Eton Ltd. operates a manufacturing process that produces product A. Information for this process last month is as follows:

(a) Opening work in progress - 2,500 kg valued at £2,000 for direct material and £1,500 for labour and overheads.

(b) Materials input - 25,000 kg at £2.10 per kg.

(c) Labour - £10,000

(d) Overheads - £5,000

(e) Output during the month - 20,000 kg.

(f) There were 7,500 units of closing work in progress which was complete as to materials and 30% complete as to conversion.

(g) Normal loss for the month was 3% of input and all losses have a scrap value of £1 per kg.
What was the average cost per kg of finished output during the month?

  1. £1.73
  2. £2.72
  3. £2.78
  4. £2.80

Answer(s): C



Refer to the Exhibit.



Fabex Ltd manufactures a household detergent called "Clear". The standard data for one of the chemicals used in production (chemical XTC) is as follows:

(a) 50 litres used per 100 litres of 'Clear' produced

(b) Budgeted monthly production is 1000 litres of 'Clear'.

The closing inventory of chemical XTC for November valued at standard price was as follows:

Actual results for the period during December were as follows:

(a) 500 litres of chemical XTC was purchased for £1300.

(b) 550 litres of chemical XTC was used.

(c) 900 litres of 'Clear' was produced.

It is company policy to extract the material price variance at the time of purchase.

What is the total direct material price variance (to the nearest whole number)?

  1. £50 adverse
  2. £50 favourable
  3. £55 adverse
  4. £55 favourable

Answer(s): A



In the process account, the accounting treatment of the value of the abnormal gain is:

  1. Credit Process account Debit Abnormal Gain account
  2. Debit Process account Credit Abnormal Gain account
  3. Credit Process account Debit Normal Loss account
  4. Debit Process account Credit Normal Loss account

Answer(s): B



CORRECT TEXT

Each unit of product GM requires 4 labour hours to be produced. 25% of the units will be completed during overtime hours.

Sales of 24,000 units are planned and finished goods inventory is budgeted to rise by 2,000 units.

If the wage rate is £6 per hour and the overtime premium is 50%, what is the budgeted labour cost?

  1. £702008

Answer(s): A



Refer to the exhibit.



T operates a process costing system. Data is available for Process A for the month of July.

Inputs for the month:

Normal losses are 15% of input and can be sold for $6 per kg. Actual output was 2,600 kg. There is no opening or closing work in progress for the period.

What is the value of the output from the process in the month?

  1. $49,291
  2. $46,538
  3. $43,784
  4. $45,120

Answer(s): C



Share your comments for CIMA CIMAPRA17-BA2-1 exam with other users:

Q
Qasim
6/11/2022 9:43:00 AM

just clear exam on 10/06/2202 dumps is valid all questions are came same in dumps only 2 new questions total 46 questions 1 case study with 5 question no lab/simulation in my exam please check the answers best of luck

C
Cath
10/10/2023 10:09:00 AM

q.112 - correct answer is c - the event registry is a module that provides event definitions. answer a - not correct as it is the definition of event log

S
Shiji
10/15/2023 1:31:00 PM

good and useful.

A
Ade
6/25/2023 1:14:00 PM

good questions

P
Praveen P
11/8/2023 5:18:00 AM

good content

A
Anastasiia
12/28/2023 9:06:00 AM

totally not correct answers. 21. you have one gcp account running in your default region and zone and another account running in a non-default region and zone. you want to start a new compute engine instance in these two google cloud platform accounts using the command line interface. what should you do? correct: create two configurations using gcloud config configurations create [name]. run gcloud config configurations activate [name] to switch between accounts when running the commands to start the compute engine instances.

P
Priyanka
7/24/2023 2:26:00 AM

kindly upload the dumps

N
Nabeel
7/25/2023 4:11:00 PM

still learning

G
gure
7/26/2023 5:10:00 PM

excellent way to learn

C
ciken
8/24/2023 2:55:00 PM

help so much

B
Biswa
11/20/2023 9:28:00 AM

understand sql col.

S
Saint Pierre
10/24/2023 6:21:00 AM

i would give 5 stars to this website as i studied for az-800 exam from here. it has all the relevant material available for preparation. i got 890/1000 on the test.

R
Rose
7/24/2023 2:16:00 PM

this is nice.

A
anon
10/15/2023 12:21:00 PM

q55- the ridac workflow can be modified using flow designer, correct answer is d not a

N
NanoTek3
6/13/2022 10:44:00 PM

by far this is the most accurate exam dumps i have ever purchased. all questions are in the exam. i saw almost 90% of the questions word by word.

E
eriy
11/9/2023 5:12:00 AM

i cleared the az-104 exam by scoring 930/1000 on the exam. it was all possible due to this platform as it provides premium quality service. thank you!

M
Muhammad Rawish Siddiqui
12/8/2023 8:12:00 PM

question # 232: accessibility, privacy, and innovation are not data quality dimensions.

V
Venkat
12/27/2023 9:04:00 AM

looks wrong answer for 443 question, please check and update

V
Varun
10/29/2023 9:11:00 PM

great question

D
Doc
10/29/2023 9:36:00 PM

question: a user wants to start a recruiting posting job posting. what must occur before the posting process can begin? 3 ans: comment- option e is incorrect reason: as part of enablement steps, sap recommends that to be able to post jobs to a job board, a user need to have the correct permission and secondly, be associated with one posting profile at minimum

I
It‘s not A
9/17/2023 5:31:00 PM

answer to question 72 is d [sys_user_role]

I
indira m
8/14/2023 12:15:00 PM

please provide the pdf

R
ribrahim
8/1/2023 6:05:00 AM

hey guys, just to let you all know that i cleared my 312-38 today within 1 hr with 100 questions and passed. thank you so much brain-dumps.net all the questions that ive studied in this dump came out exactly the same word for word "verbatim". you rock brain-dumps.net!!! section name total score gained score network perimeter protection 16 11 incident response 10 8 enterprise virtual, cloud, and wireless network protection 12 8 application and data protection 13 10 network défense management 10 9 endpoint protection 15 12 incident d

A
Andrew
8/23/2023 6:02:00 PM

very helpful

L
latha
9/7/2023 8:14:00 AM

useful questions

I
ibrahim
11/9/2023 7:57:00 AM

page :20 https://exam-dumps.com/snowflake/free-cof-c02-braindumps.html?p=20#collapse_453 q 74: true or false: pipes can be suspended and resumed. true. desc.: pausing or resuming pipes in addition to the pipe owner, a role that has the following minimum permissions can pause or resume the pipe https://docs.snowflake.com/en/user-guide/data-load-snowpipe-intro

F
Franklin Allagoa
7/5/2023 5:16:00 AM

i want hcia exam dumps

S
SSA
12/24/2023 1:18:00 PM

good training

B
BK
8/11/2023 12:23:00 PM

very useful

D
Deepika Narayanan
7/13/2023 11:05:00 PM

yes need this exam dumps

B
Blessious Phiri
8/15/2023 3:31:00 PM

these questions are a great eye opener

J
Jagdesh
9/8/2023 8:17:00 AM

thank you for providing these questions and answers. they helped me pass my exam. you guys are great.

T
TS
7/18/2023 3:32:00 PM

good knowledge

A
Asad Khan
11/1/2023 2:44:00 AM

answer 10 should be a because only a new project will be created & the organization is the same.

AI Tutor 👋 I’m here to help!