The following information and diagram apply to a project:The earliest completion time for the project is:
Answer(s): C
The two paths through the network are A-C-E 5 + 4 + 6 = 15 days) and B-D-E 3 +2 + 6 = 11 days). The critical or longest path is thus A-C-E. Hence, the earliest completion time is 15 days.
Which of the following terms is not used in project management?
Answer(s): D
Project management concerns managing teams assigned to special projects. Lumpy demand refers to periodic demand for a product or service that increases in large, lumpy increments.
Activity scheduling information for the installation of a new computer system is given belowThe earliest completion time for the project is:
The critical path is the longest path because it defines the minimum duration of the project.A-D-E 4 + 6 + 5 = 15) is the critical path.
In a critical path analysis, if slack time in an activity exists, the activity:
Slack is the free time associated with each activity. In other words, paths that are not critical have slack time. Slack represents unused resources that can be diverted to the critical path.
The primary difference between PERT and CPM is that:
Both PERT and CPM are network analysis techniques. But CPM was developed independently of PERT and is widely used in the construction industry. CPM may be thought of as a subset of PERT. Like PERT, it is a network technique, but, unlike PERT, it uses deterministic time and cost estimates. Its advantages include cost estimates plus the concept of "crash" efforts and costs. Activity times are estimated for normal effort and crash effort. Crash time is the time to complete an activity assuming that all available resources were devoted to the task overtime, extra crew, etc.). Activity costs are also estimated for normal and crash efforts. These estimates allow the project manager to estimate the costs of completing the project if some of the activities are completed on a crash basis. The network diagram is constructed in the same manner as PERT diagrams. Once the diagram is constructed, the critical paths are found for normal and crash times. More than one critical path may exist for each diagram.
Share your comments for IIA IIA-CIA-PART3-3P exam with other users:
good morning, could you please upload this exam again,
hi can you please upload the dumps for sap contingent module. thanks
good questions
looking forward to the real exam
good ones for exam preparation
this is a good experience
hi everyone
waiting for the dump. please upload.
upload cks exam questions
awesome training material
where is dump
q. 289 - the correct answer should be b not d, since the question asks for the most secure way to provide access to a s3 bucket (a single one), and by principle of the least privilege you should not be giving access to all buckets.
please i need if possible h12-831,
good collection of questions and solution for pl500 certification
i would like to appear the exam.
i am very happy as i cleared my comptia a+ 220-1101 exam. i studied from as it has all exam dumps and mock tests available. i got 91% on the test.
need this dump
its really good to eventuate knowledge before appearing for the actual exam.
this is great
please i want the questions to pass the exam
i need to pass exam
great, i appreciate it.
please could you upload (isc)2 certified in cybersecurity (cc) exam questions
good questions, wrong answers
im preparing for exams
question no: 42 isnt azure vm an iaas solution? so, shouldnt the answer be "no"?
im study azure
i need this now
i took the aws saa-c03 test and scored 935/1000. it has all the exam dumps and important info.
well explained
i got the full version and it helped me pass the exam. pdf version is very good.
provide the download link, please
please upload thank.