Reserve Analysis a technique not used in:

  1. Estimate Costs
  2. Estimating Activity Duration
  3. Control Costs
  4. Determine Budget

Answer(s): C

Explanation:

Reserve Analysis: Many cost estimators include reserves, also called contingency allowances, as costs in many schedule activity cost estimates. Reserve Analysis a technique not used in Control Costs.



A Project with a total funding of $70,000 finished with a BAC value of $60,000.
What term can best describe the difference of $10,000?

  1. Management Contingency Reserve
  2. Cost Variance
  3. Schedule Variance
  4. Management Overhead

Answer(s): A

Explanation:

The difference between the Cost Baseline and Funding requirement at Project completion is Management Contingency Reserve. BAC represents the revised Cost baseline for the project. So Management Contingency Reserve is true.



The positive value of conflict is underestimated. Properly managed, conflict is a valuable tool, particularly when

  1. A diversion is needed
  2. Conflict may cause a loss of status or position power
  3. Conflictive situations are in their early stages and emotional involvement is low
  4. Conflictive situations are in their late stages and emotional involvement is high

Answer(s): C



You are the project manager for a new website for the local zoo. You need to perform Qualitative Risk Analysis.
When you've completed this process, you'll produce all of the following as part of the risk register update output except which one?

  1. Probability of achieving time and cost estimates
  2. Watch list of low-priority risks
  3. Priority list of risks
  4. Risks grouped by categories

Answer(s): A

Explanation:

Probability of achieving time and cost estimates is an update that is produced from the Quantitative Risk Analysis process.



A clear definition of the user's needs serves as the direct basis for the:

  1. Selection of personnel.
  2. Termination decision.
  3. Work breakdown structure.
  4. Functional requirements.
  5. Project cost estimate.

Answer(s): D



Share your comments for GAQM PPM-001 exam with other users:

T
Thembelani
5/30/2023 2:47:00 AM

excellent material

V
vinesh phale
9/11/2023 2:51:00 AM

very helpfull

B
Bhagiii
11/4/2023 7:04:00 AM

well explained.

R
Rahul
8/8/2023 9:40:00 PM

i need the pdf, please.

C
CW
7/11/2023 2:51:00 PM

a good source for exam preparation

A
Anchal
10/23/2023 4:01:00 PM

nice questions

J
J Nunes
9/29/2023 8:19:00 AM

i need ielts general training audio guide questions

A
Ananya
9/14/2023 5:16:00 AM

please make this content available

S
Swathi
6/4/2023 2:18:00 PM

content is good

L
Leo
7/29/2023 8:45:00 AM

latest dumps please

L
Laolu
2/15/2023 11:04:00 PM

aside from pdf the test engine software is helpful. the interface is user-friendly and intuitive, making it easy to navigate and find the questions.

Z
Zaynik
9/17/2023 5:36:00 AM

questions and options are correct, but the answers are wrong sometimes. so please check twice or refer some other platform for the right answer

M
Massam
6/11/2022 5:55:00 PM

90% of questions was there but i failed the exam, i marked the answers as per the guide but looks like they are not accurate , if not i would have passed the exam given that i saw about 45 of 50 questions from dump

A
Anonymous
12/27/2023 12:47:00 AM

answer to this question "what administrative safeguards should be implemented to protect the collected data while in use by manasa and her product management team? " it should be (c) for the following reasons: this administrative safeguard involves controlling access to collected data by ensuring that only individuals who need the data for their job responsibilities have access to it. this helps minimize the risk of unauthorized access and potential misuse of sensitive information. while other options such as (a) documenting data flows and (b) conducting a privacy impact assessment (pia) are important steps in data protection, implementing a "need to know" access policy directly addresses the issue of protecting data while in use by limiting access to those who require it for legitimate purposes. (d) is not directly related to safeguarding data during use; it focuses on data transfers and location.

J
Japles
5/23/2023 9:46:00 PM

password lockout being the correct answer for question 37 does not make sense. it should be geofencing.

F
Faritha
8/10/2023 6:00:00 PM

for question 4, the righr answer is :recover automatically from failures

A
Anonymous
9/14/2023 4:27:00 AM

question number 4s answer is 3, option c. i

P
p das
12/7/2023 11:41:00 PM

very good questions

A
Anna
1/5/2024 1:12:00 AM

i am confused about the answers to the questions. are the answers correct?

B
Bhavya
9/13/2023 10:15:00 AM

very usefull

R
Rahul Kumar
8/31/2023 12:30:00 PM

need certification.

D
Diran Ole
9/17/2023 5:15:00 PM

great exam prep

V
Venkata Subbarao Bandaru
6/24/2023 8:45:00 AM

i require dump

D
D
7/15/2023 1:38:00 AM

good morning, could you please upload this exam again,

A
Ann
9/15/2023 5:39:00 PM

hi can you please upload the dumps for sap contingent module. thanks

S
Sridhar
1/16/2024 9:19:00 PM

good questions

S
Summer
10/4/2023 9:57:00 PM

looking forward to the real exam

V
vv
12/2/2023 2:45:00 PM

good ones for exam preparation

D
Danny Zas
9/15/2023 4:45:00 AM

this is a good experience

S
SM 1211
10/12/2023 10:06:00 PM

hi everyone

A
A
10/2/2023 6:08:00 PM

waiting for the dump. please upload.

A
Anonymous
7/16/2023 11:05:00 AM

upload cks exam questions

J
Johan
12/13/2023 8:16:00 AM

awesome training material

P
PC
7/28/2023 3:49:00 PM

where is dump