Which process is triggered towards the end of the final stage when all the assigned work has been completed?

  1. Managing a Stage Boundary
  2. Managing Product Delivery
  3. Closing a Project
  4. Controlling a Stage

Answer(s): C

Explanation:

The Closing a Project process in PRINCE2 is triggered towards the end of the final stage when all assigned work has been completed. This process is designed to ensure that all project objectives have been achieved, all products have been delivered, and the project can be formally closed and evaluated for success and areas of improvement.


Reference:

PRINCE2 Foundation manual, PRINCE2 official resources



Which is a purpose of the Controlling a Stage process?

  1. Assign work to be done and take corrective action to ensure that the stage remains within tolerance
  2. Provide a fixed reference point at which acceptance for the project product is confirmed
  3. Enable the Project Board to be provided with sufficient information to authorize the next stage
  4. Enable the organization to understand the work that needs to be done to deliver the project's products

Answer(s): A

Explanation:

The purpose of the Controlling a Stage process in PRINCE2® is to monitor and control a stage within its authorized tolerances. During this process, the Project Manager assigns work, monitors work progress, deals with issues, reports stage status to the Project Board, and takes necessary corrective actions to stay within the stage's tolerances.


Reference:

PRINCE2® Foundation official documentation and study materials.



What process is used by the Project Manager to maintain focus on delivery of a stage's products within agreed tolerances?

  1. Directing a Project
  2. Controlling a Stage
  3. Managing a Stage Boundary
  4. Managing Product Delivery

Answer(s): B

Explanation:

The Controlling a Stage process is used by the Project Manager to maintain focus on the delivery of the stage's products within the agreed tolerances. This involves assigning work, monitoring such work, managing issues and risks, and ensuring that the stage remains on track in terms of time, cost, quality, scope, risk, and benefit performance.


Reference:

PRINCE2® Foundation official documentation and study materials.



In which product does a Project Manager define the time and cost tolerances for the work to be done by a Team Manager?

  1. Product Description
  2. Team Plan
  3. Work Package
  4. Stage Plan

Answer(s): C

Explanation:

In PRINCE2®, a Work Package is the document where the Project Manager defines the time and cost tolerances for the work assigned to a Team Manager. The Work Package provides detailed information on the products to be delivered, the reporting requirements, and the tolerances within which the Team Manager operates.


Reference:

PRINCE2® Foundation official documentation and study materials.



Which is a purpose of the Directing a Project process?

  1. Create and authorize the project mandate
  2. Ensure that work on products allocated to the team is authorized and agreed
  3. Control the day-to-day running of the project
  4. Delegate day-to-day management of the project to the Project Manager

Answer(s): D

Explanation:

The purpose of the Directing a Project process is for the Project Board to delegate the day-to-day management of the project to the Project Manager, providing the overall direction and management of the project lifecycle. This process is critical for enabling the Project Manager to run the project on behalf of the Project Board within the constraints set out by them.


Reference:

PRINCE2® Foundation official documentation and study materials.



Share your comments for PRINCE2 PRINCE2 Foundation 7 Edition exam with other users:

B
BK
8/11/2023 12:23:00 PM

very useful

D
Deepika Narayanan
7/13/2023 11:05:00 PM

yes need this exam dumps

B
Blessious Phiri
8/15/2023 3:31:00 PM

these questions are a great eye opener

J
Jagdesh
9/8/2023 8:17:00 AM

thank you for providing these questions and answers. they helped me pass my exam. you guys are great.

T
TS
7/18/2023 3:32:00 PM

good knowledge

A
Asad Khan
11/1/2023 2:44:00 AM

answer 10 should be a because only a new project will be created & the organization is the same.

R
Raj
9/12/2023 3:49:00 PM

can you please upload the dump again

C
Christian Klein
6/23/2023 1:32:00 PM

is it legit questions from sap certifications ?

A
anonymous
1/12/2024 3:34:00 PM

question 16 should be b (changing the connector settings on the monitor) pc and monitor were powered on. the lights on the pc are on indicating power. the monitor is showing an error text indicating that it is receiving power too. this is a clear sign of having the wrong input selected on the monitor. thus, the "connector setting" needs to be switched from hdmi to display port on the monitor so it receives the signal from the pc, or the other way around (display port to hdmi).

N
NSPK
1/18/2024 10:26:00 AM

q 10. ans is d (in the target org: open deployment settings, click edit next to the source org. select allow inbound changes and save

M
mohamed abdo
9/1/2023 4:59:00 AM

very useful

T
Tom
3/18/2022 8:00:00 PM

i purchased this exam dumps from another website with way more questions but they were all invalid and outdate. this exam dumps was right to the point and all from recent exam. it was a hard pass.

E
Edrick GOP
10/24/2023 6:00:00 AM

it was a good experience and i got 90% in the 200-901 exam.

A
anonymous
8/10/2023 2:28:00 AM

hi please upload this

B
Bakir
7/6/2023 7:24:00 AM

please upload it

A
Aman
6/18/2023 1:27:00 PM

really need this dump. can you please help.

N
Neela Para
1/8/2024 6:39:00 PM

really good and covers many areas explaining the answer.

K
Karan Patel
8/15/2023 12:51:00 AM

yes, can you please upload the exam?

N
NISHAD
11/7/2023 11:28:00 AM

how many questions are there in these dumps?

P
Pankaj
7/3/2023 3:57:00 AM

hi team, please upload this , i need it.

D
DN
9/4/2023 11:19:00 PM

question 14 - run terraform import: this is the recommended best practice for bringing manually created or destroyed resources under terraform management. you use terraform import to associate an existing resource with a terraform resource configuration. this ensures that terraform is aware of the resource, and you can subsequently manage it with terraform.

Z
Zhiguang
8/19/2023 11:37:00 PM

please upload dump. thanks in advance.

D
deedee
12/23/2023 5:51:00 PM

great great

A
Asad Khan
11/1/2023 3:10:00 AM

answer 16 should be b your organizational policies require you to use virtual machines directly

S
Sale Danasabe
10/24/2023 5:21:00 PM

the question are kind of tricky of you didnt get the hnag on it.

L
Luis
11/16/2023 1:39:00 PM

can anyone tell me if this is for rhel8 or rhel9?

H
hik
1/19/2024 1:47:00 PM

good content

B
Blessious Phiri
8/15/2023 2:18:00 PM

pdb and cdb are critical to the database

Z
Zuned
10/22/2023 4:39:00 AM

till 104 questions are free, lets see how it helps me in my exam today.

M
Muhammad Rawish Siddiqui
12/3/2023 12:11:00 PM

question # 56, answer is true not false.

A
Amaresh Vashishtha
8/27/2023 1:33:00 AM

i would be requiring dumps to prepare for certification exam

A
Asad
9/8/2023 1:01:00 AM

very helpful

B
Blessious Phiri
8/13/2023 3:10:00 PM

control file is the heart of rman backup

S
Senthil
9/19/2023 5:47:00 AM

hi could you please upload the ibm c2090-543 dumps

AI Tutor 👋 I’m here to help!