When a Belt Poka-Yoke’s a defect out of the process entirely then she should track the activity with a robust SPC system on the characteristic of interest in the defect as an early warning system.
Answer(s): B
Following the completion of a LSS project the Belt not only creates a Control Plan he also develops a _____________so those involved in the process know what to do when the critical metrics move out of spec.
Answer(s): A
Upon completion and validation of an improvement to a process a Belt and the Project Team create a Control Plan that contains which of these?
Answer(s): D
What conclusion is most correct about the Experimental Design shown here with the response in the far right column?
Which statement(s) are correct about the Factorial Plot shown here? (Note: There are 3 correct answers).
Answer(s): A,B,C