An internal auditor is reviewing a new automated human resources system. The system contains a table of pay rates which are matched to the employee job classifications. The best control to ensure that the table is updated correctly for only valid pay changes would be to:

  1. Limit access to the data table to management and line supervisors who have the authority to determine pay rates.
  2. Require a supervisor in the department, who does not have the ability to change the table, to compare the changes to a signed management authorization.
  3. Ensure that adequate edit and reasonableness checks are built into the automated system.
  4. Require that all pay changes be signed by the employee to verify that the change goes to a bona fide employee.

Answer(s): B



What is the most important risk in determining the validity of construction delay claims?

  1. Contractor claims may be submitted prior to completion of the work.
  2. Contractor claims may include costs considered in the fixed-price portion of the work.
  3. Contractor claims may include subcontractor estimates of balances due to the subcontractor.
  4. Contractor claims may be understated.

Answer(s): B



During an audit of a branch bank, an internal auditor learned that a series of system failures had resulted in a four-day delay in processing customers' scheduled payroll direct deposits. The first failure was that of a disk drive, followed by software and other minor failures. Which of the following controls should the auditor recommend to avoid similar delays in processing?

  1. Contingency planning.
  2. Redundancy checks.
  3. Process monitoring.
  4. Preventive maintenance.

Answer(s): A



An auditor analyzed a payroll system's data files for unusual activity, such as excessive overtime hours, unusual fluctuations in pay rates, and excessive vacation time. The application controls being verified by this analysis are:

  1. Edit and validation controls.
  2. Rejected and suspense item controls.
  3. Controls over update access to the database.
  4. Programmed balancing controls.

Answer(s): A



During the development of a purchasing system, an auditor reviewed the payment authorization program. Which of the following actions should the auditor recommend for a situation in which the quantity invoiced is greater than the quantity received?

  1. Issue an exception report.
  2. Pay the amount billed and adjust the inventory account for the difference.
  3. Return the invoice to the vendor for correction.
  4. Authorize payment of the full invoice, but maintain an open purchase order record for the missing goods.

Answer(s): A



Share your comments for IIA CIA-Part2-2025 exam with other users:

A
Alex
11/7/2023 11:02:00 AM

in 72 the answer must be [sys_user_has_role] table.

F
Finn
5/4/2023 10:21:00 PM

i appreciated the mix of multiple-choice and short answer questions. i passed my exam this morning.

A
AJ
7/13/2023 8:33:00 AM

great to find this website, thanks

C
Curtis Nakawaki
6/29/2023 9:11:00 PM

examination questions seem to be relevant.

U
Umashankar Sharma
10/22/2023 9:39:00 AM

planning to take psm test

E
ED SHAW
7/31/2023 10:34:00 AM

please allow to download

A
AD
7/22/2023 11:29:00 AM

please provide dumps

A
Ayyjayy
11/6/2023 7:29:00 AM

is the answer to question 15 correct ? i feel like the answer should be b

B
Blessious Phiri
8/12/2023 11:56:00 AM

its getting more technical

J
Jeanine J
7/11/2023 3:04:00 PM

i think these questions are what i need.

A
Aderonke
10/23/2023 2:13:00 PM

helpful assessment

T
Tom
1/5/2024 2:32:00 AM

i am confused about the answers to the questions. do you know if the answers are correct?

V
Vinit N.
8/28/2023 2:33:00 AM

hi, please make the dumps available for my upcoming examination.

S
Sanyog Deshpande
9/14/2023 7:05:00 AM

good practice

T
Tyron
9/8/2023 12:12:00 AM

so far it is really informative

B
beast
7/30/2023 2:22:00 PM

hi i want it please please upload it

M
Mirex
5/26/2023 3:45:00 AM

am preparing for exam ,just nice questions

E
exampei
8/7/2023 8:05:00 AM

please upload c_tadm_23 exam

A
Anonymous
9/12/2023 12:50:00 PM

can we get tdvan4 vantage data engineering pdf?

A
Aish
10/11/2023 5:51:00 AM

want to clear the exam.

S
Smaranika
6/22/2023 8:42:00 AM

could you please upload the dumps of sap c_sac_2302

B
Blessious Phiri
8/15/2023 1:56:00 PM

asm management configuration is about storage

L
Lewis
7/6/2023 8:49:00 PM

kool thumb up

M
Moreece
5/15/2023 8:44:00 AM

just passed the az-500 exam this last friday. most of the questions in this exam dumps are in the exam. i bought the full version and noticed some of the questions which were answered wrong in the free version are all corrected in the full version. this site is good but i wish the had it in an interactive version like a test engine simulator.

T
Terry
5/24/2023 4:41:00 PM

i can practice for exam

E
Emerys
7/29/2023 6:55:00 AM

please i need this exam.

G
Goni Mala
9/2/2023 12:27:00 PM

i need the dump

L
Lenny
9/29/2023 11:30:00 AM

i want it bad, even if cs6 maybe retired, i want to learn cs6

M
MilfSlayer
12/28/2023 8:32:00 PM

i hate comptia with all my heart with their "choose the best" answer format as an argument could be made on every question. they say "the "comptia way", lmao no this right here boys is the comptia way 100%. take it from someone whos failed this exam twice but can configure an entire complex network that these are the questions that are on the test 100% no questions asked. the pbqs are dead on! nice work

S
Swati Raj
11/14/2023 6:28:00 AM

very good materials

K
Ko Htet
10/17/2023 1:28:00 AM

thanks for your support.

P
Philippe
1/22/2023 10:24:00 AM

iam impressed with the quality of these dumps. they questions and answers were easy to understand and the xengine app was very helpful to use.

S
Sam
8/31/2023 10:32:00 AM

not bad but you question database from isaca

B
Brijesh kr
6/29/2023 4:07:00 AM

awesome contents

AI Tutor 👋 I’m here to help!