Which of the following statements about FIDIC Contracts are true? Select TWO:

  1. They are used in the construction industry
  2. They are more collaborative than NEC contracts
  3. Each party manages their own risks separately
  4. Early warning notices are given when risks arise
  5. Change control is called a 'Compensation Event'

Answer(s): A,C

Explanation:

1 and 3 are correct answers. Options 2,4, and 5 are true for NEC contracts - NEC is more collaborative than FIDIC, early warning notices are given and change controls are called 'Compensation Events'. See p.74 for more information on FIDIC and NEC Contracts. This does come up in the exam



Which of the following risks is associated with sourcing from low-cost countries? Select TWO:

  1. operational risks
  2. reputational risks
  3. geopolitical risks
  4. financial risks

Answer(s): B,C

Explanation:

The correct answers are reputational risks and geopolitical risks. This is according to p. 77 of the study guide. Although I personally feel this is a bit presumptive, painting all 'low-cost' countries with the same brush (are all 'low-cost countries' politically unstable and allow dodgy things that will affect your reputation?, this is what the textbook says ...



A large multi-national corporation has just been awarded a credit rating of C by the three main credit rating agencies.
What does this score signify?

  1. low risk
  2. average risk
  3. substantial risk
  4. in default

Answer(s): C

Explanation:

a C grade = substantial risk. This is based on the grading system of AAA-D and is explained on p. 80.
basically anything that isn't an A is bad.



A supplier of non-critical items has a low credit score, Which of the following actions should be taken? Select TWO options.

  1. replace the supplier as quickly as possible with a more financially stable supplier
  2. conduct a benchmarking exercise
  3. create a risk assessment and mitigation plan
  4. inform the CEO of the company

Answer(s): B,C

Explanation:

The correct answers are conduct benchmarking and create a risk assessment. This supplier provides low value and low risk products - therefore the fact they have a bad credit rating isn't too much of a risk to your company. It's worth doing a benchmarking exercise to compare their position to others in the market to see if there are any industry-wide trends, and to create a risk assessment and mitigation plan. This could involve working with the supplier to help them improve their credit score, for example by using more favourable payment terms so they have a better cash flow. There's no need to replace them immediately, and there's no need to tell the CEO- they probably have more important things to think about than a singular supplier of non-critical items See p.81



Envy Manufacturing has several factories located in countries with poor reputations for human rights. It is concerned about potential risks of child labour being used within the supply chain. Envy Manufacturing has therefore decided to enlist the support of a third party auditing company to audit its factories. How should these audits be conducted? Select TWO

  1. organised well in advance to allow the factory managers to prepare for the audit
  2. conduct on the spot visits with no warning
  3. conduct group interviews with workers to ensure that all voices are heard
  4. conduct private meetings with a selection of workers

Answer(s): B,D

Explanation:

2 and 4 are correct. Audits should be unscheduled so that any issues can't be covered up in advance. Interviews with workers should also be conducted in private as this will allow them to speak their mind with confidence.
Where interviews are conducted as a group there may be peer-pressure to say the correct thing. especially if there are managers around. see p.88 for information on Audits



Share your comments for CIPS L5M2 exam with other users:

N
Nobody
8/30/2023 9:54:00 PM

does this actually work? are they the exam questions and answers word for word?

S
Salah
7/23/2023 9:46:00 AM

thanks for providing these questions

R
Ritu
9/15/2023 5:55:00 AM

interesting

R
Ron
5/30/2023 8:33:00 AM

these dumps are pretty good.

S
Sowl
8/10/2023 6:22:00 PM

good questions

B
Blessious Phiri
8/15/2023 2:02:00 PM

dbua is used for upgrading oracle database

R
Richard
10/24/2023 6:12:00 AM

i am thrilled to say that i passed my amazon web services mls-c01 exam, thanks to study materials. they were comprehensive and well-structured, making my preparation efficient.

J
Janjua
5/22/2023 3:31:00 PM

please upload latest ibm ace c1000-056 dumps

M
Matt
12/30/2023 11:18:00 AM

if only explanations were provided...

R
Rasha
6/29/2023 8:23:00 PM

yes .. i need the dump if you can help me

A
Anonymous
7/25/2023 8:05:00 AM

good morning, could you please upload this exam again?

A
AJ
9/24/2023 9:32:00 AM

hi please upload sre foundation and practitioner exam questions

P
peter parker
8/10/2023 10:59:00 AM

the exam is listed as 80 questions with a pass mark of 70%, how is your 50 questions related?

B
Berihun
7/13/2023 7:29:00 AM

all questions are so important and covers all ccna modules

N
nspk
1/19/2024 12:53:00 AM

q 44. ans:- b (goto setup > order settings > select enable optional price books for orders) reference link --> https://resources.docs.salesforce.com/latest/latest/en-us/sfdc/pdf/sfom_impl_b2b_b2b2c.pdf(decide whether you want to enable the optional price books feature. if so, select enable optional price books for orders. you can use orders in salesforce while managing price books in an external platform. if you’re using d2c commerce, you must select enable optional price books for orders.)

M
Muhammad Rawish Siddiqui
12/2/2023 5:28:00 AM

"cost of replacing data if it were lost" is also correct.

A
Anonymous
7/14/2023 3:17:00 AM

pls upload the questions

M
Mukesh
7/10/2023 4:14:00 PM

good questions

E
Elie Abou Chrouch
12/11/2023 3:38:00 AM

question 182 - correct answer is d. ethernet frame length is 64 - 1518b. length of user data containing is that frame: 46 - 1500b.

D
Damien
9/23/2023 8:37:00 AM

i need this exam pls

N
Nani
9/10/2023 12:02:00 PM

its required for me, please make it enable to access. thanks

E
ethiopia
8/2/2023 2:18:00 AM

seems good..

W
whoAreWeReally
12/19/2023 8:29:00 PM

took the test last week, i did have about 15 - 20 word for word from this site on the test. (only was able to cram 600 of the questions from this site so maybe more were there i didnt review) had 4 labs, bgp, lacp, vrf with tunnels and actually had to skip a lab due to time. lots of automation syntax questions.

V
vs
9/2/2023 12:19:00 PM

no comments

J
john adenu
11/14/2023 11:02:00 AM

nice questions bring out the best in you.

O
Osman
11/21/2023 2:27:00 PM

really helpful

E
Edward
9/13/2023 5:27:00 PM

question #50 and question #81 are exactly the same questions, azure site recovery provides________for virtual machines. the first says that it is fault tolerance is the answer and second says disater recovery. from my research, it says it should be disaster recovery. can anybody explain to me why? thank you

M
Monti
5/24/2023 11:14:00 PM

iam thankful for these exam dumps questions, i would not have passed without this exam dumps.

A
Anon
10/25/2023 10:48:00 PM

some of the answers seem to be inaccurate. q10 for example shouldnt it be an m custom column?

P
PeterPan
10/18/2023 10:22:00 AM

are the question real or fake?

C
CW
7/11/2023 3:19:00 PM

thank you for providing such assistance.

M
Mn8300
11/9/2023 8:53:00 AM

nice questions

N
Nico
4/23/2023 11:41:00 PM

my 3rd purcahse from this site. these exam dumps are helpful. very helpful.

C
Chere
9/15/2023 4:21:00 AM

found it good

AI Tutor 👋 I’m here to help!