ISACA Certified in Risk and Information Systems Control CRISC Dumps in PDF

Free ISACA CRISC Real Questions (page: 16)

You are working with a vendor on your project. A stakeholder has requested a change for the project, which will add value to the project deliverables. The vendor that you're working with on the project will be affected by the change. What system can help you introduce and execute the stakeholder change request with the vendor?

  1. Contract change control system
  2. Scope change control system
  3. Cost change control system
  4. Schedule change control system

Answer(s): A

Explanation:

The contract change control system is part of the project's change control system. It addresses changes with the vendor that may affect the project contract. Change control system, a part of the configuration management system, is a collection of formal documented procedures that define how project deliverables and documentation will be controlled, changed, and approved.

Incorrect Answers:
B: The scope may change because of the stakeholder change request. Vendor’s relationship to the project, hence this choice is not the best answer.

C: The cost change control system manages changes to costs in the project. D: There is no indication that the change could affect the project schedule.



You are the project manager of GHT project. You are performing cost and benefit analysis of control. You come across the result that costs of specific controls exceed the benefits of mitigating a given risk. What is the BEST action would you choose in this scenario?

  1. The enterprise may apply the appropriate control anyway.
  2. The enterprise should adopt corrective control.
  3. The enterprise may choose to accept the risk rather than incur the cost of mitigation.
  4. The enterprise should exploit the risk.

Answer(s): C

Explanation:

If the costs of specific controls or countermeasures (control overhead) exceed the benefits of mitigating a given risk the enterprise may choose to accept the risk rather than incur the cost of mitigation. This is done according to the principle of proportionality described in:
Generally accepted security systems principles (GASSP) Generally accepted information security principles (GAISP)

Incorrect Answers:
A: When the cost of specific controls exceeds the benefits of mitigating a given risk, then controls are not applied, rather risk is being accepted.

B: As the cost of control exceeds the benefits of mitigating a given risk, hence no control should be applied. Corrective control is a type of control and hence it should not be adopted.

D: The risk is being exploited when there is an opportunity, i.e., the risk is positive. But here in this case, negative risk exists as it needs mitigation. So, exploitation cannot be done.



Mortality tables are based on what mathematical activity?
Each correct answer represents a complete solution. Choose three.

  1. Normal distributions
  2. Probabilities
  3. Impact
  4. Sampling

Answer(s): A,B,D

Explanation:

Probability identifies the chances that a particular event will happen under certain circumstances.

The variables provided are based on information gathered in real life. For situations with large numbers, a smaller set of participants are identified to represent the larger population. This represents a sample of the population. The points are mapped to identify their distribution.
Normal distribution refers to the theoretical plotting of points against the mathematical mean. The result of these activities provides a reasonable predictability for the mortality of the subject.

Incorrect Answers:
C: Impact is used to identify the magnitude of identified risks. The risk leads to some type of loss. However, instead of quantifying the loss as a dollar value, an impact assessment could use words such as Low, Medium, or High. Hence it is not mathematical.



Harry is the project manager of HDW project. He has identified a risk that could injure project team members. He does not want to accept any risk where someone could become injured on this project so he hires a professional vendor to complete this portion of the project work. What type of risk response is Harry implementing?

  1. Transference
  2. Mitigation
  3. Acceptance
  4. Avoidance

Answer(s): A

Explanation:

Risk transfer means that impact of risk is reduced by transferring or otherwise sharing a portion of the risk with an external organization or another internal entity. Transfer of risk can occur in many forms but is most effective when dealing with financial risks. Insurance is one form of risk transfer. Hence when Harry hires a professional vendor to manage that risk, the risk event does not go away but the responsibility for the event is transferred to the vendor.

Incorrect Answers:
B: Risk acceptance means that no action is taken relative to a particular risk; loss is accepted if it occurs. Here Harry is not accepting this risk event; he does not want anyone of his team to become injured so he's transferring the event to professional vendor.

C: Mitigation are actions that Harry's project team could take to reduce the probability and/or impact of a risk event.

D: Avoidance removes the risk event entirely either by adding additional steps to avoid the event or reducing the project scope.



The Identify Risk process determines the risks that affect the project and document their characteristics. Why should the project team members be involved in the Identify Risk process?

  1. They are the individuals that will most likely cause and respond to the risk events.
  2. They are the individuals that will have the best responses for identified risks events within the project.
  3. They are the individuals that are most affected by the risk events.
  4. They are the individuals that will need a sense of ownership and responsibility for the risk events.

Answer(s): D

Explanation:

The project team members should be involved in the risk identification so that they will develop a sense of ownership and responsibility for the risk events and the associated risk responses.

Identify Risks is the process of determining which risks may affect the project. It also documents risks' characteristics. The Identify Risks process is part of the Project Risk Management knowledge area. As new risks may evolve or become known as the project progresses through its life cycle, Identify Risks is an iterative process. The process should involve the project team so that they can develop and maintain a sense of ownership and responsibility for the risks and associated risk response actions. Risk Register is the only output of this process.

Incorrect Answers:
A, B, C: These are not the valid answers for this question.



Share your comments for ISACA CRISC exam with other users:

J
Jas
10/25/2023 6:01:00 PM

165 should be apt

N
Neetu
6/22/2023 8:41:00 AM

please upload the dumps, real need of them

M
Mark
10/24/2023 1:34:00 AM

any recent feeedback?

G
Gopinadh
8/9/2023 4:05:00 AM

question number 2 is indicating you are giving proper questions. observe and change properly.

S
Santhi
1/1/2024 8:23:00 AM

passed today.40% questions were new.litwere case study,lots of new questions on afd,ratelimit,tm,lb,app gatway.got 2 set series of questions which are not present here.questions on azure cyclecloud, no.of vnet/vms required for implimentation,blueprints assignment/management group etc

R
Raviraj Magadum
1/12/2024 11:39:00 AM

practice test

S
sivaramakrishnan
7/27/2023 8:12:00 AM

want the dumps for emc content management server programming(cmsp)

A
Aderonke
10/23/2023 1:52:00 PM

brilliant and helpful

A
Az
9/16/2023 2:43:00 PM

q75. azure files is pass

K
ketty
11/9/2023 8:10:00 AM

very helpful

S
Sonail
5/2/2022 1:36:00 PM

thank you for these questions. it helped a lot.

S
Shariq
7/28/2023 8:00:00 AM

how do i get the h12-724 dumps

A
adi
10/30/2023 11:51:00 PM

nice data dumps

E
EDITH NCUBE
7/25/2023 7:28:00 AM

answers are correct

R
Raja
6/20/2023 4:38:00 AM

good explanation

B
BigMouthDog
1/22/2022 8:17:00 PM

hi team just want to know if there is any update version of the exam 350-401

F
francesco
10/30/2023 11:08:00 AM

helpful on 2017 scrum guide

A
Amitabha Roy
10/5/2023 3:16:00 AM

planning to attempt for the exam.

P
Prem Yadav
7/29/2023 6:20:00 AM

pleaseee upload

A
Ahmed Hashi
7/6/2023 5:40:00 PM

thanks ly so i have information cia

M
mansi
5/31/2023 7:58:00 AM

hello team, i need sap qm dumps for practice

J
Jamil aljamil
12/4/2023 4:47:00 AM

it’s good but not senatios based

C
Cath
10/10/2023 10:19:00 AM

q.119 - the correct answer is b - they are not captured in an update set as theyre data.

P
P
1/6/2024 11:22:00 AM

good matter

S
surya
7/30/2023 2:02:00 PM

please upload c_sacp_2308

S
Sasuke
7/11/2023 10:30:00 PM

please upload the dump. thanks very much !!

V
V
7/4/2023 8:57:00 AM

good questions

T
TTB
8/22/2023 5:30:00 AM

hi, could you please update the latest dump version

T
T
7/28/2023 9:06:00 PM

this question is keep repeat : you are developing a sales application that will contain several azure cloud services and handle different components of a transaction. different cloud services will process customer orders, billing, payment, inventory, and shipping. you need to recommend a solution to enable the cloud services to asynchronously communicate transaction information by using xml messages. what should you include in the recommendation?

G
Gurgaon
9/28/2023 4:35:00 AM

great questions

W
wasif
10/11/2023 2:22:00 AM

its realy good

S
Shubhra Rathi
8/26/2023 1:12:00 PM

oracle 1z0-1059-22 dumps

L
Leo
7/29/2023 8:48:00 AM

please share me the pdf..

A
AbedRabbou Alaqabna
12/18/2023 3:10:00 AM

q50: which two functions can be used by an end user when pivoting an interactive report? the correct answer is a, c because we do not have rank in the function pivoting you can check in the apex app

AI Tutor 👋 I’m here to help!