ISACA CRISC Exam (page: 16)
ISACA Certified in Risk and Information Systems Control
Updated on: 25-Dec-2025

Viewing Page 16 of 361

You are working with a vendor on your project. A stakeholder has requested a change for the project, which will add value to the project deliverables. The vendor that you're working with on the project will be affected by the change. What system can help you introduce and execute the stakeholder change request with the vendor?

  1. Contract change control system
  2. Scope change control system
  3. Cost change control system
  4. Schedule change control system

Answer(s): A

Explanation:

The contract change control system is part of the project's change control system. It addresses changes with the vendor that may affect the project contract. Change control system, a part of the configuration management system, is a collection of formal documented procedures that define how project deliverables and documentation will be controlled, changed, and approved.

Incorrect Answers:
B: The scope may change because of the stakeholder change request. Vendor’s relationship to the project, hence this choice is not the best answer.

C: The cost change control system manages changes to costs in the project. D: There is no indication that the change could affect the project schedule.



You are the project manager of GHT project. You are performing cost and benefit analysis of control. You come across the result that costs of specific controls exceed the benefits of mitigating a given risk. What is the BEST action would you choose in this scenario?

  1. The enterprise may apply the appropriate control anyway.
  2. The enterprise should adopt corrective control.
  3. The enterprise may choose to accept the risk rather than incur the cost of mitigation.
  4. The enterprise should exploit the risk.

Answer(s): C

Explanation:

If the costs of specific controls or countermeasures (control overhead) exceed the benefits of mitigating a given risk the enterprise may choose to accept the risk rather than incur the cost of mitigation. This is done according to the principle of proportionality described in:
Generally accepted security systems principles (GASSP) Generally accepted information security principles (GAISP)

Incorrect Answers:
A: When the cost of specific controls exceeds the benefits of mitigating a given risk, then controls are not applied, rather risk is being accepted.

B: As the cost of control exceeds the benefits of mitigating a given risk, hence no control should be applied. Corrective control is a type of control and hence it should not be adopted.

D: The risk is being exploited when there is an opportunity, i.e., the risk is positive. But here in this case, negative risk exists as it needs mitigation. So, exploitation cannot be done.



Mortality tables are based on what mathematical activity?
Each correct answer represents a complete solution. Choose three.

  1. Normal distributions
  2. Probabilities
  3. Impact
  4. Sampling

Answer(s): A,B,D

Explanation:

Probability identifies the chances that a particular event will happen under certain circumstances.

The variables provided are based on information gathered in real life. For situations with large numbers, a smaller set of participants are identified to represent the larger population. This represents a sample of the population. The points are mapped to identify their distribution.
Normal distribution refers to the theoretical plotting of points against the mathematical mean. The result of these activities provides a reasonable predictability for the mortality of the subject.

Incorrect Answers:
C: Impact is used to identify the magnitude of identified risks. The risk leads to some type of loss. However, instead of quantifying the loss as a dollar value, an impact assessment could use words such as Low, Medium, or High. Hence it is not mathematical.



Harry is the project manager of HDW project. He has identified a risk that could injure project team members. He does not want to accept any risk where someone could become injured on this project so he hires a professional vendor to complete this portion of the project work. What type of risk response is Harry implementing?

  1. Transference
  2. Mitigation
  3. Acceptance
  4. Avoidance

Answer(s): A

Explanation:

Risk transfer means that impact of risk is reduced by transferring or otherwise sharing a portion of the risk with an external organization or another internal entity. Transfer of risk can occur in many forms but is most effective when dealing with financial risks. Insurance is one form of risk transfer. Hence when Harry hires a professional vendor to manage that risk, the risk event does not go away but the responsibility for the event is transferred to the vendor.

Incorrect Answers:
B: Risk acceptance means that no action is taken relative to a particular risk; loss is accepted if it occurs. Here Harry is not accepting this risk event; he does not want anyone of his team to become injured so he's transferring the event to professional vendor.

C: Mitigation are actions that Harry's project team could take to reduce the probability and/or impact of a risk event.

D: Avoidance removes the risk event entirely either by adding additional steps to avoid the event or reducing the project scope.



The Identify Risk process determines the risks that affect the project and document their characteristics. Why should the project team members be involved in the Identify Risk process?

  1. They are the individuals that will most likely cause and respond to the risk events.
  2. They are the individuals that will have the best responses for identified risks events within the project.
  3. They are the individuals that are most affected by the risk events.
  4. They are the individuals that will need a sense of ownership and responsibility for the risk events.

Answer(s): D

Explanation:

The project team members should be involved in the risk identification so that they will develop a sense of ownership and responsibility for the risk events and the associated risk responses.

Identify Risks is the process of determining which risks may affect the project. It also documents risks' characteristics. The Identify Risks process is part of the Project Risk Management knowledge area. As new risks may evolve or become known as the project progresses through its life cycle, Identify Risks is an iterative process. The process should involve the project team so that they can develop and maintain a sense of ownership and responsibility for the risks and associated risk response actions. Risk Register is the only output of this process.

Incorrect Answers:
A, B, C: These are not the valid answers for this question.



Viewing Page 16 of 361



Share your comments for ISACA CRISC exam with other users:

Steve 8/17/2023 2:19:00 PM

question #18s answer should be a, not d. this should be corrected. it should be minvalidityperiod
CANADA


RITEISH 12/24/2023 4:33:00 AM

thanks for the exact solution
Anonymous


SB 10/15/2023 7:58:00 AM

need to refer the questions and have to give the exam
INDIA


Mike Derfalem 7/16/2023 7:59:00 PM

i need it right now if it was possible please
Anonymous


Isak 7/6/2023 3:21:00 AM

i need it very much please share it in the fastest time.
Anonymous


Maria 6/23/2023 11:40:00 AM

correct answer is d for student.java program
IRELAND


Nagendra Pedipina 7/12/2023 9:10:00 AM

q:37 c is correct
INDIA


John 9/16/2023 9:37:00 PM

q6 exam topic: terramearth, c: correct answer: copy 1petabyte to encrypted usb device ???
GERMANY


SAM 12/4/2023 12:56:00 AM

explained answers
INDIA


Andy 12/26/2023 9:35:00 PM

plan to take theaws certified developer - associate dva-c02 in the next few weeks
SINGAPORE


siva 5/17/2023 12:32:00 AM

very helpfull
Anonymous


mouna 9/27/2023 8:53:00 AM

good questions
Anonymous


Bhavya 9/12/2023 7:18:00 AM

help to practice csa exam
Anonymous


Malik 9/28/2023 1:09:00 PM

nice tip and well documented
Anonymous


rodrigo 6/22/2023 7:55:00 AM

i need the exam
Anonymous


Dan 6/29/2023 1:53:00 PM

please upload
Anonymous


Ale M 11/22/2023 6:38:00 PM

prepping for fsc exam
AUSTRALIA


ahmad hassan 9/6/2023 3:26:00 AM

pd1 with great experience
Anonymous


Žarko 9/5/2023 3:35:00 AM

@t it seems like azure service bus message quesues could be the best solution
UNITED KINGDOM


Shiji 10/15/2023 1:08:00 PM

helpful to check your understanding.
INDIA


Da Costa 8/27/2023 11:43:00 AM

question 128 the answer should be static not auto
Anonymous


bot 7/26/2023 6:45:00 PM

more comments here
UNITED STATES


Kaleemullah 12/31/2023 1:35:00 AM

great support to appear for exams
Anonymous


Bsmaind 8/20/2023 9:26:00 AM

useful dumps
Anonymous


Blessious Phiri 8/13/2023 8:37:00 AM

making progress
Anonymous


Nabla 9/17/2023 10:20:00 AM

q31 answer should be d i think
FRANCE


vladputin 7/20/2023 5:00:00 AM

is this real?
UNITED STATES


Nick W 9/29/2023 7:32:00 AM

q10: c and f are also true. q11: this is outdated. you no longer need ownership on a pipe to operate it
Anonymous


Naveed 8/28/2023 2:48:00 AM

good questions with simple explanation
UNITED STATES


cert 9/24/2023 4:53:00 PM

admin guide (windows) respond to malicious causality chains. when the cortex xdr agent identifies a remote network connection that attempts to perform malicious activity—such as encrypting endpoint files—the agent can automatically block the ip address to close all existing communication and block new connections from this ip address to the endpoint. when cortex xdrblocks an ip address per endpoint, that address remains blocked throughout all agent profiles and policies, including any host-firewall policy rules. you can view the list of all blocked ip addresses per endpoint from the action center, as well as unblock them to re-enable communication as appropriate. this module is supported with cortex xdr agent 7.3.0 and later. select the action mode to take when the cortex xdr agent detects remote malicious causality chains: enabled (default)—terminate connection and block ip address of the remote connection. disabled—do not block remote ip addresses. to allow specific and known s
Anonymous


Yves 8/29/2023 8:46:00 PM

very inciting
Anonymous


Miguel 10/16/2023 11:18:00 AM

question 5, it seems a instead of d, because: - care plan = case - patient = person account - product = product2;
SPAIN


Byset 9/25/2023 12:49:00 AM

it look like real one
Anonymous


Debabrata Das 8/28/2023 8:42:00 AM

i am taking oracle fcc certification test next two days, pls share question dumps
Anonymous