CIPS Strategic Programme Leadership L6M5 Dumps in PDF

Free CIPS L6M5 Real Questions (page: 2)

Joey is preparing an NEC contract for the construction of a new school.
He includes a lump-sum price of £5 million.
The contractor receives payment upon completion of specific milestones.
Q: In which section of the contract should this be detailed? Answer Options:

  1. Option A
  2. Z Clause
  3. W1 Option
  4. X Clause

Answer(s): A

Explanation:

In NEC contracts, pricing mechanisms are detailed in Options A-F (p.36). W clauses handle dispute resolution, X clauses cover secondary options, and Z clauses are additional conditions. [P.36]



Robyn has created a contract for a construction project and has used "The Red Book."
Q: Which professional organization is responsible for creating this contract? Answer Options:

  1. JCT
  2. NEC
  3. CIPS
  4. FIDIC

Answer(s): D

Explanation:

The Red Book is part of the FIDIC "Rainbow Suite" of contracts (p.40). FIDIC contracts are categorized by color, each serving a specific purpose in construction and engineering projects. [P.40]



In a fixed lump sum contract, this pricing mechanism does not allow for any changes in price. Is this statement TRUE?
Fixed lump sum contracts are widely used in construction and infrastructure projects.
Answer Options:

  1. Yes ­ the price is fixed before the contract is signed
  2. Yes ­ the contractor assumes all risks should they exceed the budget
  3. No ­ price changes are allowed as it is impossible to predict prices concretely in advance
  4. No ­ price variations are permitted if they are written into the contract

Answer(s): D

Explanation:

Fixed Lump Sum contracts allow limited price changes under specific conditions (p.55), such as client variation requests, force majeure, or inflation adjustments. Firm Fixed Price contracts, however, do not allow any changes. [P.55]



Joanne is preparing a contract for the construction of a large shopping center. The project includes 52 retail units, several restaurants, and a parking facility. Joanne's company has contracted Construct Ltd under a Turnkey project. She is using a Gantt chart as a schedule in the contract.
Q: What type of payment mechanism is being used in this contract? Answer Options:

  1. Fixed Lump Sum
  2. Bill of Quantity
  3. Activity Schedule
  4. Cost Reimbursable

Answer(s): C

Explanation:

The correct answer is Activity Schedule (p.60). A Gantt chart is a time-based project planning tool, typically used in Activity Schedule contracts, where payments are tied to the completion of specific tasks. Other payment methods, such as Fixed Lump Sum and Bill of Quantity, do not rely on this approach. [P.60]



In which scenario would a Cost Reimbursable contract be most suitable? Answer Options:

  1. A research project where the exact scope of work is unknown at the onset
  2. A construction project where raw material prices may fluctuate
  3. The creation of a new product, where time is critical, and the client wishes to reward the contractor for speedy delivery
  4. The manufacturing of food items, where the client may return raw materials that do not meet specifications

Answer(s): A

Explanation:

Cost Reimbursable contracts are widely used in research projects where the exact scope is uncertain (p.69). These contracts allow for flexibility in cost adjustments based on project progress. Option B describes a contract using cost-plus pricing, and Options C and D do not fit this contract model. [P.69]



Share your comments for CIPS L6M5 exam with other users:

N
Nobody
8/30/2023 9:54:00 PM

does this actually work? are they the exam questions and answers word for word?

S
Salah
7/23/2023 9:46:00 AM

thanks for providing these questions

R
Ritu
9/15/2023 5:55:00 AM

interesting

R
Ron
5/30/2023 8:33:00 AM

these dumps are pretty good.

S
Sowl
8/10/2023 6:22:00 PM

good questions

B
Blessious Phiri
8/15/2023 2:02:00 PM

dbua is used for upgrading oracle database

R
Richard
10/24/2023 6:12:00 AM

i am thrilled to say that i passed my amazon web services mls-c01 exam, thanks to study materials. they were comprehensive and well-structured, making my preparation efficient.

J
Janjua
5/22/2023 3:31:00 PM

please upload latest ibm ace c1000-056 dumps

M
Matt
12/30/2023 11:18:00 AM

if only explanations were provided...

R
Rasha
6/29/2023 8:23:00 PM

yes .. i need the dump if you can help me

A
Anonymous
7/25/2023 8:05:00 AM

good morning, could you please upload this exam again?

A
AJ
9/24/2023 9:32:00 AM

hi please upload sre foundation and practitioner exam questions

P
peter parker
8/10/2023 10:59:00 AM

the exam is listed as 80 questions with a pass mark of 70%, how is your 50 questions related?

B
Berihun
7/13/2023 7:29:00 AM

all questions are so important and covers all ccna modules

N
nspk
1/19/2024 12:53:00 AM

q 44. ans:- b (goto setup > order settings > select enable optional price books for orders) reference link --> https://resources.docs.salesforce.com/latest/latest/en-us/sfdc/pdf/sfom_impl_b2b_b2b2c.pdf(decide whether you want to enable the optional price books feature. if so, select enable optional price books for orders. you can use orders in salesforce while managing price books in an external platform. if you’re using d2c commerce, you must select enable optional price books for orders.)

M
Muhammad Rawish Siddiqui
12/2/2023 5:28:00 AM

"cost of replacing data if it were lost" is also correct.

A
Anonymous
7/14/2023 3:17:00 AM

pls upload the questions

M
Mukesh
7/10/2023 4:14:00 PM

good questions

E
Elie Abou Chrouch
12/11/2023 3:38:00 AM

question 182 - correct answer is d. ethernet frame length is 64 - 1518b. length of user data containing is that frame: 46 - 1500b.

D
Damien
9/23/2023 8:37:00 AM

i need this exam pls

N
Nani
9/10/2023 12:02:00 PM

its required for me, please make it enable to access. thanks

E
ethiopia
8/2/2023 2:18:00 AM

seems good..

W
whoAreWeReally
12/19/2023 8:29:00 PM

took the test last week, i did have about 15 - 20 word for word from this site on the test. (only was able to cram 600 of the questions from this site so maybe more were there i didnt review) had 4 labs, bgp, lacp, vrf with tunnels and actually had to skip a lab due to time. lots of automation syntax questions.

V
vs
9/2/2023 12:19:00 PM

no comments

J
john adenu
11/14/2023 11:02:00 AM

nice questions bring out the best in you.

O
Osman
11/21/2023 2:27:00 PM

really helpful

E
Edward
9/13/2023 5:27:00 PM

question #50 and question #81 are exactly the same questions, azure site recovery provides________for virtual machines. the first says that it is fault tolerance is the answer and second says disater recovery. from my research, it says it should be disaster recovery. can anybody explain to me why? thank you

M
Monti
5/24/2023 11:14:00 PM

iam thankful for these exam dumps questions, i would not have passed without this exam dumps.

A
Anon
10/25/2023 10:48:00 PM

some of the answers seem to be inaccurate. q10 for example shouldnt it be an m custom column?

P
PeterPan
10/18/2023 10:22:00 AM

are the question real or fake?

C
CW
7/11/2023 3:19:00 PM

thank you for providing such assistance.

M
Mn8300
11/9/2023 8:53:00 AM

nice questions

N
Nico
4/23/2023 11:41:00 PM

my 3rd purcahse from this site. these exam dumps are helpful. very helpful.

C
Chere
9/15/2023 4:21:00 AM

found it good

AI Tutor 👋 I’m here to help!