 PM

are these questions similar to actual questions in the exam? because they seem to be too easy
Anonymous


Phil 12/8/2022 11:16:00 PM

i have a lot of experience but what comes in the exam is totally different from the practical day to day tasks. so i thought i would rather rely on these brain dumps rather failing the exam.
GERMANY


BV 6/8/2023 4:35:00 AM

good questions
NETHERLANDS


krishna 12/19/2023 2:05:00 AM

valied exam dumps. they were very helpful and i got a pretty good score. i am very grateful for this service and exam questions
Anonymous


Pie 9/3/2023 4:56:00 AM

will it help?
INDIA


Lucio 10/6/2023 1:45:00 PM

very useful to verify knowledge before exam
POLAND


Ajay 5/17/2023 4:54:00 AM

good stuffs
Anonymous


TestPD1 8/10/2023 12:19:00 PM

question 17 : responses arent b and c ?
EUROPEAN UNION