B is a horticultural retailer with limited funds available to acquire new retail property. B's Finance Manager has analysed two potential property investments. Investing in property P shows an IRR of 21% while the IRR on property Q is 17%.
The Finance Manager has also advised that the NPV for property P is $750K, while the NPV of property Q is $850K.
The Board needs to choose between the two properties as it has insufficient funds for both. Based purely on the Finance Manager's analysis, which of the following is true?

  1. Premises P is clearly better than property Q in all respects.
  2. Premises Q is clearly better than property P in all respects.
  3. Board members who wish to maximise return on capital employed will want property P while those who wish to maximise shareholder wealth will want property Q.
  4. Board members who wish to maximise return on capital employed will want property Q while those who wish to maximise shareholder wealth will want property P.

Answer(s): C



RFD, a listed company, is considering making an investment in a risky new venture. RFD has a substantial cash surplus that will be used to acquire the necessary resources. It is unlikely that RFD would have been able to raise finance for this investment because the company is already highly geared.
Which of the following statements about stakeholders' conflicting interests are true?

  1. RFD's shareholders are exposed to the systematic risk from this project and the directors are exposed to total risk.
  2. RFD's lenders are likely to suffer a greater risk than RFD's equity investors.
  3. Neither RFD's shareholders or lenders are likely to have the means to prevent the directors from making this investment.
  4. RFD's existing employees are likely to enjoy a significant upside risk from this project.
  5. The diversification of RFD's interests will reduce the risks for all stakeholders.

Answer(s): A,B,C



JHU has recently completed an eight year project. The project was evaluated at a discount rate of 10% and was accepted because the net present value was $18 million. In year 3 of the project there was a significant unexpected repair arising because of the implementation stage of the project was rushed and some checks on equipment were skipped to save time. The cost of this was $8 million.
In year 8 of the project the costs of dismantling the project were $11 million more than anticipated because of unexpected changes to the law concerning disposal of industrial scrap. How should these findings be reflected in the post completion audit?

  1. Poor project management cost the entity $6 million, to the nearest million.
  2. Poor project management cost the entity $11 million, to the nearest million.
  3. Poor project management cost the entity $5 million, to the nearest million.
  4. Poor project management cost the entity $16 million, to the nearest million.

Answer(s): A



M built a large factory last year and it has just been completed. The initial outflows on this project have a present value of $400 million and the entire project has a net present value of $30 million.

The initial phase of the project caused problems and there was an overspend of $35 million as there was unstable soil. The foundations had to be underpinned with large steel bars to ensure the building would be safe. There was no other suitable site for the project. The construction could not be abandoned as the site would have had very little commercial value. The Internal Audit department has been asked to carry out a post completion audit.
What issues should it concentrate on?

  1. The audit should consider the initial survey report when the land was purchased to see if the survey mentioned the unstable soil.
  2. The audit should look at documentation to ensure proper procedures were followed at all stages of the project.
  3. The audit should consider what lessons could be learned for future projects.
  4. The audit should find out who was to blame for the project being over budget.
  5. The audit should consider whether it should have built the factory without underpinning and sold it on quickly.

Answer(s): A,B,C



DRAG DROP (Drag and Drop is not supported)
A's directors do not believe that they always get value for money from their investment in capital projects. Over the past decade the company has invested in 55 projects that have cost more than $1m. They are considering introducing a system of post completion audit to see if this will help them to understand any problems they have had with projects in the past. They hope to use the results of the post completion audits to significantly improve the results of their capital investments State whether you agree or disagree with the points raised by A's directors.

  1. See Explanation section for answer.

Answer(s): A

Explanation:



Share your comments for CIMA P3 Risk Management (Online) exam with other users:

B
Bilal
8/22/2023 6:33:00 AM

i did attend the required cources and i need to be sure that i am ready to take the exam, i would ask you please to share the questions, to be sure that i am fit to proceed with taking the exam.

J
John
11/12/2023 8:48:00 PM

why only give explanations on some, and not all questions and their respective answers?

B
Biswa
11/20/2023 8:50:00 AM

refresh db knowledge

S
Shalini Sharma
10/17/2023 8:29:00 AM

interested for sap certification

E
ethan
9/24/2023 12:38:00 PM

could you please upload practice questions for scr exam ?

V
vijay joshi
8/19/2023 3:15:00 AM

please upload free oracle cloud infrastructure 2023 foundations associate exam braindumps

A
Ayodele Talabi
8/25/2023 9:25:00 PM

sweating! they are tricky

R
Romero
3/23/2022 4:20:00 PM

i never use these dumps sites but i had to do it for this exam as it is impossible to pass without using these question dumps.

J
John Kennedy
9/20/2023 3:33:00 AM

good practice and well sites.

N
Nenad
7/12/2022 11:05:00 PM

passed my first exam last week and pass the second exam this morning. thank you sir for all the help and these brian dumps.

L
Lucky
10/31/2023 2:01:00 PM

does anyone who attended exam csa 8.8, can confirm these questions are really coming ? or these are just for practicing?

P
Prateek
9/18/2023 11:13:00 AM

kindly share the dumps

I
Irfan
11/25/2023 1:26:00 AM

very nice content

P
php
6/16/2023 12:49:00 AM

passed today

D
Durga
6/23/2023 1:22:00 AM

hi can you please upload questions

J
JJ
5/28/2023 4:32:00 AM

please upload quetions

N
Norris
1/3/2023 8:06:00 PM

i passed my exam thanks to this braindumps questions. these questions are valid in us and i highly recommend it!

A
abuti
7/21/2023 6:10:00 PM

are they truely latest

C
Curtis Nakawaki
7/5/2023 8:46:00 PM

questions appear contemporary.

V
Vv
12/2/2023 6:31:00 AM

good to prepare in this site

P
praveenkumar
11/20/2023 11:57:00 AM

very helpful to crack first attempt

A
asad Raza
5/15/2023 5:38:00 AM

please upload this exam

R
Reeta
7/17/2023 5:22:00 PM

please upload the c_activate22 dump questions with answer

W
Wong
12/20/2023 11:34:00 AM

q10 - the answer should be a. if its c, the criteria will meet if either the prospect is not part of the suppression lists or if the job title contains vice president

D
david
12/12/2023 12:38:00 PM

this was on the exam as of 1211/2023

T
Tink
7/24/2023 9:23:00 AM

great for prep

J
Jaro
12/18/2023 3:12:00 PM

i think in question 7 the first answer should be power bi portal (not power bi)

9
9eagles
4/7/2023 10:04:00 AM

on question 10 and so far 2 wrong answers as evident in the included reference link.

T
Tai
8/28/2023 5:28:00 AM

wonderful material

V
VoiceofMidnight
12/29/2023 4:48:00 PM

i passed!! ...but barely! got 728, but needed 720 to pass. the exam hit me with labs right out of the gate! then it went to multiple choice. protip: study the labs!

A
A K
8/3/2023 11:56:00 AM

correct answer for question 92 is c -aws shield

N
Nitin Mindhe
11/27/2023 6:12:00 AM

great !! it is really good

B
BailleyOne
11/22/2023 1:45:00 AM

explanations for the answers are to the point.

P
patel
10/25/2023 8:17:00 AM

how can rea next

AI Tutor 👋 I’m here to help!