Joey is preparing an NEC contract for the construction of a new school.He includes a lump-sum price of £5 million.The contractor receives payment upon completion of specific milestones.Q: In which section of the contract should this be detailed? Answer Options:
Answer(s): A
In NEC contracts, pricing mechanisms are detailed in Options A-F (p.36). W clauses handle dispute resolution, X clauses cover secondary options, and Z clauses are additional conditions. [P.36]
Robyn has created a contract for a construction project and has used "The Red Book."Q: Which professional organization is responsible for creating this contract? Answer Options:
Answer(s): D
The Red Book is part of the FIDIC "Rainbow Suite" of contracts (p.40). FIDIC contracts are categorized by color, each serving a specific purpose in construction and engineering projects. [P.40]
In a fixed lump sum contract, this pricing mechanism does not allow for any changes in price. Is this statement TRUE?Fixed lump sum contracts are widely used in construction and infrastructure projects.Answer Options:
Fixed Lump Sum contracts allow limited price changes under specific conditions (p.55), such as client variation requests, force majeure, or inflation adjustments. Firm Fixed Price contracts, however, do not allow any changes. [P.55]
Joanne is preparing a contract for the construction of a large shopping center. The project includes 52 retail units, several restaurants, and a parking facility. Joanne's company has contracted Construct Ltd under a Turnkey project. She is using a Gantt chart as a schedule in the contract.Q: What type of payment mechanism is being used in this contract? Answer Options:
Answer(s): C
The correct answer is Activity Schedule (p.60). A Gantt chart is a time-based project planning tool, typically used in Activity Schedule contracts, where payments are tied to the completion of specific tasks. Other payment methods, such as Fixed Lump Sum and Bill of Quantity, do not rely on this approach. [P.60]
In which scenario would a Cost Reimbursable contract be most suitable? Answer Options:
Cost Reimbursable contracts are widely used in research projects where the exact scope is uncertain (p.69). These contracts allow for flexibility in cost adjustments based on project progress. Option B describes a contract using cost-plus pricing, and Options C and D do not fit this contract model. [P.69]
Share your comments for CIPS L6M5 exam with other users:
q47: intrusion prevention system is the correct answer, not patch management. by definition, there are no patches available for a zero-day vulnerability. the way to prevent an attacker from exploiting a zero-day vulnerability is to use an ips.
this is simple but tiugh as well
questão 4, segundo meu compilador local e o site https://www.jdoodle.com/online-java-compiler/, a resposta correta é "c" !
its very useful
i mastered my skills and aced the comptia 220-1102 exam with a score of 920/1000. i give the credit to for my success.
real questions
very helpful assessments
hi there, i would like to get dumps for this exam
i studied for the microsoft azure az-204 exam through it has 100% real questions available for practice along with various mock tests. i scored 900/1000.
please upload 1z0-1072-23 exam dups
i was hoping if you could please share the pdf as i’m currently preparing to give the exam.
i am looking for oracle 1z0-116 exam
where we can get the answer to the questions
nice questions
question 129 is completely wrong.
i need dump
love the site.
can you please upload it back?
could you please re-upload this exam? thanks a lot!
great about shared quiz
goood helping
pay attention to questions. they are very tricky. i waould say about 80 to 85% of the questions are in this exam dump.
wish you would allow more free questions
great simulation
very g inood
q35 should be a
sap c_ts450_2021
ecellent materil for unserstanding
good so far
this is way too informative
very helpfull
q.189 - answers are incorrect.
awesome job in getting these questions