B is a horticultural retailer with limited funds available to acquire new retail property. B's Finance Manager has analysed two potential property investments. Investing in property P shows an IRR of 21% while the IRR on property Q is 17%.The Finance Manager has also advised that the NPV for property P is $750K, while the NPV of property Q is $850K.The Board needs to choose between the two properties as it has insufficient funds for both. Based purely on the Finance Manager's analysis, which of the following is true?
Answer(s): C
RFD, a listed company, is considering making an investment in a risky new venture. RFD has a substantial cash surplus that will be used to acquire the necessary resources. It is unlikely that RFD would have been able to raise finance for this investment because the company is already highly geared.Which of the following statements about stakeholders' conflicting interests are true?
Answer(s): A,B,C
JHU has recently completed an eight year project. The project was evaluated at a discount rate of 10% and was accepted because the net present value was $18 million. In year 3 of the project there was a significant unexpected repair arising because of the implementation stage of the project was rushed and some checks on equipment were skipped to save time. The cost of this was $8 million.In year 8 of the project the costs of dismantling the project were $11 million more than anticipated because of unexpected changes to the law concerning disposal of industrial scrap. How should these findings be reflected in the post completion audit?
Answer(s): A
M built a large factory last year and it has just been completed. The initial outflows on this project have a present value of $400 million and the entire project has a net present value of $30 million.The initial phase of the project caused problems and there was an overspend of $35 million as there was unstable soil. The foundations had to be underpinned with large steel bars to ensure the building would be safe. There was no other suitable site for the project. The construction could not be abandoned as the site would have had very little commercial value. The Internal Audit department has been asked to carry out a post completion audit.What issues should it concentrate on?
DRAG DROP (Drag and Drop is not supported)A's directors do not believe that they always get value for money from their investment in capital projects. Over the past decade the company has invested in 55 projects that have cost more than $1m. They are considering introducing a system of post completion audit to see if this will help them to understand any problems they have had with projects in the past. They hope to use the results of the post completion audits to significantly improve the results of their capital investments State whether you agree or disagree with the points raised by A's directors.
Share your comments for CIMA P3 Risk Management (Online) exam with other users:
questions appear contemporary.
good to prepare in this site
very helpful to crack first attempt
please upload this exam
please upload the c_activate22 dump questions with answer
q10 - the answer should be a. if its c, the criteria will meet if either the prospect is not part of the suppression lists or if the job title contains vice president
this was on the exam as of 1211/2023
great for prep
i think in question 7 the first answer should be power bi portal (not power bi)
on question 10 and so far 2 wrong answers as evident in the included reference link.
wonderful material
i passed!! ...but barely! got 728, but needed 720 to pass. the exam hit me with labs right out of the gate! then it went to multiple choice. protip: study the labs!
correct answer for question 92 is c -aws shield
great !! it is really good
explanations for the answers are to the point.
how can rea next
question: 128 d is the wrong answer...should be c
thanks for az 700 dumps
thank you for this tableau dumps . it will helpfull for tableau certification
good content
just testing if the comments are real
very helpful for exam preparation
question 11: https://help.salesforce.com/s/articleview?id=sf.admin_lead_to_patient_setup_overview.htm&type=5
i think the answer to question 42 is b not c
thanks for the dump
fantastic assessments
i find the xengine test engine simulator to be more fun than reading from pdf.
nice document
thank you for making the questions and answers intractive and selectable.
answers are correct?
can i belive this dump
great site to practice for sitecore exam
good for students
nice practice dumps
Keeping this site free takes real effort. We constantly battle automated scraping and unauthorized content copying. A quick account helps us protect the community and keep the site free.
To continue studying for your P3 Risk Management (Online), please sign in or create a free account.