BCS ISTQB-ISEB Certified Tester Foundation Level ISEB-SWT2 Dumps in PDF

Free BCS ISEB-SWT2 Real Questions (page: 12)


Mix Questions Set A

What is important to do when working with software development models?

  1. To adapt the models to the context of project and product characteristics.
  2. To choose the waterfall model because it is the first and best proven model.
  3. To start with the V-model and then move to either iterative or incremental models.
  4. To only change the organization to fit the model and not vice versa.

Answer(s): A




Mix Questions Set A

Which statement below BEST describes non-functional testing?

  1. The process of testing an integrated system to verify that it meets specified requirements.
  2. The process of testing to determine the compliance of a system to coding standards.
  3. Testing without reference to the internal structure of a system.
  4. Testing system attributes, such as usability, reliability or maintainability.

Answer(s): A




Mix Questions Set A

For which of the following would maintenance testing be used?

  1. Correction of defects during the development phase.
  2. Planned enhancements to an existing operational system.
  3. Complaints about system quality during user acceptance testing.
  4. Integrating functions during the development of a new system.

Answer(s): B




Mix Questions Set A

Reporting Discrepancies as incidents is a part of which phase:

  1. Test Analysis and Design
  2. Test Implementation and execution
  3. Test Closure Activities
  4. Evaluating exit criteria and reporting

Answer(s): B




Mix Questions Set A

Important consequences of the impossibility of complete testing are:

  1. We can never be certain that the program is bug free.
  2. We have no definite stopping point for testing, which makes it easier for some managers to argue for very little testing.
  3. We have no easy answer for what testing tasks should always be required, because every task takes time that could be spent on other high importance tasks.
  4. All of the above

Answer(s): D



Share your comments for BCS ISEB-SWT2 exam with other users:

P
Puneeth
10/5/2023 2:06:00 AM

new to this site but i feel it is good

A
Ashok Kumar
1/2/2024 6:53:00 AM

the correct answer to q8 is b. explanation since the mule app has a dependency, it is necessary to include project modules and dependencies to make sure the app will run successfully on the runtime on any other machine. source code of the component that the mule app is dependent of does not need to be included in the exported jar file, because the source code is not being used while executing an app. compiled code is being used instead.

M
Merry
7/30/2023 6:57:00 AM

good questions

V
VoiceofMidnight
12/17/2023 4:07:00 PM

Delayed the exam until December 29th.

U
Umar Ali
8/29/2023 2:59:00 PM

A and D are True

V
vel
8/28/2023 9:17:09 AM

good one with explanation

G
Gurdeep
1/18/2024 4:00:15 PM

This is one of the most useful study guides I have ever used.