Details: Ranking Investment Projects 19

The following forecasts have been prepared for a new investment by Oxford Industries of $20 million with an 8-year life:

Assume that Oxford employs straight-line depreciation, and that they are taxed at 35%. Assuming an opportunity cost of capital of 14%, what is the NPV of this project, based on expected outcomes?

  1. $2,626,415
  2. $4,563,505
  3. $6,722,109
  4. $8,055,722

Answer(s): B

Explanation:

The first step is to calculate the annual cash flows from the project for the base case (the expected values). These may be calculated as shown:


This level of cash flow occurs for each of the 8 years of the project. The present value of an 8-year, $1 annuity is 4.639 at 14%. The NPV of the project is therefore given by:




Details: Ranking Investment Projects 19

Drillers Inc. is evaluating a project to produce a high-tech deep-sea oil exploration device. The investment required is $80 million for a plant with a capacity of 15.000 units a year for 5 years. The device will be sold for a price of $12,000 per unit. Sales are expected to be 12,000 units per year. The variable cost is $7,000 and fixed costs, excluding depreciation, are $25 million per year. Assume Drillers employs straight-line depreciation on all depreciable assets, and assume that they are taxed at a rate of 36%. If the required rate of return is 12%, what is the approximate NPV of the project?

  1. $17,225,000
  2. $21511,000
  3. $26.780000
  4. $56117000

Answer(s): B

Explanation:




Details: Ranking Investment Projects 19

Assume that the probability distribution of Nap's is normal. The firm considers true risk occurring if the project results in a NPV that is zero or less. If the expected NPV is $1,000 and the standard deviation of NPV is $500, what is the probability that the project has an NPV of 0 or less?

  1. Less than 3%.
  2. Greater than 3%, but less than 9%.
  3. Greater than 9%, but less than 16%.
  4. Greater than 16%.

Answer(s): A

Explanation:

Since three standard deviations incorporate over 99% of all observations, and two standard deviations incorporate over 95% of observations, it means less than 5% will not be included within two standard deviations, and this is divided between both ends of the normal curve. Therefore, less than 2.5% of the observations will be in the negative portion of the curve.




Details: Ranking Investment Projects 19

Project 1 has an expected NPV of $120,000 and a standard deviation of $200,000. Project 2 has an expected NPV of $100,000 and a standard deviation of $150,000. The correlation between these two projects is 0.80. What is the coefficient of variation for the portfolio of projects?

  1. 1.67
  2. 1.59
  3. 1.51
  4. 0.63

Answer(s): C

Explanation:

The coefficient of variation is useful when the rates of return and standard deviations of two investments differ. It measures the risk per unit of return by dividing the standard deviation by the expected return. Thus, for Project 1, dividing $200,000 by $120,000 produces a coefficient of 1.67. For Project 2, the calculation is to divide $150,000 by $100,000, or 1.50. If the two projects had perfect correlation (=1.0), then you could combine the calculations ($350,000 + $220,000 = 1.59). However, with a correlation of less than one, the risk will be something less than 1.59.




Details: Ranking Investment Projects 19

When using the net present value method for capital budgeting analysis, the required rate of return is called all of the following except the

  1. Risk-free rate.
  2. Cost of capital.
  3. Discount rate.
  4. Cutoff rate.

Answer(s): A

Explanation:

The rate used to discount future cash flows is sometimes called the cost of capital, the discount rate, the cutoff rate, or the hurdle rate. A risk-free rate is the rate available on risk-free investments such as government bonds. The risk-free rate is not equivalent to the cost of capital because the latter must incorporate a risk premium.



Viewing Page 16 of 270



Share your comments for Financial CMA exam with other users:

Nabeel 7/25/2023 4:11:00 PM

still learning
Anonymous


gure 7/26/2023 5:10:00 PM

excellent way to learn
UNITED STATES


ciken 8/24/2023 2:55:00 PM

help so much
Anonymous


Biswa 11/20/2023 9:28:00 AM

understand sql col.
Anonymous


Saint Pierre 10/24/2023 6:21:00 AM

i would give 5 stars to this website as i studied for az-800 exam from here. it has all the relevant material available for preparation. i got 890/1000 on the test.
Anonymous


Rose 7/24/2023 2:16:00 PM

this is nice.
Anonymous


anon 10/15/2023 12:21:00 PM

q55- the ridac workflow can be modified using flow designer, correct answer is d not a
UNITED STATES


NanoTek3 6/13/2022 10:44:00 PM

by far this is the most accurate exam dumps i have ever purchased. all questions are in the exam. i saw almost 90% of the questions word by word.
UNITED STATES


eriy 11/9/2023 5:12:00 AM

i cleared the az-104 exam by scoring 930/1000 on the exam. it was all possible due to this platform as it provides premium quality service. thank you!
UNITED STATES


Muhammad Rawish Siddiqui 12/8/2023 8:12:00 PM

question # 232: accessibility, privacy, and innovation are not data quality dimensions.
SAUDI ARABIA


Venkat 12/27/2023 9:04:00 AM

looks wrong answer for 443 question, please check and update
Anonymous


Varun 10/29/2023 9:11:00 PM

great question
Anonymous


Doc 10/29/2023 9:36:00 PM

question: a user wants to start a recruiting posting job posting. what must occur before the posting process can begin? 3 ans: comment- option e is incorrect reason: as part of enablement steps, sap recommends that to be able to post jobs to a job board, a user need to have the correct permission and secondly, be associated with one posting profile at minimum
UNITED KINGDOM


It‘s not A 9/17/2023 5:31:00 PM

answer to question 72 is d [sys_user_role]
Anonymous


indira m 8/14/2023 12:15:00 PM

please provide the pdf
UNITED STATES


ribrahim 8/1/2023 6:05:00 AM

hey guys, just to let you all know that i cleared my 312-38 today within 1 hr with 100 questions and passed. thank you so much brain-dumps.net all the questions that ive studied in this dump came out exactly the same word for word "verbatim". you rock brain-dumps.net!!! section name total score gained score network perimeter protection 16 11 incident response 10 8 enterprise virtual, cloud, and wireless network protection 12 8 application and data protection 13 10 network défense management 10 9 endpoint protection 15 12 incident d
SINGAPORE


Andrew 8/23/2023 6:02:00 PM

very helpful
Anonymous


latha 9/7/2023 8:14:00 AM

useful questions
GERMANY


ibrahim 11/9/2023 7:57:00 AM

page :20 https://exam-dumps.com/snowflake/free-cof-c02-braindumps.html?p=20#collapse_453 q 74: true or false: pipes can be suspended and resumed. true. desc.: pausing or resuming pipes in addition to the pipe owner, a role that has the following minimum permissions can pause or resume the pipe https://docs.snowflake.com/en/user-guide/data-load-snowpipe-intro
FINLAND


Franklin Allagoa 7/5/2023 5:16:00 AM

i want hcia exam dumps
Anonymous


SSA 12/24/2023 1:18:00 PM

good training
Anonymous


BK 8/11/2023 12:23:00 PM

very useful
INDIA


Deepika Narayanan 7/13/2023 11:05:00 PM

yes need this exam dumps
Anonymous


Blessious Phiri 8/15/2023 3:31:00 PM

these questions are a great eye opener
Anonymous


Jagdesh 9/8/2023 8:17:00 AM

thank you for providing these questions and answers. they helped me pass my exam. you guys are great.
CANADA


TS 7/18/2023 3:32:00 PM

good knowledge
Anonymous


Asad Khan 11/1/2023 2:44:00 AM

answer 10 should be a because only a new project will be created & the organization is the same.
Anonymous


Raj 9/12/2023 3:49:00 PM

can you please upload the dump again
UNITED STATES


Christian Klein 6/23/2023 1:32:00 PM

is it legit questions from sap certifications ?
UNITED STATES


anonymous 1/12/2024 3:34:00 PM

question 16 should be b (changing the connector settings on the monitor) pc and monitor were powered on. the lights on the pc are on indicating power. the monitor is showing an error text indicating that it is receiving power too. this is a clear sign of having the wrong input selected on the monitor. thus, the "connector setting" needs to be switched from hdmi to display port on the monitor so it receives the signal from the pc, or the other way around (display port to hdmi).
UNITED STATES


NSPK 1/18/2024 10:26:00 AM

q 10. ans is d (in the target org: open deployment settings, click edit next to the source org. select allow inbound changes and save
Anonymous


mohamed abdo 9/1/2023 4:59:00 AM

very useful
Anonymous


Tom 3/18/2022 8:00:00 PM

i purchased this exam dumps from another website with way more questions but they were all invalid and outdate. this exam dumps was right to the point and all from recent exam. it was a hard pass.
UNITED KINGDOM


Edrick GOP 10/24/2023 6:00:00 AM

it was a good experience and i got 90% in the 200-901 exam.
Anonymous