Verity Fashion is a clothing manufacturer and has an order to create 10,000 pairs of flipflops for a retailer for the summer. The order was placed over the phone in February. The order has been completed and has been boxed up ready for delivery. The retailer calls Verity Fashion in June and says that the order is no longer required. What action can Verity Fashion take?
Answer(s): A
Verity can sue for damages. The order was placed over the phone meaning that there was a verbal contract in place. Contracts do not need to be written to be enforceable so option 2 is incorrect. There is no termination clause mentioned in the question so you can assume that there isn't one. This means that the retailer is committing a breach of the verbal contract by cancelling the order. Verity could therefore apply for damages. (Whether or not they'd be awarded is a different matter!). This question tests your understanding of when contracts can be terminated and remedies for breaches. See p. 134.
Which of the following is not a form of ADR (Alternative Dispute Resolution)?
Answer(s): B
Negotiation isn't an alternative dispute resolution because it's supposed to be the 'default' dispute resolution- the one you automatically do when a problem occurs. Only if negotiation fails should you turn to ADR. P. 142
Franky B's is a popular restaurant chain which is seeking a resolution to a conflict it has with its supplier of Fried Chicken. It is looking for a dispute resolution that does not involve the court but in which an expert third party will make a binding decision. Which is the most suitable dispute resolution method for Franky B's?
This is Adjudication. The other answers are incorrect- litigation involves the court. Conciliation and mediation do not provide binding decisions. P. 143
Perry is seeking a resolution to a conflict he has with his supplier. He wants a third party to make a binding and legally enforceable decision and wants the issue to remain confidential. He is considering litigation. Is this the best solution for Perry?
Answer(s): C
Perry should try adjudication. Litigation is public so there would be no confidentiality. Out of the four options only adjudication would provide Perry with what he needs; a binding decision which is confidential. See p.146 for more information on litigation.
Robert has a contract with Farmer Ted who provides his manufacturing firm with potatoes. There is a contract in place, signed by both parties that Ted will deliver 2 tonnes of potatoes per week. Due to changes in demand, Robert would like Ted to start providing 3 tonnes of potatoes every three weeks.What must be in place for this change to occur?
A variation clause and signed agreement by both parties is required to make the change. See p.16-17 for more information on contract variations. Note a 'notification of change' isn't valid unless it's accepted by the other party- so it's a good idea for both parties to sign to say they agree to the change.
Share your comments for CIPS L5M3 exam with other users:
the correct answer for the question 29 is d.
question no 22: correct answers: bc, 1 per session 1 per page 1 per component always
these are pretty useful
awesome
yes please upload
great job whoever put this together, for the greater good! thanks!
just started to view all questions for the exam
helpful material
hope for the best
will post exam has finished
really correct and good analyze!
excellent thanks a lot
will post once pass the cka exam
good content
q:32 answer has to be option c
nice questions
i really like the support team in this website. they are fast in communication and very helpful.
a good contemporary exam review
q23, its an array, isnt it? starts with [ and end with ]. its an array of objects, not object.
cool very helpfull
i just passed. this exam dumps is the same one from prepaway and examcollection. it has all the real test questions.
is this a valid prince2 practitioner dumps?
all are relatable questions
might help me to prepare for the exam
just paid and downlaod the 2 exams using the 50% sale discount. so far i was able to download the pdf and the test engine. all looks good.
i think it should be a,c. option d goes against the principle of building anything custom unless there are no work arounds available
very legible
is this exam accurate or helpful?
please upload dump, i have exam in 2 days
this is useful
question 232 answer should be perimeter not netowrk layer. wrong answer selected
hi team, could you please provide this dump ?
very helpful to clear the exam and understand the concept.
Keeping this site free takes real effort. We constantly battle automated scraping and unauthorized content copying. A quick account helps us protect the community and keep the site free.
To continue studying for your L5M3, please sign in or create a free account.