What are the three tables that are defined for order type in network costing?

There are 3 correct answers to this question.

Response:

  1. Each order type
  2. Each order type and plant
  3. Network profile
  4. Each plant

Answer(s): A,B,C



Which of the following statements concerning ProMan are correct? (5)

  1. To use ProMan, you must have defined the corresponding profiles in Customizing
  2. In ProMan, you can also analyze purchase orders that have been manually account-assigned to a WBS element
  3. You can define user-specific layouts for the overviews in ProMan
  4. In ProMan, you can also post goods receipts and goods issues among other things.
  5. In the Customizing profile for ProMan, you can specify which exceptions are displayed, which orders and documents are read and which views are displayed
  6. In ProMan, you cannot only analyze data from the Project System but also data from Materials Management, Purchasing and Production

Answer(s): B,C,D,E,F



Which of the following items can be included in the planned costs for an activity besides the cost of the activity?

There are 3 correct answers to this question.

Response:

  1. Activity elements
  2. Overheads determined through overhead costing sheet
  3. Process costs determined through a process template
  4. Material management cost

Answer(s): A,B,C



Which statements about project coding mask are true?

There are 3 correct answers to this question.

Response:

  1. You must always use a project coding mask for your projects.
  2. The project coding mask can begin with a numerical key.
  3. The project coding mask can be shortened later, even if projects have already been created with this project coding mask.
  4. In project number maintenance, special characters are automatically determined using the project coding mask.
  5. You can lock a project coding mask for standard projects or operative projects.

Answer(s): B,D,E



Which of the following can be used to calculate and update interest in SAP project system?

There are 2 correct answers to this question.

Response:

  1. Planned interest calculation
  2. Actual interest calculation
  3. Compound interest calculation
  4. Result analysis

Answer(s): A,B



Viewing Page 4 of 34



Share your comments for SAP C_TPLM22_67 exam with other users:

Da_costa 8/1/2023 5:28:00 PM

these are free brain dumps i understand, how can one get free pdf
Anonymous


vikas 10/28/2023 6:57:00 AM

provide access
EUROPEAN UNION


Abdullah 9/29/2023 2:06:00 AM

good morning
Anonymous


Raj 6/26/2023 3:12:00 PM

please upload the ncp-mci 6.5 dumps, really need to practice this one. thanks guys
Anonymous


Miguel 10/5/2023 12:21:00 PM

question 16: https://help.salesforce.com/s/articleview?id=sf.care_console_overview.htm&type=5
SPAIN


Hiren Ladva 7/8/2023 10:34:00 PM

yes i m prepared exam
Anonymous


oliverjames 10/24/2023 5:37:00 AM

my experience was great with this site as i studied for the ms-900 from here and got 900/1000 on the test. my main focus was on the tutorials which were provided and practice questions. thanks!
GERMANY


Bhuddhiman 7/20/2023 11:52:00 AM

great course
UNITED STATES


Anuj 1/14/2024 4:07:00 PM

very good question
Anonymous


Saravana Kumar TS 12/8/2023 9:49:00 AM

question: 93 which statement is true regarding the result? sales contain 6 columns and values contain 7 columns so c is not right answer.
INDIA


Lue 3/30/2023 11:43:00 PM

highly recommend just passed my exam.
CANADA


DC 1/7/2024 10:17:00 AM

great practice! thanks
UNITED STATES


Anonymus 11/9/2023 5:41:00 AM

anyone who wrote this exam recently?
SOUTH AFRICA


Khalid Javid 11/17/2023 3:46:00 PM

kindly share the dump
Anonymous


Na 8/9/2023 8:39:00 AM

could you please upload cfe fraud prevention and deterrence questions? it will be very much helpful.
Anonymous


shime 10/23/2023 10:03:00 AM

this is really very very helpful for mcd level 1
ETHIOPIA


Vnu 6/3/2023 2:39:00 AM

very helpful!
Anonymous


Steve 8/17/2023 2:19:00 PM

question #18s answer should be a, not d. this should be corrected. it should be minvalidityperiod
CANADA


RITEISH 12/24/2023 4:33:00 AM

thanks for the exact solution
Anonymous


SB 10/15/2023 7:58:00 AM

need to refer the questions and have to give the exam
INDIA


Mike Derfalem 7/16/2023 7:59:00 PM

i need it right now if it was possible please
Anonymous


Isak 7/6/2023 3:21:00 AM

i need it very much please share it in the fastest time.
Anonymous


Maria 6/23/2023 11:40:00 AM

correct answer is d for student.java program
IRELAND


Nagendra Pedipina 7/12/2023 9:10:00 AM

q:37 c is correct
INDIA


John 9/16/2023 9:37:00 PM

q6 exam topic: terramearth, c: correct answer: copy 1petabyte to encrypted usb device ???
GERMANY


SAM 12/4/2023 12:56:00 AM

explained answers
INDIA


Andy 12/26/2023 9:35:00 PM

plan to take theaws certified developer - associate dva-c02 in the next few weeks
SINGAPORE


siva 5/17/2023 12:32:00 AM

very helpfull
Anonymous


mouna 9/27/2023 8:53:00 AM

good questions
Anonymous


Bhavya 9/12/2023 7:18:00 AM

help to practice csa exam
Anonymous


Malik 9/28/2023 1:09:00 PM

nice tip and well documented
Anonymous


rodrigo 6/22/2023 7:55:00 AM

i need the exam
Anonymous


Dan 6/29/2023 1:53:00 PM

please upload
Anonymous


Ale M 11/22/2023 6:38:00 PM

prepping for fsc exam
AUSTRALIA