The planner adds non-stock material in a released maintenance order. Which of the following statements regarding the purchasing process are correct?
Note: There are 3 correct answers to this question.

  1. The maintenance order can be set to TECO before the invoice is created.
  2. A purchase order is created automatically as soon as the order is saved.
  3. A purchase requisition can be created automatically as soon asthe the order is saved.
  4. A goods receipt can be posted after the maintenance order is technically completed
  5. A goods receipt can ONLY be posted for a maintenance order with status REL.

Answer(s): A,C,D



The technical completion of the current maintenance order was posted with a delay of 5 days. What happens to the next planneddate if you set the shift factor for early completion to 100%?

  1. It is not shifted.
  2. It is postponed by 5 days.
  3. It is postponed by a full cycle (100%).
  4. It will be 5 days earlier.

Answer(s): B



Which of the following statements about breakdown maintenanceare correct?
Note: There are 3 correct answers to this question.

  1. More than one operation must always be maintained in the maintenance order.
  2. Notifications are used for documentation of technical findingsand activities performed.
  3. Maintenance orders can be created as immediate orders without any planning.
  4. Orders always need to be combined with notifications
  5. Orders and notifications can be utilized in combination

Answer(s): B,C,E



You cancel the technical completion of a work order. What are theeffects?
Note: There are 2 correct answers to this question.

  1. Open purchase orders are recompiled.
  2. Open reservations are recompiled.
  3. Referenced notifications are put In Process again.
  4. Open purchase requisitions are recompiled

Answer(s): B,D



Which objects can you use in the safety measure list?
Note: Thereare 2 correct answers to this question.

  1. Work approval
  2. Permits
  3. Documents
  4. Work clearance documents

Answer(s): B,C



Viewing Page 3 of 19



Share your comments for SAP C_TS413_2021 exam with other users:

H 7/17/2023 4:28:00 AM

could you please upload the exam?
Anonymous


Vavz 11/2/2023 6:51:00 AM

questions are accurate
Anonymous


Venkata Subbarao Bandaru 6/24/2023 8:45:00 AM

i require dump
Anonymous