Your team is using a Scrum board and has many issues planned for future sprints. You need to configure a secondary board that· excludes those planned issues from the board but not from the reports · hides issues in real time when users select multiple conditions Which two board configurations satisfy the requirements? (Choose two.)
Answer(s): B,E
To exclude the planned issues from the board but not from the reports, you need to use a board sub- filter. A board sub-filter is an additional JQL query that is applied to the board filter to further refine the issues displayed on the board. The sub-filter does not affect the reports, which are based on the board filter only. To hide issues in real time when users select multiple conditions, you need to use quick filters. Quick filters are buttons that allow users to dynamically change the view of the board by applying one or more JQL queries. Users can select or deselect quick filters to show or hide issues that match the criteria.
Configuring filters, Configuring quick filters
Quang can transition issues from Resolved to Done using the workflow button on issues in his project. However, he cannot drag then from Resolved to Done on the project's Kanban board Identify a possible reason why.
Answer(s): C
If Quang can transition issues from Resolved to Done using the workflow button on issues in his project, but cannot drag them from Resolved to Done on the project's Kanban board, a possible reason is that the statuses are mapped to the same column. The columns on a Kanban board represent the stages of work in a project. Each column can have one or more statuses mapped to it. To move an issue from one column to another, you need to drag and drop it to a column that has a different status mapped to it. If the statuses are mapped to the same column, you cannot move the issue by dragging it on the board, but you can still use the workflow button to change its status.
Configuring columns, Moving an issue
The MR manager is unsure whether she wants a Scrum or Kanban board for her project. Identify one difference between the boards.
Answer(s): E
One difference between Scrum and Kanban boards is that only Scrum boards support selecting an estimation method. Estimation is a way of measuring how much work is required to complete an issue or a sprint. Scrum boards allow you to choose between story points, original time estimate, or issue count as estimation methods. Kanban boards do not have estimation methods, as they focus on managing the flow of work rather than planning sprints.
Configuring estimation and tracking, Estimating an issue
An issue was created with the following attributes:· Issue type: Story· Priority: Blocker· Labels: Tools, DevOps· Reporter: A.GrantAn excerpt of the board's swimlane configuration is shown.In which swimlane will the issue appear?
Answer(s): B
The issue will appear in the Expedite swimlane, because it matches the query priority = Blocker. Swimlanes are used to group issues on the board based on a common attribute, such as assignee, epic, or a custom query. The board's swimlane configuration shows that the first swimlane is Expedite, which has the query priority = Blocker. This means that any issue with a blocker priority will be placed in this swimlane, regardless of its other attributes. The other swimlanes have different queries that do not match the issue's attributes, such as type, labels, or reporter. Therefore, the issue will not appear in those swimlanes. The last swimlane is Everything Else, which is the default swimlane for any issue that does not match any of the previous queries. However, since the issue matches the Expedite query, it will not fall into this swimlane either. Hence, the correct answer is B.
[Configuring swimlanes], [Using swimlanes]
Your Scrum board has the following filter query:project in (ENG. DEV) and type in (Bug. Task) ORDER BY Priority ASC You have the necessary permissions but you are unable to drag an issue into a future sprint in the backlog.
Answer(s): D
The reason why you are unable to drag an issue into a future sprint in the backlog is that ranking is disabled. Ranking is a feature that allows you to order issues based on their relative priority or importance. Ranking is enabled by adding "ORDER BY Rank ASC" or "ORDER BY Rank DESC" to your board filter query. Ranking is required for Scrum boards, as it determines the order of issues in your backlog and sprints. If ranking is disabled, you cannot drag and drop issues in your backlog or plan future sprints.
Ranking an issue, Configuring filters
Share your comments for ATLASSIAN ACP-610 exam with other users:
i have learning disability and this exam dumps allowed me to focus on the actual questions and not worry about notes and the those other study materials.
165 should be apt
please upload the dumps, real need of them
any recent feeedback?
question number 2 is indicating you are giving proper questions. observe and change properly.
passed today.40% questions were new.litwere case study,lots of new questions on afd,ratelimit,tm,lb,app gatway.got 2 set series of questions which are not present here.questions on azure cyclecloud, no.of vnet/vms required for implimentation,blueprints assignment/management group etc
practice test
want the dumps for emc content management server programming(cmsp)
brilliant and helpful
q75. azure files is pass
very helpful
thank you for these questions. it helped a lot.
how do i get the h12-724 dumps
nice data dumps
answers are correct
good explanation
hi team just want to know if there is any update version of the exam 350-401
helpful on 2017 scrum guide
planning to attempt for the exam.
pleaseee upload
thanks ly so i have information cia
hello team, i need sap qm dumps for practice
it’s good but not senatios based
q.119 - the correct answer is b - they are not captured in an update set as theyre data.
good matter
please upload c_sacp_2308
please upload the dump. thanks very much !!
good questions
hi, could you please update the latest dump version
this question is keep repeat : you are developing a sales application that will contain several azure cloud services and handle different components of a transaction. different cloud services will process customer orders, billing, payment, inventory, and shipping. you need to recommend a solution to enable the cloud services to asynchronously communicate transaction information by using xml messages. what should you include in the recommendation?
great questions
its realy good
oracle 1z0-1059-22 dumps
please share me the pdf..