To facilitate transportation efficiency and inventory management, companies frequently use:

  1. automated storage/retrieval systems (AS/RS).
  2. small lot sizes.
  3. standardized containers.
  4. contract carriers.

Answer(s): C

Explanation:

Standardized containers are containers that have uniform dimensions and specifications, such as pallets, crates, boxes, etc. Standardized containers can facilitate transportation efficiency and inventory management by reducing the handling time, increasing the loading capacity, improving the space utilization, and simplifying the packaging and labeling processes. Standardized containers can also enable the use of automated storage/retrieval systems (AS/RS) and other technologies that require consistent dimensions and weights of the items.


Reference:

CPIM Part 2 Exam Content Manual, Domain 7: Plan and Manage Distribution, Section 7.1: Distribution Network Design, p. 38.



A statistical safety stock calculation would be appropriate for:

  1. components used in multiple end items.
  2. new products at time of introduction.
  3. end items with stable demand.
  4. supply-constrained raw materials.

Answer(s): C

Explanation:

A statistical safety stock calculation is a method to determine the optimal amount of safety stock based on the demand variability, the lead time variability, and the desired service level. A statistical safety stock calculation would be appropriate for end items with stable demand, because these items have a predictable demand pattern and a low coefficient of variation. For items with unstable or unpredictable demand, such as components used in multiple end items, new products at time of introduction, or supply-constrained raw materials, a statistical safety stock calculation may not be accurate or reliable, and other methods such as judgmental or simulation-based approaches may be preferred.


Reference:

CPIM Part 2 Exam Content Manual, Domain 5: Plan and Manage Inventory, Section 5.4: Inventory Management Techniques, p. 29.



A part is sold as a service part, and it is also used as a component in another part.
Which of the following statements about the planning for this part is true?

  1. Its low-level code is zero.
  2. The material requirements for the part will be understated.
  3. The service part demand can be included in the gross requirements.
  4. It shouldn't have any safety stock.

Answer(s): C

Explanation:

A part that is sold as a service part and also used as a component in another part is called a dual- sourced item. A dual-sourced item has two sources of demand: the external demand from the customers who buy the service part, and the internal demand from the parent part that uses the component. The planning for a dual-sourced item should include both sources of demand in the gross requirements, so that the net requirements can be calculated correctly. The service part demand can be included in the gross requirements by using a planning bill of material, which is a special bill of material that shows the relationship between a parent item and its service parts. A planning bill of material allows the system to explode the service part demand to the component level and generate planned orders for both the service part and the component. The other statements about the planning for this part are false. Its low-level code is not zero, because it is not an independent item. It has a higher low-level code than its parent item, because it is a component of another item. The material requirements for the part will not be understated, if both sources of demand are included in the gross requirements. It should have some safety stock, to protect against demand and supply uncertainties.


Reference:

CPIM Part 2 Exam Content Manual, Domain 4: Plan and Manage Supply, Section 4.2: Material Requirements Planning (MRP), p. 22-23.



The benefits of standardized work include:

  1. consistent cycle time.
  2. more innovation.
  3. less finished goods inventory.
  4. shorter takt time.

Answer(s): A

Explanation:

Standardized work is a method of organizing work processes to improve efficiency, quality, and safety1. One of the benefits of standardized work is consistent cycle time, which is the time it takes to complete a task or a process. By standardizing the work sequence, the takt time, and the standard inventory, standardized work reduces the variability and unpredictability of the work flow, and ensures that each task or process is performed in a consistent and optimal manner2. Consistent cycle time can lead to other benefits, such as improved customer satisfaction, reduced waste, increased productivity, and enhanced quality3.


Reference:

Standardized Work: What Is It and Where Is It Used? - TWI Institute What is Standard Work: Benefits & Applications | SafetyCulture Standard Work: The Foundation for Kaizen - Lean Smarts



Long lead-time items with stable demand would best be supported by a supply chain:

  1. using a pull system.
  2. linked through an enterprise resources planning (ERP) system.
  3. designed to be responsive.
  4. positioning inventory close to the consumer.

Answer(s): D

Explanation:

Long lead-time items are items that take a long time to procure, produce, or deliver. Stable demand means that the demand for these items is predictable and does not fluctuate much over time. A supply chain that supports long lead-time items with stable demand would best be designed to position inventory close to the consumer, because this would reduce the delivery time and improve the customer service level. Positioning inventory close to the consumer also reduces the transportation costs and risks associated with long-distance shipments. A supply chain that uses a pull system, which is based on actual customer orders rather than forecasts, may not be suitable for long lead-time items, because it may not be able to meet the customer demand in a timely manner. A supply chain that is linked through an enterprise resources planning (ERP) system, which is a software system that integrates various business functions and processes, may improve the visibility and coordination of the supply chain, but it does not necessarily reduce the lead time or position inventory close to the consumer. A supply chain that is designed to be responsive, which means that it can quickly adapt to changes in demand or other variables, may not be necessary for long lead- time items with stable demand, because these items have low demand uncertainty and variability.


Reference:

Inventory Positioning | Supply Chain Resource Cooperative Push System vs. Pull System: Adopting A Hybrid Approach To MRP What Is Inventory Positioning in Supply Chain Management?



Share your comments for APICS CPIM-Part-2 exam with other users:

S
Samir
8/1/2023 3:07:00 PM

very useful tools

S
Saeed
11/7/2023 3:14:00 AM

looks a good platform to prepare az-104

M
Matiullah
6/24/2023 7:37:00 AM

want to pass the exam

S
SN
9/5/2023 2:25:00 PM

good resource

Z
Zoubeyr
9/8/2023 5:56:00 AM

question 11 : d

U
User
8/29/2023 3:24:00 AM

only the free dumps will be enough for pass, or have to purchase the premium one. please suggest.

C
CW
7/6/2023 7:37:00 PM

good questions. thanks.

F
Farooqi
11/21/2023 1:37:00 AM

good for practice.

I
Isaac
10/28/2023 2:30:00 PM

great case study

M
Malviya
2/3/2023 9:10:00 AM

the questions in this exam dumps is valid. i passed my test last monday. i only whish they had their pricing in inr instead of usd. but it is still worth it.

R
rsmyth
5/18/2023 12:44:00 PM

q40 the answer is not d, why are you giving incorrect answers? snapshot consolidation is used to merge the snapshot delta disk files to the vm base disk

K
Keny
6/23/2023 9:00:00 PM

thanks, very relevant

M
Muhammad Rawish Siddiqui
11/29/2023 12:14:00 PM

wrong answer. it is true not false.

J
Josh
7/10/2023 1:54:00 PM

please i need the mo-100 questions

V
VINNY
6/2/2023 11:59:00 AM

very good use full

A
Andy
12/6/2023 5:56:00 AM

very valid questions

M
Mamo
8/12/2023 7:46:00 AM

will these question help me to clear pl-300 exam?

M
Marial Manyang
7/26/2023 10:13:00 AM

please provide me with these dumps questions. thanks

A
Amel Mhamdi
12/16/2022 10:10:00 AM

in the pdf downloaded is write google cloud database engineer i think that it isnt the correct exam

A
Angel
8/30/2023 10:58:00 PM

i think you have the answers wrong regarding question: "what are three core principles of web content accessibility guidelines (wcag)? answer: robust, operable, understandable

S
SH
5/16/2023 1:43:00 PM

these questions are not valid , they dont come for the exam now

S
sudhagar
9/6/2023 3:02:00 PM

question looks valid

V
Van
11/24/2023 4:02:00 AM

good for practice

D
Divya
8/2/2023 6:54:00 AM

need more q&a to go ahead

R
Rakesh
10/6/2023 3:06:00 AM

question 59 - a newly-created role is not assigned to any user, nor granted to any other role. answer is b https://docs.snowflake.com/en/user-guide/security-access-control-overview

N
Nik
11/10/2023 4:57:00 AM

just passed my exam today. i saw all of these questions in my text today. so i can confirm this is a valid dump.

D
Deep
6/12/2023 7:22:00 AM

needed dumps

T
tumz
1/16/2024 10:30:00 AM

very helpful

N
NRI
8/27/2023 10:05:00 AM

will post once the exam is finished

K
kent
11/3/2023 10:45:00 AM

relevant questions

Q
Qasim
6/11/2022 9:43:00 AM

just clear exam on 10/06/2202 dumps is valid all questions are came same in dumps only 2 new questions total 46 questions 1 case study with 5 question no lab/simulation in my exam please check the answers best of luck

C
Cath
10/10/2023 10:09:00 AM

q.112 - correct answer is c - the event registry is a module that provides event definitions. answer a - not correct as it is the definition of event log

S
Shiji
10/15/2023 1:31:00 PM

good and useful.

A
Ade
6/25/2023 1:14:00 PM

good questions

AI Tutor 👋 I’m here to help!