The average labor cost per unit for the first batch produced by a new process is US $120. The cumulative average labor cost after the second batch is US $72 per product. Using a batch size of 100 and assuming the learning curve continues, the total labor cost of four batches will be:

  1. US$4,320
  2. US$10,368
  3. US$2,592
  4. US$17,280

Answer(s): D

Explanation:

The learning curve reflects the increased rate at which people perform tasks as they gain experience. The time required to perform a given task becomes progressively shorter. Ordinarily, the curve is expressed in a percentage of reduced time to complete a task for each doubling of cumulative production. One common assumption in a learning curve model is that the cumulative average time (and labor cost) per unit is reduced by a certain percentage each time production doubles. Given a US $120 cost per unit for the first 100 units and a US $72 cost per unit when cumulative production doubled to 200 units, the learning curve percentage must be 60% (US $72 + $120). If production is again doubled to 400 units (four batches), the average unit labor cost should be US $43.20 ($72 x 60%). Hence, total labor cost for 400 units is estimated to be US $17,280 (400 units x $43.20).



CORRECT TEXT
Simulation, a widely used technique in decision modeling, is a(n):

  1. Process of modeling whereby real activities are represented in mathematical or other form.
  2. Technique used to pinpoint random deviations in industrial processes and other repetitive operations.
  3. Technique used to separate costs into fixed and variable portions.
  4. Inventory management model that is used to calculate the optimum order quantity.

Answer(s): A

Explanation:

Computer simulation is used when an optimization model cannot be developed, e.g., because the variables exceed the equations describing them. Simulation involves constructing a mathematical/logical model incorporating most of the features of the problem. This model is tested in a variety of hypothetical situations, and the modeled responses can then be measured.



An account executive has just designed a Monte Carlo model to estimate the costs of a particular type of project. Validating the model could include all except:

  1. Checking for errors in the computer programming.
  2. Checking that assumed probability distributions are reasonable.
  3. Comparing test results with previously validated models.
  4. Applying the model.

Answer(s): D

Explanation:

The Monte Carlo technique is used in a simulation to generate the individual values for a random value. An essential step in the simulation procedure is to validate the mathematical model used. This process involves not only searching for errors but also verifying the assumptions. It also should provide some assurance that the results of the experiment will be realistic. This assurance is often obtained using historical data. If the model gives results equivalent to what actually happened, the model is historically valid. There is still some risk, however, that changes could make the model invalid for the future. The model should not be implemented until this validation process is complete.



Which of the following is not true about simu-lation models that use Monte Carlo processes?

  1. They are deterministic in nature.
  2. They may involve sampling.
  3. They mathematically estimate what actual performance would be.
  4. They emulate stochastic systems.

Answer(s): A

Explanation:

The Monte Carlo simulation is often used in computer modeling to generate the individual values for a random variable. The performance of a quantitative model under uncertainty may be investigated by randomly selecting values for each variable in the model (based on the probability distribution of each variable) and then calculating the value of the solution. Because Monte Carlo processes use the laws of probability to generate values for random variables, simulations using them are probabilistic, not deterministic.



The sales manager for a builder of custom yachts developed the following conditional table for annual production and sales:



According to the table, how many yachts should be built?

  1. 10
  2. 20
  3. 30
  4. 50

Answer(s): C

Explanation:

To achieve the maximum expected profit. 30 yachts should be built. For each level of production, multiply the probability of demand by the expected profit. The computation for the maximum is: 0.1 (-US $10) + 0.2($10) + 0.5($30) + 0.2($30) = US $22.



Share your comments for IIA IIA-CIA-Part3 exam with other users:

A
Arun
9/20/2023 4:52:00 PM

nice and helpful questions

J
Joseph J
7/11/2023 2:53:00 PM

i found the questions helpful

M
Meg
10/12/2023 8:02:00 AM

q 105 . ans is d

N
Navaneeth S
7/14/2023 7:57:00 AM

i have interest to get a sybase iq dba certification

A
Aish
10/11/2023 5:27:00 AM

want to pass exm.

A
Anonymous
6/12/2023 7:23:00 AM

are the answers correct?

K
Kris
7/7/2023 9:43:00 AM

good morning, could you please upload this exam again, i need it to test my knowledge in sd-wan with version 7.0.

M
Meghraj mali
10/7/2023 1:47:00 PM

very nice question

N
Noel
11/1/2022 9:14:00 PM

i have learning disability and this exam dumps allowed me to focus on the actual questions and not worry about notes and the those other study materials.

J
Jas
10/25/2023 6:01:00 PM

165 should be apt

N
Neetu
6/22/2023 8:41:00 AM

please upload the dumps, real need of them

M
Mark
10/24/2023 1:34:00 AM

any recent feeedback?

G
Gopinadh
8/9/2023 4:05:00 AM

question number 2 is indicating you are giving proper questions. observe and change properly.

S
Santhi
1/1/2024 8:23:00 AM

passed today.40% questions were new.litwere case study,lots of new questions on afd,ratelimit,tm,lb,app gatway.got 2 set series of questions which are not present here.questions on azure cyclecloud, no.of vnet/vms required for implimentation,blueprints assignment/management group etc

R
Raviraj Magadum
1/12/2024 11:39:00 AM

practice test

S
sivaramakrishnan
7/27/2023 8:12:00 AM

want the dumps for emc content management server programming(cmsp)

A
Aderonke
10/23/2023 1:52:00 PM

brilliant and helpful

A
Az
9/16/2023 2:43:00 PM

q75. azure files is pass

K
ketty
11/9/2023 8:10:00 AM

very helpful

S
Sonail
5/2/2022 1:36:00 PM

thank you for these questions. it helped a lot.

S
Shariq
7/28/2023 8:00:00 AM

how do i get the h12-724 dumps

A
adi
10/30/2023 11:51:00 PM

nice data dumps

E
EDITH NCUBE
7/25/2023 7:28:00 AM

answers are correct

R
Raja
6/20/2023 4:38:00 AM

good explanation

B
BigMouthDog
1/22/2022 8:17:00 PM

hi team just want to know if there is any update version of the exam 350-401

F
francesco
10/30/2023 11:08:00 AM

helpful on 2017 scrum guide

A
Amitabha Roy
10/5/2023 3:16:00 AM

planning to attempt for the exam.

P
Prem Yadav
7/29/2023 6:20:00 AM

pleaseee upload

A
Ahmed Hashi
7/6/2023 5:40:00 PM

thanks ly so i have information cia

M
mansi
5/31/2023 7:58:00 AM

hello team, i need sap qm dumps for practice

J
Jamil aljamil
12/4/2023 4:47:00 AM

it’s good but not senatios based

C
Cath
10/10/2023 10:19:00 AM

q.119 - the correct answer is b - they are not captured in an update set as theyre data.

P
P
1/6/2024 11:22:00 AM

good matter

S
surya
7/30/2023 2:02:00 PM

please upload c_sacp_2308

AI Tutor 👋 I’m here to help!