CIPS Managing Contractual Risk L5M3 Dumps in PDF

Free CIPS L5M3 Real Questions (page: 14)

Verity Fashion is a clothing manufacturer and has an order to create 10,000 pairs of flipflops for a retailer for the summer. The order was placed over the phone in February. The order has been completed and has been boxed up ready for delivery. The retailer calls Verity Fashion in June and says that the order is no longer required.
What action can Verity Fashion take?

  1. sue for damages as the flip flops have already been made and this incurred costs
  2. nothing- there is no written contract in place
  3. subcontract the manufacturing of the flipflops to a third party
  4. claim on insurance

Answer(s): A

Explanation:

Verity can sue for damages. The order was placed over the phone meaning that there was a verbal contract in place. Contracts do not need to be written to be enforceable so option 2 is incorrect. There is no termination clause mentioned in the question so you can assume that there isn't one. This means that the retailer is committing a breach of the verbal contract by cancelling the order. Verity could therefore apply for damages. (Whether or not they'd be awarded is a different matter!). This question tests your understanding of when contracts can be terminated and remedies for breaches. See p. 134.



Which of the following is not a form of ADR (Alternative Dispute Resolution)?

  1. mediation
  2. negotiation
  3. arbitration
  4. conciliation

Answer(s): B

Explanation:

Negotiation isn't an alternative dispute resolution because it's supposed to be the 'default' dispute resolution- the one you automatically do when a problem occurs. Only if negotiation fails should you turn to ADR. P. 142



Franky B's is a popular restaurant chain which is seeking a resolution to a conflict it has with its supplier of Fried Chicken. It is looking for a dispute resolution that does not involve the court but in which an expert third party will make a binding decision.
Which is the most suitable dispute resolution method for Franky B's?

  1. litigation
  2. adjudication
  3. conciliation
  4. mediation

Answer(s): B

Explanation:

This is Adjudication. The other answers are incorrect- litigation involves the court. Conciliation and mediation do not provide binding decisions. P. 143



Perry is seeking a resolution to a conflict he has with his supplier. He wants a third party to make a binding and legally enforceable decision and wants the issue to remain confidential. He is considering litigation. Is this the best solution for Perry?

  1. yes- litigation is the most appropriate for his requirements
  2. no- Perry should try mediation
  3. no- Perry should try Adjudication
  4. no - Perry should try Conciliation

Answer(s): C

Explanation:

Perry should try adjudication. Litigation is public so there would be no confidentiality. Out of the four options only adjudication would provide Perry with what he needs; a binding decision which is confidential. See p.146 for more information on litigation.



Robert has a contract with Farmer Ted who provides his manufacturing firm with potatoes. There is a contract in place, signed by both parties that Ted will deliver 2 tonnes of potatoes per week. Due to changes in demand, Robert would like Ted to start providing 3 tonnes of potatoes every three weeks.
What must be in place for this change to occur?

  1. a variation clause and a new liquidated damage fee
  2. a variation clause and a signed agreement by both parties
  3. a notification of change and adequate compensation
  4. a notification of change and indemnity

Answer(s): B

Explanation:

A variation clause and signed agreement by both parties is required to make the change. See p.16-17 for more information on contract variations. Note a 'notification of change' isn't valid unless it's accepted by the other party- so it's a good idea for both parties to sign to say they agree to the change.



Share your comments for CIPS L5M3 exam with other users:

M
Marianne
10/22/2023 11:57:00 PM

i cannot see the button to go to the questions

S
sushant
6/28/2023 4:52:00 AM

good questions

A
A\MAM
6/27/2023 5:17:00 PM

q-6 ans-b correct. https://docs.paloaltonetworks.com/pan-os/9-1/pan-os-cli-quick-start/use-the-cli/commit-configuration-changes

U
unanimous
12/15/2023 6:38:00 AM

very nice very nice

A
akminocha
9/28/2023 10:36:00 AM

please help us with 1z0-1107-2 dumps

J
Jefi
9/4/2023 8:15:00 AM

please upload the practice questions

T
Thembelani
5/30/2023 2:45:00 AM

need this dumps

A
Abduraimov
4/19/2023 12:43:00 AM

preparing for this exam is overwhelming. you cannot pass without the help of these exam dumps.

P
Puneeth
10/5/2023 2:06:00 AM

new to this site but i feel it is good

A
Ashok Kumar
1/2/2024 6:53:00 AM

the correct answer to q8 is b. explanation since the mule app has a dependency, it is necessary to include project modules and dependencies to make sure the app will run successfully on the runtime on any other machine. source code of the component that the mule app is dependent of does not need to be included in the exported jar file, because the source code is not being used while executing an app. compiled code is being used instead.

M
Merry
7/30/2023 6:57:00 AM

good questions

V
VoiceofMidnight
12/17/2023 4:07:00 PM

Delayed the exam until December 29th.

U
Umar Ali
8/29/2023 2:59:00 PM

A and D are True

V
vel
8/28/2023 9:17:09 AM

good one with explanation

G
Gurdeep
1/18/2024 4:00:15 PM

This is one of the most useful study guides I have ever used.

AI Tutor 👋 I’m here to help!