The question below is based on the following chart of values relative to upper and lower control limits:

Which of the following types of variation is shown?

  1. Special
  2. Periodic
  3. Common
  4. Assignable

Answer(s): C



The primary reason for using an empty conveyance container as a triggering signal is to:

  1. communicate the need for material.
  2. keep the original container filled with material.
  3. pull material downstream.
  4. push material downstream.

Answer(s): A



Which of the following actions helps product design and development pursue a strategy of first-to-market?

  1. Coordinating with product engineering
  2. Developing warranty specifications
  3. Finding the lowest-cost suppliers
  4. Flow-charting current processes

Answer(s): A



Operations management should measure the workload resulting from manufacturing orders for which of the following reasons?

  1. Determining order priority
  2. Controlling queues
  3. Planning materials
  4. Planning yields

Answer(s): B



A company is gathering data as to why the machine is consistently shutting down. What methodology should a company pursue first?

  1. 5S
  2. Plan-do-check-act
  3. Kaizen event
  4. Statistical process control

Answer(s): B



Share your comments for APICS CPIM-ECO exam with other users:

V
vel
8/28/2023 9:17:09 AM

good one with explanation

G
Gurdeep
1/18/2024 4:00:15 PM

This is one of the most useful study guides I have ever used.

AI Tutor 👋 I’m here to help!