B is a horticultural retailer with limited funds available to acquire new retail property. B's Finance Manager has analysed two potential property investments. Investing in property P shows an IRR of 21% while the IRR on property Q is 17%.The Finance Manager has also advised that the NPV for property P is $750K, while the NPV of property Q is $850K.The Board needs to choose between the two properties as it has insufficient funds for both. Based purely on the Finance Manager's analysis, which of the following is true?
Answer(s): C
RFD, a listed company, is considering making an investment in a risky new venture. RFD has a substantial cash surplus that will be used to acquire the necessary resources. It is unlikely that RFD would have been able to raise finance for this investment because the company is already highly geared.Which of the following statements about stakeholders' conflicting interests are true?
Answer(s): A,B,C
JHU has recently completed an eight year project. The project was evaluated at a discount rate of 10% and was accepted because the net present value was $18 million. In year 3 of the project there was a significant unexpected repair arising because of the implementation stage of the project was rushed and some checks on equipment were skipped to save time. The cost of this was $8 million.In year 8 of the project the costs of dismantling the project were $11 million more than anticipated because of unexpected changes to the law concerning disposal of industrial scrap. How should these findings be reflected in the post completion audit?
Answer(s): A
M built a large factory last year and it has just been completed. The initial outflows on this project have a present value of $400 million and the entire project has a net present value of $30 million.The initial phase of the project caused problems and there was an overspend of $35 million as there was unstable soil. The foundations had to be underpinned with large steel bars to ensure the building would be safe. There was no other suitable site for the project. The construction could not be abandoned as the site would have had very little commercial value. The Internal Audit department has been asked to carry out a post completion audit.What issues should it concentrate on?
DRAG DROP (Drag and Drop is not supported)A's directors do not believe that they always get value for money from their investment in capital projects. Over the past decade the company has invested in 55 projects that have cost more than $1m. They are considering introducing a system of post completion audit to see if this will help them to understand any problems they have had with projects in the past. They hope to use the results of the post completion audits to significantly improve the results of their capital investments State whether you agree or disagree with the points raised by A's directors.
Share your comments for CIMA CIMAPRA19-P03-1 exam with other users:
grazie mille. i got a satisfactory mark in my exam test today because of this exam dumps. sorry for my english.
some of the answers are incorrect. need to be reviewed.
so far so good
i am really liking it
thanks good stuff
need dump c_tadm_23
next time i will write a full review
first time using this site
please sent me oracle 1z0-1105-22 pdf
very helpful
good info about oml
very useful to practice
this website is very helpful.
good content
so challenging
17 should be d ,for morequery its scale out
nice question
yes.
good mateial
good practice exam
impressivre qustion
questions seem helpful
question 21 answer is alerts
am preparing for exam
good one thanks
only got thru 5 questions, need more to evaluate
q26 should be b
the aaa triad in information security is authentication, accounting and authorisation so the answer should be d 1, 3 and 5.
need to attend this
these are free brain dumps i understand, how can one get free pdf
provide access
good morning
please upload the ncp-mci 6.5 dumps, really need to practice this one. thanks guys
Keeping this site free takes real effort. We constantly battle automated scraping and unauthorized content copying. A quick account helps us protect the community and keep the site free.
To continue studying for your CIMAPRA19-P03-1, please sign in or create a free account.