Which is a difference between management and technical stages?

  1. Management stages require planning and technical stages do not
  2. Technical stages can overlap and management stages cannot
  3. Management stages deliver products and technical stages do not
  4. Technical stages require resources and management stages do not

Answer(s): B

Explanation:

A key difference between management and technical stages in PRINCE2® is that technical stages can overlap whereas management stages cannot. Technical stages refer to the actual work being done, which can sometimes proceed in parallel, while management stages are concerned with the control and decision points that must be sequential to ensure proper governance.


Reference:

PRINCE2® Foundation official documentation and study materials.



Which is a purpose of a Lessons Log?

  1. Note any lessons that are raised in Checkpoint Reports
  2. Record that corrective action is being taken
  3. Escalate lessons to the Project Board
  4. Raise improvements with Project Assurance

Answer(s): A

Explanation:

The purpose of a Lessons Log in PRINCE2® is to record all lessons that arise during the project, including those noted in Checkpoint Reports. This log helps in capturing valuable insights and learning points which can be used to improve future projects or later stages of the current project.


Reference:

PRINCE2® Foundation official documentation and study materials.



Which is a true statement about PRINCE2 event-driven controls?

  1. Event-driven controls take place at predefined periodic intervals
  2. Event-driven controls are produced at the frequency defined in a Work Package
  3. Event-driven controls are used for decision making
  4. Checkpoint Reports are event-driven controls

Answer(s): C

Explanation:

PRINCE2 defines event-driven controls as those that are triggered by the occurrence of certain events within the project lifecycle, such as the completion of a product or phase. These controls are essential for decision-making because they provide necessary information at key points, allowing project managers and the Project Board to make informed decisions about the future of the project.


Reference:

PRINCE2 Foundation manual, PRINCE2 official resources



Which is a purpose of an End Project Report?

  1. Identify individuals or groups that need to be told that the project is coming to an end
  2. Review how well the project performed against the Project Initiation Documentation used to authorize it
  3. Identify individuals or groups that are responsible for measuring the expected benefits after the project has closed
  4. Ensure that key project information is archived and made secure

Answer(s): B

Explanation:

The purpose of an End Project Report in PRINCE2 is to review how well the project performed against the Project Initiation Documentation (PID) used to authorize it. This report provides a final account of the project, including whether it met its objectives and delivered the expected benefits, and highlights lessons learned to inform future projects.


Reference:

PRINCE2 Foundation manual, PRINCE2 official resources



How many management stages should a PRINCE2 project consist of?

  1. Start up stage, initiation stage and at least one other management stage to cover the remainder of the project
  2. Start up stage, at least one other management stage to cover the remainder of the project and a closing stage
  3. Initiation stage and at least one other management stage to cover the remainder of the project
  4. Start up stage, initiation stage and a closing stage

Answer(s): A

Explanation:

A PRINCE2 project should consist of a start-up stage, an initiation stage, and at least one other management stage to cover the remainder of the project. This structure ensures that the project is properly initiated and planned before entering into a series of management stages where the work is executed and completed, followed by a closing stage.


Reference:

PRINCE2 Foundation manual, PRINCE2 official resources



Share your comments for PRINCE2 PRINCE2 Foundation 7 Edition exam with other users:

Y
Yves
8/29/2023 8:46:00 PM

very inciting

M
Miguel
10/16/2023 11:18:00 AM

question 5, it seems a instead of d, because: - care plan = case - patient = person account - product = product2;

B
Byset
9/25/2023 12:49:00 AM

it look like real one

D
Debabrata Das
8/28/2023 8:42:00 AM

i am taking oracle fcc certification test next two days, pls share question dumps

N
nITA KALE
8/22/2023 1:57:00 AM

i need dumps

C
CV
9/9/2023 1:54:00 PM

its time to comptia sec+

S
SkepticReader
8/1/2023 8:51:00 AM

question 35 has an answer for a different question. i believe the answer is "a" because it shut off the firewall. "0" in registry data means that its false (aka off).

N
Nabin
10/16/2023 4:58:00 AM

helpful content

B
Blessious Phiri
8/15/2023 3:19:00 PM

oracle 19c is complex db

S
Sreenivas
10/24/2023 12:59:00 AM

helpful for practice

L
Liz
9/11/2022 11:27:00 PM

support team is fast and deeply knowledgeable. i appreciate that a lot.

N
Namrata
7/15/2023 2:22:00 AM

helpful questions

L
lipsa
11/8/2023 12:54:00 PM

thanks for question

E
Eli
6/18/2023 11:27:00 PM

the software is provided for free so this is a big change. all other sites are charging for that. also that fucking examtopic site that says free is not free at all. you are hit with a pay-wall.

O
open2exam
10/29/2023 1:14:00 PM

i need exam questions nca 6.5 any help please ?

G
Gerald
9/11/2023 12:22:00 PM

just took the comptia cybersecurity analyst (cysa+) - wished id seeing this before my exam

R
ryo
9/10/2023 2:27:00 PM

very helpful

J
Jamshed
6/20/2023 4:32:00 AM

i need this exam

R
Roberto Capra
6/14/2023 12:04:00 PM

nice questions... are these questions the same of the exam?

S
Synt
5/23/2023 9:33:00 PM

need to view

V
Vey
5/27/2023 12:06:00 AM

highly appreciate for your sharing.

T
Tshepang
8/18/2023 4:41:00 AM

kindly share this dump. thank you

J
Jay
9/26/2023 8:00:00 AM

link plz for download

L
Leo
10/30/2023 1:11:00 PM

data quality oecd

B
Blessious Phiri
8/13/2023 9:35:00 AM

rman is one good recovery technology

D
DiligentSam
9/30/2023 10:26:00 AM

need it thx

V
Vani
8/10/2023 8:11:00 PM

good questions

F
Fares
9/11/2023 5:00:00 AM

good one nice revision

L
Lingaraj
10/26/2023 1:27:00 AM

i love this thank you i need

M
Muhammad Rawish Siddiqui
12/5/2023 12:38:00 PM

question # 142: data governance is not one of the deliverables in the document and content management context diagram.

A
al
6/7/2023 10:25:00 AM

most answers not correct here

B
Bano
1/19/2024 2:29:00 AM

what % of questions do we get in the real exam?

O
Oliviajames
10/25/2023 5:31:00 AM

i just want to tell you. i took my microsoft az-104 exam and passed it. your program was awesome. i especially liked your detailed questions and answers and practice tests that made me well-prepared for the exam. thanks to this website!!!

D
Divya
8/27/2023 12:31:00 PM

all the best

AI Tutor 👋 I’m here to help!