Which is a difference between management and technical stages?

  1. Management stages require planning and technical stages do not
  2. Technical stages can overlap and management stages cannot
  3. Management stages deliver products and technical stages do not
  4. Technical stages require resources and management stages do not

Answer(s): B

Explanation:

A key difference between management and technical stages in PRINCE2® is that technical stages can overlap whereas management stages cannot. Technical stages refer to the actual work being done, which can sometimes proceed in parallel, while management stages are concerned with the control and decision points that must be sequential to ensure proper governance.


Reference:

PRINCE2® Foundation official documentation and study materials.



Which is a purpose of a Lessons Log?

  1. Note any lessons that are raised in Checkpoint Reports
  2. Record that corrective action is being taken
  3. Escalate lessons to the Project Board
  4. Raise improvements with Project Assurance

Answer(s): A

Explanation:

The purpose of a Lessons Log in PRINCE2® is to record all lessons that arise during the project, including those noted in Checkpoint Reports. This log helps in capturing valuable insights and learning points which can be used to improve future projects or later stages of the current project.


Reference:

PRINCE2® Foundation official documentation and study materials.



Which is a true statement about PRINCE2 event-driven controls?

  1. Event-driven controls take place at predefined periodic intervals
  2. Event-driven controls are produced at the frequency defined in a Work Package
  3. Event-driven controls are used for decision making
  4. Checkpoint Reports are event-driven controls

Answer(s): C

Explanation:

PRINCE2 defines event-driven controls as those that are triggered by the occurrence of certain events within the project lifecycle, such as the completion of a product or phase. These controls are essential for decision-making because they provide necessary information at key points, allowing project managers and the Project Board to make informed decisions about the future of the project.


Reference:

PRINCE2 Foundation manual, PRINCE2 official resources



Which is a purpose of an End Project Report?

  1. Identify individuals or groups that need to be told that the project is coming to an end
  2. Review how well the project performed against the Project Initiation Documentation used to authorize it
  3. Identify individuals or groups that are responsible for measuring the expected benefits after the project has closed
  4. Ensure that key project information is archived and made secure

Answer(s): B

Explanation:

The purpose of an End Project Report in PRINCE2 is to review how well the project performed against the Project Initiation Documentation (PID) used to authorize it. This report provides a final account of the project, including whether it met its objectives and delivered the expected benefits, and highlights lessons learned to inform future projects.


Reference:

PRINCE2 Foundation manual, PRINCE2 official resources



How many management stages should a PRINCE2 project consist of?

  1. Start up stage, initiation stage and at least one other management stage to cover the remainder of the project
  2. Start up stage, at least one other management stage to cover the remainder of the project and a closing stage
  3. Initiation stage and at least one other management stage to cover the remainder of the project
  4. Start up stage, initiation stage and a closing stage

Answer(s): A

Explanation:

A PRINCE2 project should consist of a start-up stage, an initiation stage, and at least one other management stage to cover the remainder of the project. This structure ensures that the project is properly initiated and planned before entering into a series of management stages where the work is executed and completed, followed by a closing stage.


Reference:

PRINCE2 Foundation manual, PRINCE2 official resources



Share your comments for PRINCE2 PRINCE2 Foundation 7 Edition exam with other users:

M
Marc blue
9/15/2023 4:11:00 AM

great job. hope this helps out.

A
Anne
9/13/2023 2:33:00 AM

upload please. many thanks!

P
pepe el toro
9/12/2023 7:55:00 PM

this is so interesting

A
Antony
11/28/2023 12:13:00 AM

great material thanks

T
Thembelani
5/30/2023 2:22:00 AM

anyone who wrote this exam recently

P
P
9/16/2023 1:27:00 AM

ok they re good

J
Jorn
7/13/2023 5:05:00 AM

relevant questions

A
AM
6/20/2023 7:54:00 PM

please post

N
Nagendra Pedipina
7/13/2023 2:22:00 AM

q:42 there has to be a image in the question to choose what does it mean from the options

B
BrainDumpee
11/18/2023 1:36:00 PM

looking for cphq dumps, where can i find these for free? please and thank you.

S
sheik
10/14/2023 11:37:00 AM

@aarun , thanks for the information. it would be great help if you share your email

R
Random user
12/11/2023 1:34:00 AM

1z0-1078-23 need this dumps

L
labuschanka
11/16/2023 6:06:00 PM

i gave the microsoft azure az-500 tests and prepared from this site as it has latest mock tests available which helped me evaluate my performance and score 919/1000

M
Marianne
10/22/2023 11:57:00 PM

i cannot see the button to go to the questions

S
sushant
6/28/2023 4:52:00 AM

good questions

A
A\MAM
6/27/2023 5:17:00 PM

q-6 ans-b correct. https://docs.paloaltonetworks.com/pan-os/9-1/pan-os-cli-quick-start/use-the-cli/commit-configuration-changes

U
unanimous
12/15/2023 6:38:00 AM

very nice very nice

A
akminocha
9/28/2023 10:36:00 AM

please help us with 1z0-1107-2 dumps

J
Jefi
9/4/2023 8:15:00 AM

please upload the practice questions

T
Thembelani
5/30/2023 2:45:00 AM

need this dumps

A
Abduraimov
4/19/2023 12:43:00 AM

preparing for this exam is overwhelming. you cannot pass without the help of these exam dumps.

P
Puneeth
10/5/2023 2:06:00 AM

new to this site but i feel it is good

A
Ashok Kumar
1/2/2024 6:53:00 AM

the correct answer to q8 is b. explanation since the mule app has a dependency, it is necessary to include project modules and dependencies to make sure the app will run successfully on the runtime on any other machine. source code of the component that the mule app is dependent of does not need to be included in the exported jar file, because the source code is not being used while executing an app. compiled code is being used instead.

M
Merry
7/30/2023 6:57:00 AM

good questions

V
VoiceofMidnight
12/17/2023 4:07:00 PM

Delayed the exam until December 29th.

U
Umar Ali
8/29/2023 2:59:00 PM

A and D are True

V
vel
8/28/2023 9:17:09 AM

good one with explanation

G
Gurdeep
1/18/2024 4:00:15 PM

This is one of the most useful study guides I have ever used.

AI Tutor 👋 I’m here to help!