The average labor cost per unit for the first batch produced by a new process is US $120. The cumulative average labor cost after the second batch is US $72 per product. Using a batch size of 100 and assuming the learning curve continues, the total labor cost of four batches will be:

  1. US $4,320
  2. US $10,368
  3. US $2,592
  4. US $17,280

Answer(s): D

Explanation:

The learning curve reflects the increased rate at which people perform tasks as they gain experience. The time required to perform a given task becomes progressively shorter.
Ordinarily, the curve is expressed in a percentage of reduced time to complete a task for each doubling of cumulative production. One common assumption in a learning curve model is that the cumulative average time and labor cost) per unit is reduced by a certain percentage each time production doubles. Given a US $120 cost per unit for the first 100 units and a US $72 cost per unit when cumulative production doubled to 200 units, the learning curve percentage must be 60% US $72 - $120). If production is again doubled to 400 units four batches), the average unit labor cost should be US $43.20 $72 x 60%). Hence, total labor cost for 400 units is estimated to be US $17,280 400 $43.20).



A plumbing company, a wholesale distributor, supplies plumbing contractors and retailers throughout the Northeast on a next-day delivery. basis. The company has a centrally located warehouse to accept receipts of plumbing supplies. The warehouse has a single dock to accept and unload railroad freight cars during the night. It takes 5 hours to unload each freight car. The company's prior records indicate that the number of freight cars that arrive in the course of a night range from zero to five or mare, with no indicated pattern of arrivals. If more than two freight cars arrive on the same night, some freight must be held until the next dad{ for unloading. The company wants to estimate the wait time when more than two freight cars arrive in the same night. The appropriate technique to analyze the arrival of freight cars is

  1. Integer programming.
  2. Linear programming.
  3. Monte Carlo simulation.
  4. Regression analysis.

Answer(s): C

Explanation:

The Monte Carlo simulation method is often used to generate the individual values for a random variable. The performance of a quantitative model under uncertainty may be investigated by randomly selecting values for each variable in the model based on the probability distribution of each variable) and then calculating the value of the solution. If this process is performed many times, the distribution of results from the model will be obtained.



Through the use of decision models, managers thoroughly analyze many alternatives and decide on the best alternative for the company. Often the actual results achieved from a particular decision are not what was expected when the decision was made. In addition, an alternative that was not selected would have actually been the best decision for the company.
The appropriate technique to analyze the alternatives by using expected inputs and altering them before a decision is made is:

  1. Expected value analysis.
  2. Linear programming.
  3. Program evaluation review technique PERT
  4. Sensitivity analysis.

Answer(s): D

Explanation:

Sensitivity modeling can be used to determine the outcome of a variety of decisions. A trial and- error method may be adopted, usually in a computer model, to calculate the sensitivity of the solution variability of outcomes) to changes in a variable.



A firm is attempting to estimate the reserves for doubtful accounts. The probabilities of these doubtful accounts follow a transition process over time. They evolve from their starting value to a changed value. As such, the most effective technique to analyze the problem is:

  1. Markov chain analysis.
  2. Econometric theory.
  3. Monte Carlo analysis.
  4. Dynamic programming.

Answer(s): A

Explanation:

A Markov chain is a series of events in which the probability of an event depends on the immediately preceding event. An example is the game of blackjack in which the probability of certain cards being dealt is dependent upon what cards have already been dealt. In the analysis of bad debts, preceding events, such as collections, credit policy changes, and write offs, affect the probabilities of future losses.



A company has several departments that conduct technical studies and prepare reports for clients. Recently, there have been long delays in having these reports copied at the company's centralized copy center because of the dramatic increase in business. !Management is considering decentralizing copy services to reduce the turnaround and provide clients with timely reports. An appropriate technique for minimizing turnaround time and the cost of providing copy services is:

  1. Queuing theory.
  2. Linear programming.
  3. Regression analysis.
  4. Game theory.

Answer(s): A

Explanation:

Two basic costs are involved in queuing waiting-line) models: I) the cost of providing service including facility costs and operating costs), and 2) the cost of idle resources waiting in line. The latter II may be a direct cost if paid employees are waiting, or an opportunity cost in the case of waiting customers. The objective of queuing theory is to minimize the total cost of the system, including both service and waiting costs, for a given rate of arrivals. This minimization occurs at the point at which cost of waiting is balanced by the cost of providing service. This company wishes to reduce the total of waiting costs turnaround time) and the cost of copy services.



Share your comments for IIA IIA-CIA-Part3 exam with other users:

I
indira m
8/14/2023 12:15:00 PM

please provide the pdf

R
ribrahim
8/1/2023 6:05:00 AM

hey guys, just to let you all know that i cleared my 312-38 today within 1 hr with 100 questions and passed. thank you so much brain-dumps.net all the questions that ive studied in this dump came out exactly the same word for word "verbatim". you rock brain-dumps.net!!! section name total score gained score network perimeter protection 16 11 incident response 10 8 enterprise virtual, cloud, and wireless network protection 12 8 application and data protection 13 10 network défense management 10 9 endpoint protection 15 12 incident d

A
Andrew
8/23/2023 6:02:00 PM

very helpful

L
latha
9/7/2023 8:14:00 AM

useful questions

I
ibrahim
11/9/2023 7:57:00 AM

page :20 https://exam-dumps.com/snowflake/free-cof-c02-braindumps.html?p=20#collapse_453 q 74: true or false: pipes can be suspended and resumed. true. desc.: pausing or resuming pipes in addition to the pipe owner, a role that has the following minimum permissions can pause or resume the pipe https://docs.snowflake.com/en/user-guide/data-load-snowpipe-intro

F
Franklin Allagoa
7/5/2023 5:16:00 AM

i want hcia exam dumps

S
SSA
12/24/2023 1:18:00 PM

good training

B
BK
8/11/2023 12:23:00 PM

very useful

D
Deepika Narayanan
7/13/2023 11:05:00 PM

yes need this exam dumps

B
Blessious Phiri
8/15/2023 3:31:00 PM

these questions are a great eye opener

J
Jagdesh
9/8/2023 8:17:00 AM

thank you for providing these questions and answers. they helped me pass my exam. you guys are great.

T
TS
7/18/2023 3:32:00 PM

good knowledge

A
Asad Khan
11/1/2023 2:44:00 AM

answer 10 should be a because only a new project will be created & the organization is the same.

R
Raj
9/12/2023 3:49:00 PM

can you please upload the dump again

C
Christian Klein
6/23/2023 1:32:00 PM

is it legit questions from sap certifications ?

A
anonymous
1/12/2024 3:34:00 PM

question 16 should be b (changing the connector settings on the monitor) pc and monitor were powered on. the lights on the pc are on indicating power. the monitor is showing an error text indicating that it is receiving power too. this is a clear sign of having the wrong input selected on the monitor. thus, the "connector setting" needs to be switched from hdmi to display port on the monitor so it receives the signal from the pc, or the other way around (display port to hdmi).

N
NSPK
1/18/2024 10:26:00 AM

q 10. ans is d (in the target org: open deployment settings, click edit next to the source org. select allow inbound changes and save

M
mohamed abdo
9/1/2023 4:59:00 AM

very useful

T
Tom
3/18/2022 8:00:00 PM

i purchased this exam dumps from another website with way more questions but they were all invalid and outdate. this exam dumps was right to the point and all from recent exam. it was a hard pass.

E
Edrick GOP
10/24/2023 6:00:00 AM

it was a good experience and i got 90% in the 200-901 exam.

A
anonymous
8/10/2023 2:28:00 AM

hi please upload this

B
Bakir
7/6/2023 7:24:00 AM

please upload it

A
Aman
6/18/2023 1:27:00 PM

really need this dump. can you please help.

N
Neela Para
1/8/2024 6:39:00 PM

really good and covers many areas explaining the answer.

K
Karan Patel
8/15/2023 12:51:00 AM

yes, can you please upload the exam?

N
NISHAD
11/7/2023 11:28:00 AM

how many questions are there in these dumps?

P
Pankaj
7/3/2023 3:57:00 AM

hi team, please upload this , i need it.

D
DN
9/4/2023 11:19:00 PM

question 14 - run terraform import: this is the recommended best practice for bringing manually created or destroyed resources under terraform management. you use terraform import to associate an existing resource with a terraform resource configuration. this ensures that terraform is aware of the resource, and you can subsequently manage it with terraform.

Z
Zhiguang
8/19/2023 11:37:00 PM

please upload dump. thanks in advance.

D
deedee
12/23/2023 5:51:00 PM

great great

A
Asad Khan
11/1/2023 3:10:00 AM

answer 16 should be b your organizational policies require you to use virtual machines directly

S
Sale Danasabe
10/24/2023 5:21:00 PM

the question are kind of tricky of you didnt get the hnag on it.

L
Luis
11/16/2023 1:39:00 PM

can anyone tell me if this is for rhel8 or rhel9?

H
hik
1/19/2024 1:47:00 PM

good content

AI Tutor 👋 I’m here to help!