What is the primary responsibility of a Scrum Master in order to keep a Scrum team working at its peak level of productivity?

  1. Keeping high priority features at the top of the Product Backlog.
  2. Not allowing changes to the Product Backlog once the Sprint begins.
  3. Supporting the team's decisions and resolving the team's issues.

Answer(s): C



A customer requests a report that summarizes functionality added and defects found and fixed, right at the end of a Sprint.
Who may best prepare this report?

  1. The Product Owner
  2. The Scrum Master
  3. The team
  4. This type of report should not be prepared.

Answer(s): B



Who should update the work estimates during the Sprint?

  1. Only the team members
  2. The Project Manager
  3. The Product Owner

Answer(s): A



Which means of communication is the most preferable to clarify the interpretation of a requirement?

  1. E-mail
  2. Face-to-face
  3. Instant messaging
  4. Telephone

Answer(s): B



In a Scrum project, when would a requirement get added to the Product backlog?

  1. When it is developed, but cannot yet be released.
  2. When the team works on it for a particular release.
  3. When the customer requests a new requirement.

Answer(s): C



Share your comments for EXIN EX0-008 exam with other users:

L
labuschanka
11/16/2023 6:06:00 PM

i gave the microsoft azure az-500 tests and prepared from this site as it has latest mock tests available which helped me evaluate my performance and score 919/1000

M
Marianne
10/22/2023 11:57:00 PM

i cannot see the button to go to the questions

S
sushant
6/28/2023 4:52:00 AM

good questions

A
A\MAM
6/27/2023 5:17:00 PM

q-6 ans-b correct. https://docs.paloaltonetworks.com/pan-os/9-1/pan-os-cli-quick-start/use-the-cli/commit-configuration-changes

U
unanimous
12/15/2023 6:38:00 AM

very nice very nice

A
akminocha
9/28/2023 10:36:00 AM

please help us with 1z0-1107-2 dumps

J
Jefi
9/4/2023 8:15:00 AM

please upload the practice questions

T
Thembelani
5/30/2023 2:45:00 AM

need this dumps

A
Abduraimov
4/19/2023 12:43:00 AM

preparing for this exam is overwhelming. you cannot pass without the help of these exam dumps.

P
Puneeth
10/5/2023 2:06:00 AM

new to this site but i feel it is good

A
Ashok Kumar
1/2/2024 6:53:00 AM

the correct answer to q8 is b. explanation since the mule app has a dependency, it is necessary to include project modules and dependencies to make sure the app will run successfully on the runtime on any other machine. source code of the component that the mule app is dependent of does not need to be included in the exported jar file, because the source code is not being used while executing an app. compiled code is being used instead.

M
Merry
7/30/2023 6:57:00 AM

good questions

V
VoiceofMidnight
12/17/2023 4:07:00 PM

Delayed the exam until December 29th.

U
Umar Ali
8/29/2023 2:59:00 PM

A and D are True

V
vel
8/28/2023 9:17:09 AM

good one with explanation

G
Gurdeep
1/18/2024 4:00:15 PM

This is one of the most useful study guides I have ever used.

AI Tutor 👋 I’m here to help!