Which does NOT reflect the PRINCE2 principle of continued business justification?
Answer(s): C
The principle of continued business justification in PRINCE2 means that a project must remain justified throughout its life cycle. The key factor is the project's ongoing justification, not solely its ability to deliver financial benefits. Projects may continue for reasons other than financial gain, such as strategic importance, compliance, or public safety. Therefore, stopping a project based only on financial criteria does not reflect this principle accurately.
PRINCE2 Foundation manual, PRINCE2 official resources
Which characteristic distinguishes a project from regular business operations?
Answer(s): B
A characteristic that distinguishes a project from regular business operations is that it introduces business change. Projects are temporary endeavors undertaken to create a unique product, service, or result, and they often drive significant changes within an organization, unlike regular operations, which are repetitive and ongoing.
Which characteristic of a project reflects that there are different perspectives and motivations for customers and suppliers?
The characteristic of a project that reflects different perspectives and motivations for customers and suppliers is its "Unique" nature. Projects typically bring together diverse groups, each with distinct objectives and expectations. The uniqueness of a project involves these varied stakeholder inputs and requirements, which often need to be balanced and managed.
Which PRINCE2 principle is supported by the setting of tolerances for the three levels of plan?
The PRINCE2 principle supported by the setting of tolerances for the three levels of plan (Project, Stage, and Team Plans) is "Manage by exception." This principle allows management to set predefined tolerances for project objectives, and only escalate issues to higher management if these tolerances are exceeded, thereby facilitating efficient use of management time and focus.
Which role is responsible for creating Checkpoint Reports?
In PRINCE2®, the Team Manager is responsible for creating Checkpoint Reports. These reports provide the Project Manager with a summary of the progress within a Work Package, detailing performance against plan, and highlighting any issues that might affect the work.
PRINCE2® Foundation official study materials.
Share your comments for PRINCE2 PRINCE2 Foundation 7 Edition exam with other users:
i need to pass exam
great, i appreciate it.
please could you upload (isc)2 certified in cybersecurity (cc) exam questions
good questions, wrong answers
im preparing for exams
question no: 42 isnt azure vm an iaas solution? so, shouldnt the answer be "no"?
im study azure
i need this now
i took the aws saa-c03 test and scored 935/1000. it has all the exam dumps and important info.
good questions
well explained
i got the full version and it helped me pass the exam. pdf version is very good.
provide the download link, please
please upload thank.
please can you share 1z0-1055-22 dump pls
i will wait impatiently. thank youu
is it possible to clear the exam if we focus on only these 156 questions instead of 623 questions? kindly help!
really helped with preparation of my scrum exam
very informative and through explanations
prep for exam
thanks for helping us
i prepared for the eccouncil 350-401 exam. i scored 92% on the test.
aba questions to practice
great content
how do i get the remaining questions?
well formatted pdf and the test engine software is free. well worth the money i sept.
looking for 1z0-116
in question 22, shouldnt be in the data (option a) layer?
the questions are incredibly close to real exam. you people are amazing.
q15. answer is b. simple
great practice
thanks to this exam dumps, i felt confident and passed my exam with ease.
need 1z0-1105-22 exam
this is a beautiful tool. passed after a week of studying.