Describe the seven stages of the Tender Process and explain the reasons why the stages must be followed.

  1. See Explanation section for answer.

Answer(s): A

Explanation:

The purpose of the tendering process is to invite potential suppliers to bid to supply a product or service to the buying organization. Then buying organization select suitable suppliers, award con- tract and manage. The process is selected mostly when the need is a large or complex project or the law mandates it or it is in the company's policies to do so. The stages of the tendering process includes:

Stage 1: decide which style of tender to use. There are four types of tendering used within pro- curement and this include; 1) open 2) Restricted 3) Negotiated 4) Competitive Dialogue

Stage 2: Prepare invitation to tender (ITT): this stage is to prepare the document that will be made available to potential supplier. It should contain everything potential bidders will need to know to fully understand the need and to prepare and send a suitable RESPONSE it may likely in-clude; open letter, company details, overview of a project, evaluation criteria, submission date and so on.
Stage 3: send ITT: With fairness, transparency and equality, buyer will provide the documents to all potential suppliers at the same time and also provide exactly the same information/documents to all suppliers. If after receiving the ITT and some suppliers seek clarifications on anything in the documentation, buyers must give same response to identical questions to keep the process transparent and fair. Also, the response to each query to all bidders in the process. Failure to this may result in bidders who feel disadvantaged or discriminated in any form to submit a legal challenge. Supplier submitting a Legal challenge may cause delay in the process and eventually increase administrative cost for the buyer.

Stage 4: Buying organization receives responses to the Invitation to tender from suppliers (bids). Suppliers must adhere to the bid submission dead line included in the invitation to tender document. Any bid that arrives after the deadline must be left out of the process, or else this may result to other suppliers legally challenging the process.

Stage 5: Evaluate bid. The buying organization can now evaluate the bids based on the criteria in the ITT document. It is always thorough that cross-functional team evaluates the bids to guarantee complete fairness and ensure that the chosen bid is fit for purpose. In evaluating the bids, the cross- functional team will consider the bids in the following areas; supplier organization, ethics, price, sustainability, quality, payment, disposal, service level, location, warranty and risk.
Stage 6: Award contract and give feedback hence the buying organization wards the contract to the winning supplier. This can take place by a formal communication like a letter or an e-mail. Stage 7: Contract management. Contracts must be evaluated against the criteria in the invitation to tender.
The reasons why these stages must be followed includes;
1. Knowing the right TYPE of tender to use, reduces administration cost, for example, deciding to do restricted tendering to reduce the interest that are going to be sent in have already cut down on administrative cost.
2. The supplier can know what exactly the buyer's intentions are by developing description and the required specification.
3. To ensure that objectives of resorting to use the tendering style and the tendering process is achieved
4. To ensure that the organization generates added value by going through the stages.
5. To ensure that there are none unethical issues like fraud, bribes etc are not part of the system.
6. To ensure that the tendering process becomes transparent to all suppliers. These stages must be followed for transparency and fairness. Just like in stage 3: buyer send out the ITT to potential suppliers at the same time and providing them same information. Failure to this and bidders who feel disadvantaged or discriminated in any form may submit a legal challenge. Supplier submitting a Legal challenge may cause delay in the process and eventually increase administrative cost for the buyer.



Which four procurement cycle stages happen after the award of the contract?

  1. See Explanation section for answer.

Answer(s): A

Explanation:

The procurement cycle is the heart of purchasing, sourcing and supplying and should be followed in day-to-day practice in the industry. The procurement cycle has thirteen stages. Contract award is stage 9, and the stages after the contract award are;
Stage 10: ware house, logistic and receipt
Stage 11: Contract performance review and continuous improvement
Stage 12: SRM/SCM and contract management
Stage 13: Asset management, lessons learned, end of life.



Which four procurement cycle stages happen after the award of the contract?

  1. See Explanation section for answer.

Answer(s): A

Explanation:

The procurement cycle is the heart of purchasing, sourcing and supplying and should be followed in day-to-day practice in the industry. The procurement cycle has thirteen stages. Contract award is stage 9, and the stages after the contract award are;
Stage 10: ware house, logistic and receipt
Stage 11: Contract performance review and continuous improvement Stage 12: SRM/SCM and contract management
Stage 13: Asset management, lessons learned, end of life.



What does the acronym SMART stand for?

  1. See Explanation section for answer.

Answer(s): A

Explanation:

When the procurement professional is setting key performance indicator (KPI) where which the supplier performance will be monitored and managed. The KPI is expected to be SMART. SMART is an acronym that is used to set KPI and specification.
S - specific ,
M - measurable,
A - achievable,
R - relevant, and
T - timebound.



What does the acronym SMART stand for?

  1. See Explanation section for answer.

Answer(s): A

Explanation:

When the procurement professional is setting key performance indicator (KPI) where which the supplier performance will be monitored and managed. The KPI is expected to be SMART. SMART is an acronym that is used to set KPI and specification.
S - specific ,
M - measurable,
A - achievable,
R - relevant, and
T - timebound.



Viewing Page 7 of 40



Share your comments for CIPS L4M8 exam with other users:

Georgio 1/19/2024 8:15:00 AM

question 205 answer is b
Anonymous


Matthew Dievendorf 5/30/2023 9:37:00 PM

question 39, should be answer b, directions stated is being sudneted from /21 to a /23. a /23 has 512 ips so 510 hosts. and can make 4 subnets out of the /21
Anonymous


Adhithya 8/11/2022 12:27:00 AM

beautiful test engine software and very helpful. questions are same as in the real exam. i passed my paper.
UNITED ARAB EMIRATES


SuckerPumch88 4/25/2022 10:24:00 AM

the questions are exactly the same in real exam. just make sure not to answer all them correct or else they suspect you are cheating.
UNITED STATES


soheib 7/24/2023 7:05:00 PM

question: 78 the right answer i think is d not a
Anonymous


srija 8/14/2023 8:53:00 AM

very helpful
EUROPEAN UNION


Thembelani 5/30/2023 2:17:00 AM

i am writing this exam tomorrow and have dumps
Anonymous


Anita 10/1/2023 4:11:00 PM

can i have the icdl excel exam
Anonymous


Ben 9/9/2023 7:35:00 AM

please upload it
Anonymous


anonymous 9/20/2023 11:27:00 PM

hye when will post again the past year question for this h13-311_v3 part since i have to for my test tommorow…thank you very much
Anonymous


Randall 9/28/2023 8:25:00 PM

on question 22, option b-once per session is also valid.
Anonymous


Tshegofatso 8/28/2023 11:51:00 AM

this website is very helpful
SOUTH AFRICA


philly 9/18/2023 2:40:00 PM

its my first time exam
SOUTH AFRICA


Beexam 9/4/2023 9:06:00 PM

correct answers are device configuration-enable the automatic installation of webview2 runtime. & policy management- prevent users from submitting feedback.
NEW ZEALAND


RAWI 7/9/2023 4:54:00 AM

is this dump still valid? today is 9-july-2023
SWEDEN


Annie 6/7/2023 3:46:00 AM

i need this exam.. please upload these are really helpful
PAKISTAN


Shubhra Rathi 8/26/2023 1:08:00 PM

please upload the oracle 1z0-1059-22 dumps
Anonymous


Shiji 10/15/2023 1:34:00 PM

very good questions
INDIA


Rita Rony 11/27/2023 1:36:00 PM

nice, first step to exams
Anonymous


Aloke Paul 9/11/2023 6:53:00 AM

is this valid for chfiv9 as well... as i am reker 3rd time...
CHINA


Calbert Francis 1/15/2024 8:19:00 PM

great exam for people taking 220-1101
UNITED STATES


Ayushi Baria 11/7/2023 7:44:00 AM

this is very helpfull for me
Anonymous


alma 8/25/2023 1:20:00 PM

just started preparing for the exam
UNITED KINGDOM


CW 7/10/2023 6:46:00 PM

these are the type of questions i need.
UNITED STATES


Nobody 8/30/2023 9:54:00 PM

does this actually work? are they the exam questions and answers word for word?
Anonymous


Salah 7/23/2023 9:46:00 AM

thanks for providing these questions
Anonymous


Ritu 9/15/2023 5:55:00 AM

interesting
CANADA


Ron 5/30/2023 8:33:00 AM

these dumps are pretty good.
Anonymous


Sowl 8/10/2023 6:22:00 PM

good questions
UNITED STATES


Blessious Phiri 8/15/2023 2:02:00 PM

dbua is used for upgrading oracle database
Anonymous


Richard 10/24/2023 6:12:00 AM

i am thrilled to say that i passed my amazon web services mls-c01 exam, thanks to study materials. they were comprehensive and well-structured, making my preparation efficient.
Anonymous


Janjua 5/22/2023 3:31:00 PM

please upload latest ibm ace c1000-056 dumps
GERMANY


Matt 12/30/2023 11:18:00 AM

if only explanations were provided...
FRANCE


Rasha 6/29/2023 8:23:00 PM

yes .. i need the dump if you can help me
Anonymous