Which of the following should be considered when calculating ratios relating to a supplier's liquidity?
Answer(s): A
A buyer in the public sector has put an advert out asking for interested suppliers to express an interest in a potential tender activity to provide a facilities management contract to a hospital trust. The suppliers who have met that criteria are then sent a document detailing how they should submit their tender, how to price the opportunity, asks Questions relating to how they will deliver the service and gives a deadline for bids to be submitted. Which document have the suppliers ben sent?
Answer(s): B
This is an Invitation to Tender.The only other real document listed in Request for Quotation. This is incorrect because the document asks questions relating to how they will deliver the service. This means price isn't the only factor, which is the case for a RfQ.Request for Tender and Invitation to Quote are not real things.
Which of the following would you expect to find in an Invitation to Tender? Select THREE
Answer(s): A,D
An ITT would include details on the awarding body (usually a brief overview of the buyer), the deadline (bids must be received by a certain date) and qualifications required (such as ISO requirements or competency certificates of staff members if it's a service contract). You wouldn't find pricing schedules in an ITT (this would be provided by the supplier in response to the ITT), nor would you find risk assessments (a supplier might be asked to provide one as part of the quality assessment of the tender though).Invitation To Tender Simply Explained I Thornton & Lowe (thorntonandlowe.com)
Luke has sent out a Request for Information to test the waters of the supply market for a new product he is sourcing. He has received a high number of detailed documents back from suppliers. Which of the following is Luke now likely to know about the marketplace? Select THREE
Answer(s): A,B,C
The correct answers are; lead times, product competition and changes in the marketplace. You wouldn't expect to receive samples or costings from a Request for Information - rather, these should be expected as part of the Tender Competition
Achieving the 'five rights of procurement' is one of the key objectives of procurement managers. Which of the following are not considered one of the 5 rights? Select TWO.
Answer(s): B,C
ethics and environment are not a 'right of procurement'. The 5 rights are price, quality, quantity, time and place.
Share your comments for CIPS L4M4 exam with other users:
q 14 should be dmz sever1 and notepad.exe why does note pad have a 443 connection
question # 108, correct answers are business growth and risk reduction.
are these valid chfi questions
question: 162 should be dlp (b)
good exam questions
I have to say this is really close to real exam. Passed my exam with this.
good analytics question
this looks accurate
question 46, the answer should be data "virtualization" (not visualization).
its useful.
Pass this exam 3 days ago. The PDF version and the Xengine App is quite useful.
informative for me.
question 134s answer shoule be "dlp"
in 72 the answer must be [sys_user_has_role] table.
i appreciated the mix of multiple-choice and short answer questions. i passed my exam this morning.
great to find this website, thanks
examination questions seem to be relevant.
planning to take psm test
please allow to download
please provide dumps
is the answer to question 15 correct ? i feel like the answer should be b
its getting more technical
i think these questions are what i need.
helpful assessment
i am confused about the answers to the questions. do you know if the answers are correct?
hi, please make the dumps available for my upcoming examination.
good practice
so far it is really informative
hi i want it please please upload it
am preparing for exam ,just nice questions
please upload c_tadm_23 exam
can we get tdvan4 vantage data engineering pdf?
want to clear the exam.
could you please upload the dumps of sap c_sac_2302