Which of the following requires the MOST availability from the business team?

  1. SDLC
  2. Scrum
  3. PRINCE2
  4. Waterfall

Answer(s): B



Which of the following software programs would be BEST to use to store information related to business transactions?

  1. Record management system
  2. Customer relationship management
  3. Enterprise resource planning
  4. Content management system

Answer(s): C



During a status meeting, the development team reviews work and finds an unforeseen dependency on one of the critical project activities. As a result, the project will most likely be delayed. Which of the following actions should the project manager MOST likely perform?

  1. Work with the project scheduler to update the project timeline.
  2. Communicate to the stakeholders about the updated timeline.
  3. Ask the development team to fast-track upcoming activities.
  4. Add two resources so the critical activities will finish on time.

Answer(s): A



Which of the following would be the NEXT document a project manager should update once the need to procure goods and/or services is identified?

  1. Memorandum of understanding
  2. Request for information
  3. Statement of work
  4. Non-disclosure agreement

Answer(s): C



A PM received feedback from the project sponsor that the resources involved in the project are unsure of their daily activities. Which of the following is the MOST effective step for the PM to take to ensure clarity within the team?

  1. Create a list of tasks and share it with the team.
  2. Resend the scope of work to the team.
  3. Review the Gantt chart weekly with the team.
  4. Have the project sponsor meet with the team.

Answer(s): C



A project manager has been informed that the delivery of required IT equipment will be delayed. Which of the following is the FIRST step the project manager should take?

  1. Make an impact assessment.
  2. Prepare a new purchase order.
  3. Select a new vendor.
  4. Create a risk register.

Answer(s): A



Which of the following BEST identifies the intent and purpose of a project closeout report?

  1. To provide documentation of lessons learned
  2. To document variances from the initial project baseline
  3. To validate that a project has been successfully completed
  4. To release resources and terminate all access rights

Answer(s): C



A PM is working with stakeholders in the discovery phase and comparing the cost of the project to the cost savings the project will produce when it is complete. The output of this exercise will produce the:

  1. ROI.
  2. SOW.
  3. RFI.
  4. RFP.

Answer(s): A



Share your comments for CompTIA PK0-002 exam with other users:

P
praveenkumar
11/20/2023 11:57:00 AM

very helpful to crack first attempt

A
asad Raza
5/15/2023 5:38:00 AM

please upload this exam

R
Reeta
7/17/2023 5:22:00 PM

please upload the c_activate22 dump questions with answer

W
Wong
12/20/2023 11:34:00 AM

q10 - the answer should be a. if its c, the criteria will meet if either the prospect is not part of the suppression lists or if the job title contains vice president

D
david
12/12/2023 12:38:00 PM

this was on the exam as of 1211/2023

T
Tink
7/24/2023 9:23:00 AM

great for prep

J
Jaro
12/18/2023 3:12:00 PM

i think in question 7 the first answer should be power bi portal (not power bi)

9
9eagles
4/7/2023 10:04:00 AM

on question 10 and so far 2 wrong answers as evident in the included reference link.

T
Tai
8/28/2023 5:28:00 AM

wonderful material

V
VoiceofMidnight
12/29/2023 4:48:00 PM

i passed!! ...but barely! got 728, but needed 720 to pass. the exam hit me with labs right out of the gate! then it went to multiple choice. protip: study the labs!

A
A K
8/3/2023 11:56:00 AM

correct answer for question 92 is c -aws shield

N
Nitin Mindhe
11/27/2023 6:12:00 AM

great !! it is really good

B
BailleyOne
11/22/2023 1:45:00 AM

explanations for the answers are to the point.

P
patel
10/25/2023 8:17:00 AM

how can rea next

M
MortonG
10/19/2023 6:32:00 PM

question: 128 d is the wrong answer...should be c

J
Jayant
11/2/2023 3:15:00 AM

thanks for az 700 dumps

B
Bipul Mishra
12/14/2023 7:12:00 AM

thank you for this tableau dumps . it will helpfull for tableau certification

H
hello
10/31/2023 12:07:00 PM

good content

M
Matheus
9/3/2023 2:14:00 PM

just testing if the comments are real

Y
yenvti2@gmail.com
8/12/2023 7:56:00 PM

very helpful for exam preparation

M
Miguel
10/5/2023 12:16:00 PM

question 11: https://help.salesforce.com/s/articleview?id=sf.admin_lead_to_patient_setup_overview.htm&type=5

N
Noushin
11/28/2023 4:52:00 PM

i think the answer to question 42 is b not c

S
susan sandivore
8/28/2023 1:00:00 AM

thanks for the dump

A
Aderonke
10/31/2023 12:51:00 AM

fantastic assessments

P
Priscila
7/22/2022 9:59:00 AM

i find the xengine test engine simulator to be more fun than reading from pdf.

S
suresh
12/16/2023 10:54:00 PM

nice document

W
Wali
6/4/2023 10:07:00 PM

thank you for making the questions and answers intractive and selectable.

N
Nawaz
7/18/2023 1:10:00 AM

answers are correct?

D
das
6/23/2023 7:57:00 AM

can i belive this dump

S
Sanjay
10/15/2023 1:34:00 PM

great site to practice for sitecore exam

J
jaya
12/17/2023 8:36:00 AM

good for students

B
Bsmaind
8/20/2023 9:23:00 AM

nice practice dumps

K
kumar
11/15/2023 11:24:00 AM

nokia 4a0-114 dumps

V
Vetri
10/3/2023 12:59:00 AM

great content and wonderful to have the answers with explanation

AI Tutor 👋 I’m here to help!