What is the objective of a sprint retrospective meeting?

  1. Improve the scrum process
  2. Review and prioritize the backlog
  3. Provide formal feedback to the project manager
  4. Define the stakeholder management approach

Answer(s): A



In SAP activate, what tool is used in the agile delivery approach during the realize phase.

  1. Product Increment
  2. Project plan
  3. Burndown chart
  4. Release plan

Answer(s): C



What information does the project team need before they can.

  1. Definition of done
  2. Available project resources
  3. Overall project schedule
  4. Test strategy

Answer(s): A



Which of the following belong to the application design and configuration workstream for SAP S/4HANA cloud in the explore phase?

There are 2 correct answers to this question

  1. Kick-off workshop
  2. Integration prerequisites confirmation
  3. Fit-to-standard workshop
  4. Configuration definition

Answer(s): C,D



What is the Primary Purpose of the SAP Activate Methodology ?

  1. To enable access to the SAP ecosystem
  2. To Provide the Sequence of actions in the project
  3. To provide end-to-end Application Lifecycle Management
  4. To manage solution documentation

Answer(s): C