APICS CPIM-8.0 Exam (page: 6)
APICS Certified in Planning and Inventory Management (CPIM 8.0)
Updated on: 09-Feb-2026

Viewing Page 6 of 31

During the sales and operations planning (S&OP) process, which of the following tasks is the primary responsibility of the functional representatives on the supply planning team?

  1. Identifying reasons why the demand plan is not realistic
  2. Communicating when an event will prevent meeting the supply plan
  3. Ensuring that the functional objectives are considered when developing the plans
  4. Understanding how to use the plan to improve functional performance

Answer(s): C

Explanation:

The supply planning team is responsible for developing a supply plan that balances the demand plan with the available resources and capacities. The functional representatives on the supply planning team, such as production, procurement, engineering, and finance, need to ensure that their functional objectives are considered when developing the plans. For example, production needs to consider the impact of the supply plan on the production schedule, capacity utilization, and labor requirements. Procurement needs to consider the impact of the supply plan on the supplier relationships, lead times, and inventory levels. Engineering needs to consider the impact of the supply plan on the product design, quality, and innovation. Finance needs to consider the impact of the supply plan on the costs, revenues, and profitability. By ensuring that the functional objectives are considered, the supply planning team can create a feasible and optimal supply plan that aligns with the overall business strategy.


Reference:

1 S&OP: A Comprehensive Overview of Sales and Operations Planning 3 2 CPIM Exam Reference - Association for Supply Chain Management 1



An example of a cradle-to-cradle sustainability model would be:

  1. a laundry service collects dirty baby clothes from families; cleans the clothes in large, efficient batches; and then sorts and delivers the clothes back to each family.
  2. a coffee shop collects paper waste in its restaurants, has a selected supplier collect the paper waste to be recycled, and then purchases paper products from that supplier.
  3. a company uses wood that has been gathered from multiple sources to construct items, such as beds and toys for babies and young children.
  4. a bank offers the lowest interest rates on loans to firms that are committed to using recycled materials and implementing zero-waste initiatives in their processes.

Answer(s): B

Explanation:

A cradle-to-cradle sustainability model is a design concept that aims to create products that can be reused or recycled indefinitely, without generating any waste or pollution. It mimics the natural cycles of nature, where everything is a nutrient for something else. A cradle-to-cradle model differs from a cradle-to-grave model, which follows a linear path of production, consumption, and disposal. Option B is an example of a cradle-to-cradle model, because the paper waste from the coffee shop is collected and recycled by a supplier, who then provides new paper products to the coffee shop. This creates a closed loop of material flow, where nothing is wasted and the paper is continuously reused. Option A is not a cradle-to-cradle model, because the laundry service does not reuse or recycle the baby clothes. It only cleans and delivers them, but does not prevent them from eventually ending up in the landfill.
Option C is not a cradle-to-cradle model, because the company does not ensure that the wood it uses is from sustainable sources, or that the products it makes can be easily disassembled and recycled. It also does not consider the environmental impacts of transporting the wood from different locations. Option D is not a cradle-to-cradle model, because the bank does not directly influence the design or production of the products that the firms use. It only provides financial incentives for them to adopt more sustainable practices, but does not guarantee that they will follow a cradle-to-cradle approach.


Reference:

* Cradle-to-Cradle for Sustainable Development: From Ecodesign to Circular Economy
* Cradle to Cradle ­ Sustainability Guide



What priority control technique is most appropriate for a firm using a cellular production system?

  1. Shortest processing time (SPT) rule
  2. Distribution requirements planning (DRP)
  3. Pull production activity control (PAC)
  4. Push production activity control (PAC)

Answer(s): C

Explanation:

A cellular production system is a type of lean manufacturing system that reduces waste and improves efficiency by grouping machines and workers into cells that can produce a complete product or a product family. A pull production activity control (PAC) technique is most appropriate for a cellular production system because it allows the cells to produce only what is needed by the downstream processes or customers, thus minimizing inventory and overproduction. A pull PAC technique also enables quick response to changes in demand and feedback from quality control. A push PAC technique, on the other hand, is based on predetermined schedules and forecasts, which may not match the actual demand and may result in excess inventory and waste. The shortest processing time

(SPT) rule and the distribution requirements planning (DRP) are not specific to cellular production systems and do not take into account the customer demand or the cell capacity.


Reference:

* CPIM Part 2 Exam Content Manual, p. 49
* Cellular Manufacturing: A Comprehensive Guide
* Cellular manufacturing - Wikipedia



Which of the following circumstances would cause a move from acceptance sampling to 100% inspection?

  1. History shows that the quality level has been stable from lot to lot.
  2. The company uses one of its qualified suppliers.
  3. Downstream operators encounter recurring defects.
  4. The percent of defects is expected to be greater than 5%.

Answer(s): C

Explanation:

Acceptance sampling is a statistical quality control technique that involves inspecting a sample of products or materials from a lot and deciding whether to accept or reject the lot based on the sample results. Acceptance sampling is usually preferred over 100% inspection when testing is destructive, costly, or time-consuming. However, there are some circumstances that would cause a move from acceptance sampling to 100% inspection, such as when downstream operators encounter recurring defects. This means that the acceptance sampling plan is not effective in detecting and preventing defective products or materials from reaching the next stage of the production process,

which may result in rework, scrap, customer complaints, or safety issues. In this case, 100% inspection may be necessary to ensure that every product or material meets the quality standards and specifications, and to identify and correct the root causes of the defects.


Reference:

1 Acceptance sampling - Wikipedia 4 2 100% Inspection or Sampling Inspection? Which is Best. 3 CPIM Exam Reference - Association for Supply Chain Management 1



In pyramid forecasting, the "roll up" process begins with:

  1. combining individual product item forecasts into forecasts for product families.
  2. combining forecasts for product families into a total business forecast.
  3. allocating total business forecast changes to product families.
  4. allocating product family forecast changes to individual products.

Answer(s): A

Explanation:

Pyramid forecasting is a method of forecasting that uses a hierarchical structure of data to improve the accuracy and consistency of the forecasts. The lowest level of the pyramid represents the most detailed data, such as individual product items, while the higher levels represent more aggregated data, such as product families or total business. The "roll up" process is the process of aggregating the forecasts from the lower level to the higher level, starting with the most detailed level. This process helps to align the forecasts across different levels and reduce the forecast error.


Reference:

1: Pyramid Forecasting Process 2: Rolling Forecast Model | FP&A Tutorial + Excel Template
3: ROLL-UP FORECASTS



Viewing Page 6 of 31



Share your comments for APICS CPIM-8.0 exam with other users:

Marc blue 9/15/2023 4:11:00 AM

great job. hope this helps out.
UNITED STATES


Anne 9/13/2023 2:33:00 AM

upload please. many thanks!
Anonymous


pepe el toro 9/12/2023 7:55:00 PM

this is so interesting
Anonymous


Antony 11/28/2023 12:13:00 AM

great material thanks
AUSTRALIA


Thembelani 5/30/2023 2:22:00 AM

anyone who wrote this exam recently
Anonymous


P 9/16/2023 1:27:00 AM

ok they re good
Anonymous


Jorn 7/13/2023 5:05:00 AM

relevant questions
UNITED KINGDOM


AM 6/20/2023 7:54:00 PM

please post
UNITED STATES


Nagendra Pedipina 7/13/2023 2:22:00 AM

q:42 there has to be a image in the question to choose what does it mean from the options
INDIA


BrainDumpee 11/18/2023 1:36:00 PM

looking for cphq dumps, where can i find these for free? please and thank you.
UNITED STATES


sheik 10/14/2023 11:37:00 AM

@aarun , thanks for the information. it would be great help if you share your email
Anonymous


Random user 12/11/2023 1:34:00 AM

1z0-1078-23 need this dumps
Anonymous


labuschanka 11/16/2023 6:06:00 PM

i gave the microsoft azure az-500 tests and prepared from this site as it has latest mock tests available which helped me evaluate my performance and score 919/1000
Anonymous


Marianne 10/22/2023 11:57:00 PM

i cannot see the button to go to the questions
Anonymous


sushant 6/28/2023 4:52:00 AM

good questions
EUROPEAN UNION


A\MAM 6/27/2023 5:17:00 PM

q-6 ans-b correct. https://docs.paloaltonetworks.com/pan-os/9-1/pan-os-cli-quick-start/use-the-cli/commit-configuration-changes
UNITED STATES


unanimous 12/15/2023 6:38:00 AM

very nice very nice
Anonymous


akminocha 9/28/2023 10:36:00 AM

please help us with 1z0-1107-2 dumps
INDIA


Jefi 9/4/2023 8:15:00 AM

please upload the practice questions
Anonymous


Thembelani 5/30/2023 2:45:00 AM

need this dumps
Anonymous


Abduraimov 4/19/2023 12:43:00 AM

preparing for this exam is overwhelming. you cannot pass without the help of these exam dumps.
UNITED KINGDOM


Puneeth 10/5/2023 2:06:00 AM

new to this site but i feel it is good
EUROPEAN UNION


Ashok Kumar 1/2/2024 6:53:00 AM

the correct answer to q8 is b. explanation since the mule app has a dependency, it is necessary to include project modules and dependencies to make sure the app will run successfully on the runtime on any other machine. source code of the component that the mule app is dependent of does not need to be included in the exported jar file, because the source code is not being used while executing an app. compiled code is being used instead.
Anonymous


Merry 7/30/2023 6:57:00 AM

good questions
Anonymous


VoiceofMidnight 12/17/2023 4:07:00 PM

Delayed the exam until December 29th.
UNITED STATES


Umar Ali 8/29/2023 2:59:00 PM

A and D are True
Anonymous


vel 8/28/2023 9:17:09 AM

good one with explanation
Anonymous


Gurdeep 1/18/2024 4:00:15 PM

This is one of the most useful study guides I have ever used.
CANADA