Which THREE of the following are advantages of changing from a 'top-down' to a 'bottom- up' (participative) style of budgeting?

  1. The budget will be based on information from employees who are familiar with the day to day activities.
  2. Motivation will improve due to a feeling of ownership of the budget.
  3. There will be increased commitment to organizational objectives.
  4. Budget setters will be forced to justify every item on the budget.
  5. There will be reduced likelihood of budgetary slack being built into the budgets for 'selfish' reasons.
  6. It will be less time-consuming for operational managers.

Answer(s): A,B,C



A company manufactures and sells a range of products. Relevant data for one unit of a particular product are as follows.



The company is using target costing to ensure that it achieves a contribution of 40% of the market selling price.

In order to achieve the target cost, by how much does the company need to reduce the variable cost per unit?

  1. $ 2.10
  2. $ 0.50
  3. $ 1.40
  4. $ 2.60

Answer(s): B



Four mutually exclusive projects have been appraised as follows using net present value (NPV), internal rate of return (IRR), accounting rate of return (ARR) and payback period (PP).



Recommend which of the projects should be chosen.

  1. Project A
  2. Project B
  3. Project C
  4. Project D

Answer(s): D



In an inflationary environment which is the correct way of calculating net present value (NPV)?

  1. Using nominal cash flows and a nominal discount rate.
  2. Forecasting the cash flows including the effect of inflation and then using a real discount rate.
  3. Using real cash flows and a nominal discount rate.
  4. Forecasting the cash flows excluding the effect of inflation and then using a nominal discount rate.

Answer(s): A



A company operates a divisional structure. The manager of division D receives a bonus based on the division's annual return on capital employed (ROCE).

A minimum ROCE of 20% must be achieved to receive any bonus and thereafter the bonus increases in line with increases in ROCE.

This year division D achieved a ROCE of 24% and the divisional manager received a large bonus.

The manager is considering an investment in a new machine for next year. The incremental ROCE earned by the machine is expected to be 19% although the ROCE for the division as a whole with the machine is expected to be 22%. Without the machine, ROCE is likely to be stable at 24%.

The cost of capital for the company as a whole is 18% per year.

Which of the following statements is correct?

  1. The manager will accept the investment because overall the division will earn a ROCE that exceeds the minimum target of 20%.
  2. The manager will reject the investment because it will result in a lower bonus than without the investment.
  3. The manager will accept the investment because it will earn a ROCE that is higher than the company's cost of capital.
  4. The manager will reject the investment because it will result in the receipt of no bonus.

Answer(s): B



Share your comments for CIMA P2 exam with other users:

S
shime
10/23/2023 10:03:00 AM

this is really very very helpful for mcd level 1

V
Vnu
6/3/2023 2:39:00 AM

very helpful!

S
Steve
8/17/2023 2:19:00 PM

question #18s answer should be a, not d. this should be corrected. it should be minvalidityperiod

R
RITEISH
12/24/2023 4:33:00 AM

thanks for the exact solution

S
SB
10/15/2023 7:58:00 AM

need to refer the questions and have to give the exam

M
Mike Derfalem
7/16/2023 7:59:00 PM

i need it right now if it was possible please

I
Isak
7/6/2023 3:21:00 AM

i need it very much please share it in the fastest time.

M
Maria
6/23/2023 11:40:00 AM

correct answer is d for student.java program

N
Nagendra Pedipina
7/12/2023 9:10:00 AM

q:37 c is correct

J
John
9/16/2023 9:37:00 PM

q6 exam topic: terramearth, c: correct answer: copy 1petabyte to encrypted usb device ???

S
SAM
12/4/2023 12:56:00 AM

explained answers

A
Andy
12/26/2023 9:35:00 PM

plan to take theaws certified developer - associate dva-c02 in the next few weeks

S
siva
5/17/2023 12:32:00 AM

very helpfull

M
mouna
9/27/2023 8:53:00 AM

good questions

B
Bhavya
9/12/2023 7:18:00 AM

help to practice csa exam

M
Malik
9/28/2023 1:09:00 PM

nice tip and well documented

R
rodrigo
6/22/2023 7:55:00 AM

i need the exam

D
Dan
6/29/2023 1:53:00 PM

please upload

A
Ale M
11/22/2023 6:38:00 PM

prepping for fsc exam

A
ahmad hassan
9/6/2023 3:26:00 AM

pd1 with great experience

Ž
Žarko
9/5/2023 3:35:00 AM

@t it seems like azure service bus message quesues could be the best solution

S
Shiji
10/15/2023 1:08:00 PM

helpful to check your understanding.

D
Da Costa
8/27/2023 11:43:00 AM

question 128 the answer should be static not auto

B
bot
7/26/2023 6:45:00 PM

more comments here

K
Kaleemullah
12/31/2023 1:35:00 AM

great support to appear for exams

B
Bsmaind
8/20/2023 9:26:00 AM

useful dumps

B
Blessious Phiri
8/13/2023 8:37:00 AM

making progress

N
Nabla
9/17/2023 10:20:00 AM

q31 answer should be d i think

V
vladputin
7/20/2023 5:00:00 AM

is this real?

N
Nick W
9/29/2023 7:32:00 AM

q10: c and f are also true. q11: this is outdated. you no longer need ownership on a pipe to operate it

N
Naveed
8/28/2023 2:48:00 AM

good questions with simple explanation

C
cert
9/24/2023 4:53:00 PM

admin guide (windows) respond to malicious causality chains. when the cortex xdr agent identifies a remote network connection that attempts to perform malicious activity—such as encrypting endpoint files—the agent can automatically block the ip address to close all existing communication and block new connections from this ip address to the endpoint. when cortex xdrblocks an ip address per endpoint, that address remains blocked throughout all agent profiles and policies, including any host-firewall policy rules. you can view the list of all blocked ip addresses per endpoint from the action center, as well as unblock them to re-enable communication as appropriate. this module is supported with cortex xdr agent 7.3.0 and later. select the action mode to take when the cortex xdr agent detects remote malicious causality chains: enabled (default)—terminate connection and block ip address of the remote connection. disabled—do not block remote ip addresses. to allow specific and known s

Y
Yves
8/29/2023 8:46:00 PM

very inciting

M
Miguel
10/16/2023 11:18:00 AM

question 5, it seems a instead of d, because: - care plan = case - patient = person account - product = product2;

AI Tutor 👋 I’m here to help!