SAP C_TS412_2021 Exam (page: 1)
SAP Certified Application Associate - S/4HANA Project Systems
Updated on: 12-Feb-2026

Viewing Page 1 of 23

What are valid procurement types for stock items?
Note: There are 3 correct answers to this question

  1. Preliminary purchase requisition for WBS element
  2. Planned order
  3. Third-party order
  4. Purchase requisition and Reservation for WBS element
  5. Reservation for WBS element

Answer(s): B,C,D

Explanation:

Stock items can be procured using planned orders, third-party orders, or purchase requisitions and reservations for WBS elements. Preliminary purchase requisitions are used for non-stock items and reservations are used for stock items that are already available in the warehouse.


Reference:

https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en- US/6a7a9f0a6e421014e10000000a174cb4.html



Which objects do you have to maintain to enable automatic assignment of material components to the project?
Note: There are 2 correct answers to this question

  1. Material master
  2. Network activity
  3. WBS element
  4. BOM item

Answer(s): A,D

Explanation:

To enable automatic assignment of material components to the project, you have to maintain the material master and the BOM item. The material master contains the data required for planning and procurement of materials. The BOM item contains the data required for assigning materials to a network activity or a WBS element.


Reference:

https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en- US/6a7a9f0a6e421014e10000000a174cb4.html



When you create a service activity in your network, what data can be entered?
Note: There are 3 correct answers to this question.

  1. Service specification
  2. Overall limit (maximum value of all unplanned services)
  3. Service purchase order number
  4. Material master within service specification
  5. Vendor

Answer(s): A,B,E

Explanation:

When you create a service activity in your network, you can enter a service specification, an overall limit, and a vendor. The service specification defines the scope and details of the service to be performed. The overall limit sets a maximum value for all unplanned services that can be entered during service entry. The vendor specifies the external service provider who will perform the service.


Reference:

https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en- US/6a7a9f0a6e421014e10000000a174cb4.html



Float time is calculated during scheduling.
Which of the following statements about float time are correct?
Note: There are 3 correct answers to this question

  1. Float time can be negative
  2. Activities with the time constraint "Must start on" always have a negative float time
  3. The float time of WBS elements is calculated by extrapolation
  4. By default, critical activities have a float time, which is less than or equal to zero
  5. The maximum size of a free float is as large as the total float of an activity

Answer(s): A,C,E

Explanation:

Float time is the amount of time that an activity or a WBS element can be delayed without affecting the end date of the project. Float time can be negative if an activity or a WBS element is already behind schedule. The float time of WBS elements is calculated by extrapolating the float times of their subordinate activities. The free float is the amount of time that an activity can be delayed without affecting the start date of its successor activities. The total float is the amount of time that an activity can be delayed without affecting the end date of the project. Therefore, the maximum size of a free float is as large as the total float of an activity.


Reference:

https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en- US/6a7a9f0a6e421014e10000000a174cb4.html



You have created an internally-processed network activity, and assigned a work center and the work. After saving, you discover that no planned costs are displayed in the cost element report for the activity.
What could be the reason?
Note: There are 3 correct answers to this question

  1. The formula for costing in the work center is incorrect
  2. The activity output price for the activity type and cost center assigned to the work center is not maintained.
  3. The duration is missing in the activity
  4. The Determine Costs indicator in the network header rules out planned cost calculation
  5. Integrated planning for the network is active

Answer(s): A,B,D

Explanation:

Planned costs are calculated for internally-processed network activities based on the formula for costing in the work center, the activity output price for the activity type and cost center assigned to the work center, and the duration of the activity. If any of these factors are missing or incorrect, no planned costs will be displayed. The Determine Costs indicator in the network header also controls whether planned costs are calculated or not. If it is not set, no planned costs will be displayed.


Reference:

https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en- US/6a7a9f0a6e421014e10000000a174cb4.html



Viewing Page 1 of 23



Share your comments for SAP C_TS412_2021 exam with other users:

ED SHAW 7/31/2023 10:34:00 AM

please allow to download
UNITED STATES


AD 7/22/2023 11:29:00 AM

please provide dumps
UNITED STATES


Ayyjayy 11/6/2023 7:29:00 AM

is the answer to question 15 correct ? i feel like the answer should be b
BAHRAIN


Blessious Phiri 8/12/2023 11:56:00 AM

its getting more technical
Anonymous


Jeanine J 7/11/2023 3:04:00 PM

i think these questions are what i need.
UNITED STATES


Aderonke 10/23/2023 2:13:00 PM

helpful assessment
UNITED KINGDOM


Tom 1/5/2024 2:32:00 AM

i am confused about the answers to the questions. do you know if the answers are correct?
KOREA REPUBLIC OF


Vinit N. 8/28/2023 2:33:00 AM

hi, please make the dumps available for my upcoming examination.
UNITED STATES


Sanyog Deshpande 9/14/2023 7:05:00 AM

good practice
UNITED STATES


Tyron 9/8/2023 12:12:00 AM

so far it is really informative
Anonymous


beast 7/30/2023 2:22:00 PM

hi i want it please please upload it
Anonymous


Mirex 5/26/2023 3:45:00 AM

am preparing for exam ,just nice questions
Anonymous


exampei 8/7/2023 8:05:00 AM

please upload c_tadm_23 exam
TURKEY


Anonymous 9/12/2023 12:50:00 PM

can we get tdvan4 vantage data engineering pdf?
UNITED STATES


Aish 10/11/2023 5:51:00 AM

want to clear the exam.
INDIA


Smaranika 6/22/2023 8:42:00 AM

could you please upload the dumps of sap c_sac_2302
INDIA


Blessious Phiri 8/15/2023 1:56:00 PM

asm management configuration is about storage
Anonymous


Lewis 7/6/2023 8:49:00 PM

kool thumb up
UNITED STATES


Moreece 5/15/2023 8:44:00 AM

just passed the az-500 exam this last friday. most of the questions in this exam dumps are in the exam. i bought the full version and noticed some of the questions which were answered wrong in the free version are all corrected in the full version. this site is good but i wish the had it in an interactive version like a test engine simulator.
Anonymous


Terry 5/24/2023 4:41:00 PM

i can practice for exam
Anonymous


Emerys 7/29/2023 6:55:00 AM

please i need this exam.
Anonymous


Goni Mala 9/2/2023 12:27:00 PM

i need the dump
Anonymous


Lenny 9/29/2023 11:30:00 AM

i want it bad, even if cs6 maybe retired, i want to learn cs6
HONG KONG


MilfSlayer 12/28/2023 8:32:00 PM

i hate comptia with all my heart with their "choose the best" answer format as an argument could be made on every question. they say "the "comptia way", lmao no this right here boys is the comptia way 100%. take it from someone whos failed this exam twice but can configure an entire complex network that these are the questions that are on the test 100% no questions asked. the pbqs are dead on! nice work
Anonymous


Swati Raj 11/14/2023 6:28:00 AM

very good materials
UNITED STATES


Ko Htet 10/17/2023 1:28:00 AM

thanks for your support.
Anonymous


Philippe 1/22/2023 10:24:00 AM

iam impressed with the quality of these dumps. they questions and answers were easy to understand and the xengine app was very helpful to use.
CANADA


Sam 8/31/2023 10:32:00 AM

not bad but you question database from isaca
MALAYSIA


Brijesh kr 6/29/2023 4:07:00 AM

awesome contents
INDIA


JM 12/19/2023 1:22:00 PM

answer to 134 is casb. while data loss prevention is the goal, in order to implement dlp in cloud applications you need to deploy a casb.
UNITED STATES


Neo 7/26/2023 9:36:00 AM

are these brain dumps sufficient enough to go write exam after practicing them? or does one need more material this wont be enough?
SOUTH AFRICA


Bilal 8/22/2023 6:33:00 AM

i did attend the required cources and i need to be sure that i am ready to take the exam, i would ask you please to share the questions, to be sure that i am fit to proceed with taking the exam.
Anonymous


John 11/12/2023 8:48:00 PM

why only give explanations on some, and not all questions and their respective answers?
UNITED STATES


Biswa 11/20/2023 8:50:00 AM

refresh db knowledge
Anonymous