The following information and diagram apply to a project:



The earliest completion time for the project is:

  1. 11 days.
  2. 14 days.
  3. 15 days.
  4. 20 days.

Answer(s): C

Explanation:

The two paths through the network are A-C-E 5 + 4 + 6 = 15 days) and B-D-E 3 +2 + 6 = 11 days). The critical or longest path is thus A-C-E. Hence, the earliest completion time is 15 days.



Which of the following terms is not used in project management?

  1. Dummy activity.
  2. Latest finish.
  3. Optimistic time.
  4. Lumpy demand.

Answer(s): D

Explanation:

Project management concerns managing teams assigned to special projects. Lumpy demand refers to periodic demand for a product or service that increases in large, lumpy increments.



Activity scheduling information for the installation of a new computer system is given below



The earliest completion time for the project is:

  1. A-C.
  2. B-E.
  3. A-D-E.
  4. B-D-C.

Answer(s): C

Explanation:

The critical path is the longest path because it defines the minimum duration of the project.
A-D-E 4 + 6 + 5 = 15) is the critical path.



In a critical path analysis, if slack time in an activity exists, the activity:

  1. Is not essential to the overall project.
  2. Is a backup activity to replace a main activity should it fail.
  3. Could be delayed without delaying the overall project.
  4. Involves essentially no time to complete.

Answer(s): C

Explanation:

Slack is the free time associated with each activity. In other words, paths that are not critical have slack time. Slack represents unused resources that can be diverted to the critical path.



The primary difference between PERT and CPM is that:

  1. CPM uses probabilities on the activity times and PERT does not.
  2. PERT considers activity costs and CPM does not.
  3. PERT can assign probabilities to activity times and CPM does not.
  4. CPM considers activity costs and PERT does not.

Answer(s): D

Explanation:

Both PERT and CPM are network analysis techniques. But CPM was developed independently of PERT and is widely used in the construction industry. CPM may be thought of as a subset of PERT. Like PERT, it is a network technique, but, unlike PERT, it uses deterministic time and cost estimates. Its advantages include cost estimates plus the concept of "crash" efforts and costs. Activity times are estimated for normal effort and crash effort. Crash time is the time to complete an activity assuming that all available resources were devoted to the task overtime, extra crew, etc.). Activity costs are also estimated for normal and crash efforts. These estimates allow the project manager to estimate the costs of completing the project if some of the activities are completed on a crash basis. The network diagram is constructed in the same manner as PERT diagrams. Once the diagram is constructed, the critical paths are found for normal and crash times. More than one critical path may exist for each diagram.



Share your comments for IIA IIA-CIA-PART3-3P exam with other users:

K
Khalid Javid
11/17/2023 3:46:00 PM

kindly share the dump

N
Na
8/9/2023 8:39:00 AM

could you please upload cfe fraud prevention and deterrence questions? it will be very much helpful.

S
shime
10/23/2023 10:03:00 AM

this is really very very helpful for mcd level 1

V
Vnu
6/3/2023 2:39:00 AM

very helpful!

S
Steve
8/17/2023 2:19:00 PM

question #18s answer should be a, not d. this should be corrected. it should be minvalidityperiod

R
RITEISH
12/24/2023 4:33:00 AM

thanks for the exact solution

S
SB
10/15/2023 7:58:00 AM

need to refer the questions and have to give the exam

M
Mike Derfalem
7/16/2023 7:59:00 PM

i need it right now if it was possible please

I
Isak
7/6/2023 3:21:00 AM

i need it very much please share it in the fastest time.

M
Maria
6/23/2023 11:40:00 AM

correct answer is d for student.java program

N
Nagendra Pedipina
7/12/2023 9:10:00 AM

q:37 c is correct

J
John
9/16/2023 9:37:00 PM

q6 exam topic: terramearth, c: correct answer: copy 1petabyte to encrypted usb device ???

S
SAM
12/4/2023 12:56:00 AM

explained answers

A
Andy
12/26/2023 9:35:00 PM

plan to take theaws certified developer - associate dva-c02 in the next few weeks

S
siva
5/17/2023 12:32:00 AM

very helpfull

M
mouna
9/27/2023 8:53:00 AM

good questions

B
Bhavya
9/12/2023 7:18:00 AM

help to practice csa exam

M
Malik
9/28/2023 1:09:00 PM

nice tip and well documented

R
rodrigo
6/22/2023 7:55:00 AM

i need the exam

D
Dan
6/29/2023 1:53:00 PM

please upload

A
Ale M
11/22/2023 6:38:00 PM

prepping for fsc exam

A
ahmad hassan
9/6/2023 3:26:00 AM

pd1 with great experience

Ž
Žarko
9/5/2023 3:35:00 AM

@t it seems like azure service bus message quesues could be the best solution

S
Shiji
10/15/2023 1:08:00 PM

helpful to check your understanding.

D
Da Costa
8/27/2023 11:43:00 AM

question 128 the answer should be static not auto

B
bot
7/26/2023 6:45:00 PM

more comments here

K
Kaleemullah
12/31/2023 1:35:00 AM

great support to appear for exams

B
Bsmaind
8/20/2023 9:26:00 AM

useful dumps

B
Blessious Phiri
8/13/2023 8:37:00 AM

making progress

N
Nabla
9/17/2023 10:20:00 AM

q31 answer should be d i think

V
vladputin
7/20/2023 5:00:00 AM

is this real?

N
Nick W
9/29/2023 7:32:00 AM

q10: c and f are also true. q11: this is outdated. you no longer need ownership on a pipe to operate it

N
Naveed
8/28/2023 2:48:00 AM

good questions with simple explanation

C
cert
9/24/2023 4:53:00 PM

admin guide (windows) respond to malicious causality chains. when the cortex xdr agent identifies a remote network connection that attempts to perform malicious activity—such as encrypting endpoint files—the agent can automatically block the ip address to close all existing communication and block new connections from this ip address to the endpoint. when cortex xdrblocks an ip address per endpoint, that address remains blocked throughout all agent profiles and policies, including any host-firewall policy rules. you can view the list of all blocked ip addresses per endpoint from the action center, as well as unblock them to re-enable communication as appropriate. this module is supported with cortex xdr agent 7.3.0 and later. select the action mode to take when the cortex xdr agent detects remote malicious causality chains: enabled (default)—terminate connection and block ip address of the remote connection. disabled—do not block remote ip addresses. to allow specific and known s

AI Tutor 👋 I’m here to help!