The Sprint Goal is a result of Sprint Planning, as is the Sprint Backlog. True or False?

  1. True
  2. False

Answer(s): A

Explanation:

The Sprint Goal and the Sprint Backlog are both outcomes of Sprint Planning, making this statement true. According to the Scrum Guide, Sprint Planning is an event where the Scrum Team collaborates to define the work to be performed during the Sprint. The Sprint Goal is a single objective set for the Sprint, providing focus and coherence to the work selected. It is crafted collaboratively by the Product Owner, Developers, and Scrum Master during Sprint Planning. Simultaneously, the Sprint Backlog is created, consisting of the Product Backlog items selected for the Sprint plus a plan to deliver them, aligned with the Sprint Goal. The Scrum Guide states: "Sprint Planning initiates the Sprint by laying out the work to be performed... This resulting plan is created by the collaborative work of the entire Scrum Team." Thus, both the Sprint Goal and Sprint Backlog emerge from this event, confirming option A as correct.


Reference:

Scrum Guide (2020), Section: "Sprint Planning."



Every Scrum Team should have: (Choose the best answer)

  1. The competencies and skills needed to deliver a Done Increment in a Sprint.
  2. At least one representative from each major software engineering discipline (like QA, Dev, UX).
  3. One Lead Developer and no more than eight other members.

Answer(s): A

Explanation:

The Scrum Guide emphasizes that a Scrum Team must be cross-functional, meaning it has all the competencies and skills necessary to create a "Done" Increment within a Sprint without relying on external resources. Option A aligns directly with this principle: "The Scrum Team consists of one Scrum Master, one Product Owner, and Developers... They are cross-functional, meaning the members have all the skills necessary to create value each Sprint." Option B, while suggesting a structured representation from disciplines, is too prescriptive and not a Scrum requirement--Scrum does not mandate specific roles like QA or UX within the Developers. Option C imposes a rigid team structure (one Lead Developer and a maximum of eight others), which contradicts Scrum's flexibility in team composition (typically 10 or fewer total, but no specific roles or limits beyond that are mandated). Thus, A is the best answer, focusing on capability rather than structure.


Reference:

Scrum Guide (2020), Section: "The Scrum Team."



What three factors are best considered when establishing the Sprint length? (Choose the best three answers)

  1. The ability to go to market with a product release.
  2. Sprints must have the same length throughout an organization.
  3. The frequency at which team formation can be changed.
  4. The level of uncertainty over the technology to be used.
  5. The risk of being disconnected from the stakeholders.

Answer(s): A,D,E

Explanation:

Sprint length in Scrum is a critical decision that impacts the team's ability to deliver value and adapt. The Scrum Guide states that Sprints are fixed in length (typically one month or less) to create consistency and enable regular inspection and adaptation.
While it doesn't explicitly list factors, practical application and Scrum principles suggest:

A (The ability to go to market with a product release): Shorter Sprints allow faster feedback and releases, aligning with Scrum's focus on delivering value frequently.

D (The level of uncertainty over the technology to be used): High uncertainty may warrant shorter Sprints to mitigate risk and validate assumptions, a key aspect of empirical process control.

E (The risk of being disconnected from the stakeholders): Shorter Sprints ensure frequent stakeholder engagement (e.g., via Sprint Reviews), reducing this risk.

Option B is incorrect because Scrum does not require uniform Sprint lengths across an organization-- each team can choose what works best. Option C is irrelevant, as team formation changes are not tied to Sprint length in Scrum. Thus, A, D, and E are the best factors.


Reference:

Scrum Guide (2020), Section: "Sprint."



Which three of the following are true about Scrum? (Choose the best three answers)

  1. Scrum is a methodology, where you can pick and choose which parts of Scrum you think will work for your environment.
  2. Scrum is like traditional processes but with self-organization to replace Project Managers.
  3. Scrum is a framework for developing and sustaining complex products.
  4. Scrum is based on empirical process control theory.
  5. Each component of Scrum serves a specific purpose and is essential to Scrum's success and your usage of Scrum to develop complex products.

Answer(s): C,D,E

Explanation:

C: The Scrum Guide defines Scrum as "a lightweight framework that helps people, teams, and organizations generate value through adaptive solutions for complex problems." This is a core truth.

D: Scrum's foundation in empirical process control theory (transparency, inspection, adaptation) is explicitly stated in the Scrum Guide: "Scrum is founded on empiricism and lean thinking."

E: The Scrum Guide emphasizes that "each element of the framework serves a specific purpose that is essential to the overall value and results realized with Scrum." Altering components risks losing Scrum's benefits.

Option A is false--Scrum is a framework, not a methodology, and cherry-picking parts undermines its integrity. Option B misrepresents Scrum; it's not a tweak on traditional processes but a distinct approach, and it doesn't merely replace Project Managers with self-organization--it eliminates that role entirely. Thus, C, D, and E are correct.


Reference:

Scrum Guide (2020), Sections: "Scrum Definition," "Scrum Theory."



When a Developers determines that it has over-committed itself for a Sprint, who has to be present when reviewing and adjusting the Sprint work selected? (Choose the best answer)

  1. The Scrum Master, project manager, and Developers.
  2. The Product Owner and the Developers.
  3. The Product Owner and all stakeholders.
  4. The Developers.

Answer(s): B

Explanation:

The Scrum Guide states that the Sprint Backlog is owned by the Developers, who are responsible for planning and executing the work to achieve the Sprint Goal. If they realize they've over-committed, they must adjust the Sprint Backlog. However, since the Product Owner is accountable for maximizing value and managing the Product Backlog, their involvement is critical to ensure adjustments align with value delivery and the Sprint Goal. The Scrum Guide notes: "The Product Owner may influence the Developers by helping them understand and select trade-offs." Option A includes a non-existent "project manager" role in Scrum, making it incorrect. Option C involves stakeholders, who are not part of mid-Sprint adjustments (they provide feedback at the Sprint Review). Option D excludes the Product Owner, which is insufficient given their role. Thus, B is correct.


Reference:

Scrum Guide (2020), Sections: "Sprint Backlog," "The Product Owner."



Which statement best describes the Sprint Backlog as an outcome of the Sprint Planning? (Choose the best answer)

  1. It is a complete list of all work to be done in a Sprint.
  2. Each task is estimated in hours.
  3. It is the Developers' plan for the Sprint.
  4. Every item has a designated owner.
  5. It is ordered by the Product Owner.

Answer(s): C

Explanation:

The Scrum Guide defines the Sprint Backlog as "a plan by and for the Developers" that includes selected Product Backlog items and a plan to deliver the Sprint Goal. Option C accurately reflects this ownership and purpose. Option A is too absolute--while it's a plan, it's not necessarily "complete" as it can evolve during the Sprint. Option B is incorrect--Scrum does not mandate hour-based estimates; estimation is up to the Developers' discretion. Option D is false--items don't require individual owners; the Developers collectively own the Sprint Backlog. Option E is wrong--the Product Owner orders the Product Backlog, not the Sprint Backlog, which is managed by the Developers. Thus, C is the best description.


Reference:

Scrum Guide (2020), Section: "Sprint Backlog."



Which two (2) metrics will help a Product Owner establish that value is being delivered? (Choose the best two answers)

  1. Time to market.
  2. Customer satisfaction.
  3. Velocity.
  4. Productivity.
  5. Budget spent.

Answer(s): A,B

Explanation:

The Product Owner's primary accountability is maximizing the value of the product, per the Scrum Guide. Metrics should reflect outcomes, not just internal process efficiency:

A (Time to market): Faster delivery of Increments to the market validates value through real-world feedback, a key Scrum principle.

B (Customer satisfaction): This directly measures whether the product meets user needs, aligning with value delivery.

C (Velocity): While useful for Developers to gauge capacity, it's an internal metric, not a direct indicator of value.

D (Productivity): This focuses on effort, not outcome, and isn't tied to value in Scrum.

E (Budget spent): Spending doesn't guarantee value; it's a cost metric, not a value metric.

Thus, A and B best help the Product Owner assess value.


Reference:

Scrum Guide (2020), Section: "The Product Owner."



The Product Owner is accountable for the functionality included in each Increment. Does he or she have the final say over the definition of "Done"?

  1. Yes, the Product Owner is responsible for the definition of "Done". The Developers may be consulted.
  2. No, the Scrum Team is responsible for the definition of "Done". The Product Owner may be consulted.

Answer(s): B

Explanation:

The Scrum Guide clarifies that the definition of "Done" is a shared commitment created by the Scrum Team: "The Definition of Done is a formal description of the state of the Increment when it meets the quality measures required for the product." While the Product Owner defines what goes into the Increment (via the Product Backlog), the definition of "Done" is a collaborative effort, often driven by the Developers' technical expertise and organizational standards, with input from the Product Owner on value and quality expectations. Option A incorrectly gives the Product Owner sole authority, while B correctly reflects the team's collective responsibility, with the Product Owner as a contributor, not the final arbiter.


Reference:

Scrum Guide (2020), Section: "Definition of Done."



Viewing Page 1 of 11



Share your comments for GAQM CASPO-001 exam with other users:

Oliviajames 10/25/2023 5:31:00 AM

i just want to tell you. i took my microsoft az-104 exam and passed it. your program was awesome. i especially liked your detailed questions and answers and practice tests that made me well-prepared for the exam. thanks to this website!!!
UNITED STATES


Divya 8/27/2023 12:31:00 PM

all the best
UNITED STATES


KY 1/1/2024 11:01:00 PM

very usefull document
Anonymous


Arun 9/20/2023 4:52:00 PM

nice and helpful questions
INDIA


Joseph J 7/11/2023 2:53:00 PM

i found the questions helpful
UNITED STATES


Meg 10/12/2023 8:02:00 AM

q 105 . ans is d
INDIA


Navaneeth S 7/14/2023 7:57:00 AM

i have interest to get a sybase iq dba certification
UNITED STATES


Aish 10/11/2023 5:27:00 AM

want to pass exm.
INDIA


Anonymous 6/12/2023 7:23:00 AM

are the answers correct?
INDIA


Kris 7/7/2023 9:43:00 AM

good morning, could you please upload this exam again, i need it to test my knowledge in sd-wan with version 7.0.
Anonymous


Meghraj mali 10/7/2023 1:47:00 PM

very nice question
CANADA


Noel 11/1/2022 9:14:00 PM

i have learning disability and this exam dumps allowed me to focus on the actual questions and not worry about notes and the those other study materials.
SOUTH AFRICA


Jas 10/25/2023 6:01:00 PM

165 should be apt
UNITED STATES


Neetu 6/22/2023 8:41:00 AM

please upload the dumps, real need of them
Anonymous


Mark 10/24/2023 1:34:00 AM

any recent feeedback?
UNITED STATES


Gopinadh 8/9/2023 4:05:00 AM

question number 2 is indicating you are giving proper questions. observe and change properly.
Anonymous


Santhi 1/1/2024 8:23:00 AM

passed today.40% questions were new.litwere case study,lots of new questions on afd,ratelimit,tm,lb,app gatway.got 2 set series of questions which are not present here.questions on azure cyclecloud, no.of vnet/vms required for implimentation,blueprints assignment/management group etc
INDIA


Raviraj Magadum 1/12/2024 11:39:00 AM

practice test
INDIA


sivaramakrishnan 7/27/2023 8:12:00 AM

want the dumps for emc content management server programming(cmsp)
Anonymous


Aderonke 10/23/2023 1:52:00 PM

brilliant and helpful
UNITED KINGDOM


Az 9/16/2023 2:43:00 PM

q75. azure files is pass
SWITZERLAND


ketty 11/9/2023 8:10:00 AM

very helpful
Anonymous


Sonail 5/2/2022 1:36:00 PM

thank you for these questions. it helped a lot.
UNITED STATES


Shariq 7/28/2023 8:00:00 AM

how do i get the h12-724 dumps
Anonymous


adi 10/30/2023 11:51:00 PM

nice data dumps
Anonymous


EDITH NCUBE 7/25/2023 7:28:00 AM

answers are correct
SOUTH AFRICA


Raja 6/20/2023 4:38:00 AM

good explanation
UNITED STATES


BigMouthDog 1/22/2022 8:17:00 PM

hi team just want to know if there is any update version of the exam 350-401
AUSTRALIA


francesco 10/30/2023 11:08:00 AM

helpful on 2017 scrum guide
EUROPEAN UNION


Amitabha Roy 10/5/2023 3:16:00 AM

planning to attempt for the exam.
Anonymous


Prem Yadav 7/29/2023 6:20:00 AM

pleaseee upload
INDIA


Ahmed Hashi 7/6/2023 5:40:00 PM

thanks ly so i have information cia
EUROPEAN UNION


mansi 5/31/2023 7:58:00 AM

hello team, i need sap qm dumps for practice
INDIA


Jamil aljamil 12/4/2023 4:47:00 AM

it’s good but not senatios based
UNITED KINGDOM