Reserve Analysis a technique not used in:

  1. Estimate Costs
  2. Estimating Activity Duration
  3. Control Costs
  4. Determine Budget

Answer(s): C

Explanation:

Reserve Analysis: Many cost estimators include reserves, also called contingency allowances, as costs in many schedule activity cost estimates. Reserve Analysis a technique not used in Control Costs.



A Project with a total funding of $70,000 finished with a BAC value of $60,000.
What term can best describe the difference of $10,000?

  1. Management Contingency Reserve
  2. Cost Variance
  3. Schedule Variance
  4. Management Overhead

Answer(s): A

Explanation:

The difference between the Cost Baseline and Funding requirement at Project completion is Management Contingency Reserve. BAC represents the revised Cost baseline for the project. So Management Contingency Reserve is true.



The positive value of conflict is underestimated. Properly managed, conflict is a valuable tool, particularly when

  1. A diversion is needed
  2. Conflict may cause a loss of status or position power
  3. Conflictive situations are in their early stages and emotional involvement is low
  4. Conflictive situations are in their late stages and emotional involvement is high

Answer(s): C



You are the project manager for a new website for the local zoo. You need to perform Qualitative Risk Analysis.
When you've completed this process, you'll produce all of the following as part of the risk register update output except which one?

  1. Probability of achieving time and cost estimates
  2. Watch list of low-priority risks
  3. Priority list of risks
  4. Risks grouped by categories

Answer(s): A

Explanation:

Probability of achieving time and cost estimates is an update that is produced from the Quantitative Risk Analysis process.



A clear definition of the user's needs serves as the direct basis for the:

  1. Selection of personnel.
  2. Termination decision.
  3. Work breakdown structure.
  4. Functional requirements.
  5. Project cost estimate.

Answer(s): D



Share your comments for GAQM PPM-001 exam with other users:

B
Bhuddhiman
7/30/2023 1:18:00 AM

good mateial

K
KJ
11/17/2023 3:50:00 PM

good practice exam

S
sowm
10/29/2023 2:44:00 PM

impressivre qustion

C
CW
7/6/2023 7:06:00 PM

questions seem helpful

L
luke
9/26/2023 10:52:00 AM

good content

Z
zazza
6/16/2023 9:08:00 AM

question 21 answer is alerts

A
Abwoch Peter
7/4/2023 3:08:00 AM

am preparing for exam

M
mohamed
9/12/2023 5:26:00 AM

good one thanks

M
Mfc
10/23/2023 3:35:00 PM

only got thru 5 questions, need more to evaluate

W
Whizzle
7/24/2023 6:19:00 AM

q26 should be b

S
sarra
1/17/2024 3:44:00 AM

the aaa triad in information security is authentication, accounting and authorisation so the answer should be d 1, 3 and 5.

D
DBS
5/14/2023 12:56:00 PM

need to attend this

D
Da_costa
8/1/2023 5:28:00 PM

these are free brain dumps i understand, how can one get free pdf

V
vikas
10/28/2023 6:57:00 AM

provide access

A
Abdullah
9/29/2023 2:06:00 AM

good morning

R
Raj
6/26/2023 3:12:00 PM

please upload the ncp-mci 6.5 dumps, really need to practice this one. thanks guys

M
Miguel
10/5/2023 12:21:00 PM

question 16: https://help.salesforce.com/s/articleview?id=sf.care_console_overview.htm&type=5

H
Hiren Ladva
7/8/2023 10:34:00 PM

yes i m prepared exam

O
oliverjames
10/24/2023 5:37:00 AM

my experience was great with this site as i studied for the ms-900 from here and got 900/1000 on the test. my main focus was on the tutorials which were provided and practice questions. thanks!

B
Bhuddhiman
7/20/2023 11:52:00 AM

great course

A
Anuj
1/14/2024 4:07:00 PM

very good question

S
Saravana Kumar TS
12/8/2023 9:49:00 AM

question: 93 which statement is true regarding the result? sales contain 6 columns and values contain 7 columns so c is not right answer.

L
Lue
3/30/2023 11:43:00 PM

highly recommend just passed my exam.

D
DC
1/7/2024 10:17:00 AM

great practice! thanks

A
Anonymus
11/9/2023 5:41:00 AM

anyone who wrote this exam recently?

K
Khalid Javid
11/17/2023 3:46:00 PM

kindly share the dump

N
Na
8/9/2023 8:39:00 AM

could you please upload cfe fraud prevention and deterrence questions? it will be very much helpful.

S
shime
10/23/2023 10:03:00 AM

this is really very very helpful for mcd level 1

V
Vnu
6/3/2023 2:39:00 AM

very helpful!

S
Steve
8/17/2023 2:19:00 PM

question #18s answer should be a, not d. this should be corrected. it should be minvalidityperiod

R
RITEISH
12/24/2023 4:33:00 AM

thanks for the exact solution

S
SB
10/15/2023 7:58:00 AM

need to refer the questions and have to give the exam

M
Mike Derfalem
7/16/2023 7:59:00 PM

i need it right now if it was possible please

I
Isak
7/6/2023 3:21:00 AM

i need it very much please share it in the fastest time.

AI Tutor 👋 I’m here to help!