You have been contracted to manage the acceptance testing of a new computer-based reservation system for a travel agency. You have provided an approximate budget estimate for the testing project based on previous experience with similar sized projects. However, the management of the parent company of the travel agency will not commit to the budget until detailed cost estimates are provided.
The reservation system is being developed by a third party However, detailed specifications of the software are available, as well as an estimate of the total effort that will be spent in developing the software. The software is to be delivered in four increments, and the functionality to be delivered in each increment has already been agreed on.

In general which part of the testing activity is most difficult to estimate?

  1. Test planning
  2. Test execution
  3. Test management
  4. Test design

Answer(s): B




You have been contracted to manage the acceptance testing of a new computer-based reservation system for a travel agency. You have provided an approximate budget estimate for the testing project based on previous experience with similar sized projects. However, the management of the parent company of the travel agency will not commit to the budget until detailed cost estimates are provided.
The reservation system is being developed by a third party However, detailed specifications of the software are available, as well as an estimate of the total effort that will be spent in developing the software. The software is to be delivered in four increments, and the functionality to be delivered in each increment has already been agreed on.

In general, why is it NOT a good idea to estimate the testing effort based only on a percentage of development effort? Identify THREE valid reasons.

  1. The quality of the development estimate may be poor.
  2. In general bottom-up estimation is always better than top-down estimation.
  3. The percentage based technique only applies to the V life cycle model.
  4. Using the same percentage every time does not address the level of risk of the application to be tested.
  5. The maturity of the organization, e.g. the quality of the test basis, quality of development testing, configuration management, availability of test tools, also influence the effort needed for testing.
  6. It builds on large set of historical data
  7. The result is almost always a too low estimate for the required test effort

Answer(s): A,D,E




You have been contracted to manage the acceptance testing of a new computer-based reservation system for a travel agency. You have provided an approximate budget estimate for the testing project based on previous experience with similar sized projects. However, the management of the parent company of the travel agency will not commit to the budget until detailed cost estimates are provided.
The reservation system is being developed by a third party However, detailed specifications of the software are available, as well as an estimate of the total effort that will be spent in developing the software. The software is to be delivered in four increments, and the functionality to be delivered in each increment has already been agreed on.

Which aspect in the test estimate is the main risk in this project?

  1. Quality of the specification
  2. Availability of end-users
  3. The costs of hardware and tools
  4. Unknown input quality due to third party development

Answer(s): D




You have raised the issue that improving the testing process is also dependent on the status of the software development process.

Model characteristics:
Which THREE of the below mentioned characteristics relate to TMMi?

  1. 5 maturity levels
  2. Focussed on higher level testing
  3. 20 key areas
  4. Highly related to CMMI
  5. Continuous model
  6. Staged model
  7. Focussed on component and integration testing
  8. Is build around 12 critical testing processes

Answer(s): A,D,F




You have raised the issue that improving the testing process is also dependent on the status of the software development process.

The test improvement project will take place in an organization developing a safety-critical avionics application. Which one of the following standards do you believe would be most appropriate to take into account for compliance during your assignment?

  1. ISO 9126
  2. IEEE 829
  3. BS 7925/2
  4. DO-178B

Answer(s): D



Share your comments for GAQM CTFL exam with other users:

A
abuti
7/21/2023 6:24:00 PM

cool very helpfull

K
Krishneel
3/17/2023 10:34:00 AM

i just passed. this exam dumps is the same one from prepaway and examcollection. it has all the real test questions.

R
Regor
12/4/2023 2:01:00 PM

is this a valid prince2 practitioner dumps?

A
asl
9/14/2023 3:59:00 PM

all are relatable questions

S
Siyya
1/19/2024 8:30:00 PM

might help me to prepare for the exam

T
Ted
6/21/2023 11:11:00 PM

just paid and downlaod the 2 exams using the 50% sale discount. so far i was able to download the pdf and the test engine. all looks good.

P
Paul K
11/27/2023 2:28:00 AM

i think it should be a,c. option d goes against the principle of building anything custom unless there are no work arounds available

P
ph
6/16/2023 12:41:00 AM

very legible

S
sephs2001
7/31/2023 10:42:00 PM

is this exam accurate or helpful?

A
ash
7/11/2023 3:00:00 AM

please upload dump, i have exam in 2 days

S
Sneha
8/17/2023 6:29:00 PM

this is useful

S
sachin
12/27/2023 2:45:00 PM

question 232 answer should be perimeter not netowrk layer. wrong answer selected

T
tomAws
7/18/2023 5:05:00 AM

nice questions

R
Rahul
6/11/2023 2:07:00 AM

hi team, could you please provide this dump ?

T
TeamOraTech
12/5/2023 9:49:00 AM

very helpful to clear the exam and understand the concept.

C
Curtis
7/12/2023 8:20:00 PM

i think it is great that you are helping people when they need it. thanks.

S
sam
7/17/2023 6:22:00 PM

cannot evaluate yet

N
nutz
7/20/2023 1:54:00 AM

a laptops wireless antenna is most likely located in the bezel of the lid

R
rajesh soni
1/17/2024 6:53:00 AM

good examplae to learn basic

T
Tanya
10/25/2023 7:07:00 AM

this is useful information

N
Nasir Mahmood
12/11/2023 7:32:00 AM

looks usefull

J
Jason
9/30/2023 1:07:00 PM

question 81 should be c.

T
TestPD1
8/10/2023 12:22:00 PM

question 18 : response isnt a ?

A
ally
8/19/2023 5:31:00 PM

plaese add questions

D
DIA
10/7/2023 5:59:00 AM

is dumps still valid ?

A
Annie
7/7/2023 8:33:00 AM

thanks for this

A
arnie
9/17/2023 6:38:00 AM

please upload questions

T
Tanuj Rana
7/22/2023 2:33:00 AM

please upload the question dump for professional machinelearning

F
Future practitioner
8/10/2023 1:26:00 PM

question 4 answer is c. this site shows the correct answer as b. "adopt a consumption model" is clearly a cost optimization design principle. looks like im done using this site to study!!!

A
Ace
8/3/2023 10:37:00 AM

number 52 answer is d

N
Nathan
12/17/2023 12:04:00 PM

just started preparing for my exam , and this site is so much help

C
Corey
12/29/2023 5:06:00 PM

question 35 is incorrect, the correct answer is c, it even states so: explanation: when a vm is infected with ransomware, you should not restore the vm to the infected vm. this is because the ransomware will still be present on the vm, and it will encrypt the files again. you should also not restore the vm to any vm within the companys subscription. this is because the ransomware could spread to other vms in the subscription. the best way to restore a vm that is infected with ransomware is to restore it to a new azure vm. this will ensure that the ransomware is not present on the new vm.

R
Rajender
10/18/2023 3:54:00 AM

i would like to take psm1 exam.

B
Blessious Phiri
8/14/2023 9:53:00 AM

cbd and pdb are key to the database

AI Tutor 👋 I’m here to help!