You have been contracted to manage the acceptance testing of a new computer-based reservation system for a travel agency. You have provided an approximate budget estimate for the testing project based on previous experience with similar sized projects. However, the management of the parent company of the travel agency will not commit to the budget until detailed cost estimates are provided.
The reservation system is being developed by a third party However, detailed specifications of the software are available, as well as an estimate of the total effort that will be spent in developing the software. The software is to be delivered in four increments, and the functionality to be delivered in each increment has already been agreed on.

In general which part of the testing activity is most difficult to estimate?

  1. Test planning
  2. Test execution
  3. Test management
  4. Test design

Answer(s): B




You have been contracted to manage the acceptance testing of a new computer-based reservation system for a travel agency. You have provided an approximate budget estimate for the testing project based on previous experience with similar sized projects. However, the management of the parent company of the travel agency will not commit to the budget until detailed cost estimates are provided.
The reservation system is being developed by a third party However, detailed specifications of the software are available, as well as an estimate of the total effort that will be spent in developing the software. The software is to be delivered in four increments, and the functionality to be delivered in each increment has already been agreed on.

In general, why is it NOT a good idea to estimate the testing effort based only on a percentage of development effort? Identify THREE valid reasons.

  1. The quality of the development estimate may be poor.
  2. In general bottom-up estimation is always better than top-down estimation.
  3. The percentage based technique only applies to the V life cycle model.
  4. Using the same percentage every time does not address the level of risk of the application to be tested.
  5. The maturity of the organization, e.g. the quality of the test basis, quality of development testing, configuration management, availability of test tools, also influence the effort needed for testing.
  6. It builds on large set of historical data
  7. The result is almost always a too low estimate for the required test effort

Answer(s): A,D,E




You have been contracted to manage the acceptance testing of a new computer-based reservation system for a travel agency. You have provided an approximate budget estimate for the testing project based on previous experience with similar sized projects. However, the management of the parent company of the travel agency will not commit to the budget until detailed cost estimates are provided.
The reservation system is being developed by a third party However, detailed specifications of the software are available, as well as an estimate of the total effort that will be spent in developing the software. The software is to be delivered in four increments, and the functionality to be delivered in each increment has already been agreed on.

Which aspect in the test estimate is the main risk in this project?

  1. Quality of the specification
  2. Availability of end-users
  3. The costs of hardware and tools
  4. Unknown input quality due to third party development

Answer(s): D




You have raised the issue that improving the testing process is also dependent on the status of the software development process.

Model characteristics:
Which THREE of the below mentioned characteristics relate to TMMi?

  1. 5 maturity levels
  2. Focussed on higher level testing
  3. 20 key areas
  4. Highly related to CMMI
  5. Continuous model
  6. Staged model
  7. Focussed on component and integration testing
  8. Is build around 12 critical testing processes

Answer(s): A,D,F




You have raised the issue that improving the testing process is also dependent on the status of the software development process.

The test improvement project will take place in an organization developing a safety-critical avionics application. Which one of the following standards do you believe would be most appropriate to take into account for compliance during your assignment?

  1. ISO 9126
  2. IEEE 829
  3. BS 7925/2
  4. DO-178B

Answer(s): D



Share your comments for GAQM CTFL exam with other users:

S
Swati Raj
11/14/2023 6:28:00 AM

very good materials

K
Ko Htet
10/17/2023 1:28:00 AM

thanks for your support.

P
Philippe
1/22/2023 10:24:00 AM

iam impressed with the quality of these dumps. they questions and answers were easy to understand and the xengine app was very helpful to use.

S
Sam
8/31/2023 10:32:00 AM

not bad but you question database from isaca

B
Brijesh kr
6/29/2023 4:07:00 AM

awesome contents

J
JM
12/19/2023 1:22:00 PM

answer to 134 is casb. while data loss prevention is the goal, in order to implement dlp in cloud applications you need to deploy a casb.

N
Neo
7/26/2023 9:36:00 AM

are these brain dumps sufficient enough to go write exam after practicing them? or does one need more material this wont be enough?

B
Bilal
8/22/2023 6:33:00 AM

i did attend the required cources and i need to be sure that i am ready to take the exam, i would ask you please to share the questions, to be sure that i am fit to proceed with taking the exam.

J
John
11/12/2023 8:48:00 PM

why only give explanations on some, and not all questions and their respective answers?

B
Biswa
11/20/2023 8:50:00 AM

refresh db knowledge

S
Shalini Sharma
10/17/2023 8:29:00 AM

interested for sap certification

E
ethan
9/24/2023 12:38:00 PM

could you please upload practice questions for scr exam ?

V
vijay joshi
8/19/2023 3:15:00 AM

please upload free oracle cloud infrastructure 2023 foundations associate exam braindumps

A
Ayodele Talabi
8/25/2023 9:25:00 PM

sweating! they are tricky

R
Romero
3/23/2022 4:20:00 PM

i never use these dumps sites but i had to do it for this exam as it is impossible to pass without using these question dumps.

J
John Kennedy
9/20/2023 3:33:00 AM

good practice and well sites.

N
Nenad
7/12/2022 11:05:00 PM

passed my first exam last week and pass the second exam this morning. thank you sir for all the help and these brian dumps.

L
Lucky
10/31/2023 2:01:00 PM

does anyone who attended exam csa 8.8, can confirm these questions are really coming ? or these are just for practicing?

P
Prateek
9/18/2023 11:13:00 AM

kindly share the dumps

I
Irfan
11/25/2023 1:26:00 AM

very nice content

P
php
6/16/2023 12:49:00 AM

passed today

D
Durga
6/23/2023 1:22:00 AM

hi can you please upload questions

J
JJ
5/28/2023 4:32:00 AM

please upload quetions

N
Norris
1/3/2023 8:06:00 PM

i passed my exam thanks to this braindumps questions. these questions are valid in us and i highly recommend it!

A
abuti
7/21/2023 6:10:00 PM

are they truely latest

C
Curtis Nakawaki
7/5/2023 8:46:00 PM

questions appear contemporary.

V
Vv
12/2/2023 6:31:00 AM

good to prepare in this site

P
praveenkumar
11/20/2023 11:57:00 AM

very helpful to crack first attempt

A
asad Raza
5/15/2023 5:38:00 AM

please upload this exam

R
Reeta
7/17/2023 5:22:00 PM

please upload the c_activate22 dump questions with answer

W
Wong
12/20/2023 11:34:00 AM

q10 - the answer should be a. if its c, the criteria will meet if either the prospect is not part of the suppression lists or if the job title contains vice president

D
david
12/12/2023 12:38:00 PM

this was on the exam as of 1211/2023

T
Tink
7/24/2023 9:23:00 AM

great for prep

J
Jaro
12/18/2023 3:12:00 PM

i think in question 7 the first answer should be power bi portal (not power bi)

AI Tutor 👋 I’m here to help!