Which is a difference between management and technical stages?

  1. Management stages require planning and technical stages do not
  2. Technical stages can overlap and management stages cannot
  3. Management stages deliver products and technical stages do not
  4. Technical stages require resources and management stages do not

Answer(s): B

Explanation:

A key difference between management and technical stages in PRINCE2® is that technical stages can overlap whereas management stages cannot. Technical stages refer to the actual work being done, which can sometimes proceed in parallel, while management stages are concerned with the control and decision points that must be sequential to ensure proper governance.


Reference:

PRINCE2® Foundation official documentation and study materials.



Which is a purpose of a Lessons Log?

  1. Note any lessons that are raised in Checkpoint Reports
  2. Record that corrective action is being taken
  3. Escalate lessons to the Project Board
  4. Raise improvements with Project Assurance

Answer(s): A

Explanation:

The purpose of a Lessons Log in PRINCE2® is to record all lessons that arise during the project, including those noted in Checkpoint Reports. This log helps in capturing valuable insights and learning points which can be used to improve future projects or later stages of the current project.


Reference:

PRINCE2® Foundation official documentation and study materials.



Which is a true statement about PRINCE2 event-driven controls?

  1. Event-driven controls take place at predefined periodic intervals
  2. Event-driven controls are produced at the frequency defined in a Work Package
  3. Event-driven controls are used for decision making
  4. Checkpoint Reports are event-driven controls

Answer(s): C

Explanation:

PRINCE2 defines event-driven controls as those that are triggered by the occurrence of certain events within the project lifecycle, such as the completion of a product or phase. These controls are essential for decision-making because they provide necessary information at key points, allowing project managers and the Project Board to make informed decisions about the future of the project.


Reference:

PRINCE2 Foundation manual, PRINCE2 official resources



Which is a purpose of an End Project Report?

  1. Identify individuals or groups that need to be told that the project is coming to an end
  2. Review how well the project performed against the Project Initiation Documentation used to authorize it
  3. Identify individuals or groups that are responsible for measuring the expected benefits after the project has closed
  4. Ensure that key project information is archived and made secure

Answer(s): B

Explanation:

The purpose of an End Project Report in PRINCE2 is to review how well the project performed against the Project Initiation Documentation (PID) used to authorize it. This report provides a final account of the project, including whether it met its objectives and delivered the expected benefits, and highlights lessons learned to inform future projects.


Reference:

PRINCE2 Foundation manual, PRINCE2 official resources



How many management stages should a PRINCE2 project consist of?

  1. Start up stage, initiation stage and at least one other management stage to cover the remainder of the project
  2. Start up stage, at least one other management stage to cover the remainder of the project and a closing stage
  3. Initiation stage and at least one other management stage to cover the remainder of the project
  4. Start up stage, initiation stage and a closing stage

Answer(s): A

Explanation:

A PRINCE2 project should consist of a start-up stage, an initiation stage, and at least one other management stage to cover the remainder of the project. This structure ensures that the project is properly initiated and planned before entering into a series of management stages where the work is executed and completed, followed by a closing stage.


Reference:

PRINCE2 Foundation manual, PRINCE2 official resources



Share your comments for PRINCE2 PRINCE2-7-Foundation exam with other users:

P
PMSAGAR
9/19/2023 2:48:00 AM

pls share teh dump

Z
zazza
6/16/2023 10:47:00 AM

question 44 answer is user risk

P
Prasana
6/23/2023 1:59:00 AM

please post the questions for preparation

T
test user
9/24/2023 3:15:00 AM

thanks for the questions

D
Draco
7/19/2023 5:34:00 AM

please reopen it now ..its really urgent

M
Megan
4/14/2023 5:08:00 PM

these practice exam questions were exactly what i needed. the variety of questions and the realistic exam-like environment they created helped me assess my strengths and weaknesses. i felt more confident and well-prepared on exam day, and i owe it to this exam dumps!

A
abdo casa
8/9/2023 6:10:00 PM

thank u it very instructuf

D
Danny
1/15/2024 9:10:00 AM

its helpful?

H
hanaa
10/3/2023 6:57:00 PM

is this dump still valid???

G
Georgio
1/19/2024 8:15:00 AM

question 205 answer is b

M
Matthew Dievendorf
5/30/2023 9:37:00 PM

question 39, should be answer b, directions stated is being sudneted from /21 to a /23. a /23 has 512 ips so 510 hosts. and can make 4 subnets out of the /21

A
Adhithya
8/11/2022 12:27:00 AM

beautiful test engine software and very helpful. questions are same as in the real exam. i passed my paper.

S
SuckerPumch88
4/25/2022 10:24:00 AM

the questions are exactly the same in real exam. just make sure not to answer all them correct or else they suspect you are cheating.

S
soheib
7/24/2023 7:05:00 PM

question: 78 the right answer i think is d not a

S
srija
8/14/2023 8:53:00 AM

very helpful

T
Thembelani
5/30/2023 2:17:00 AM

i am writing this exam tomorrow and have dumps

A
Anita
10/1/2023 4:11:00 PM

can i have the icdl excel exam

B
Ben
9/9/2023 7:35:00 AM

please upload it

A
anonymous
9/20/2023 11:27:00 PM

hye when will post again the past year question for this h13-311_v3 part since i have to for my test tommorow…thank you very much

R
Randall
9/28/2023 8:25:00 PM

on question 22, option b-once per session is also valid.

T
Tshegofatso
8/28/2023 11:51:00 AM

this website is very helpful

P
philly
9/18/2023 2:40:00 PM

its my first time exam

B
Beexam
9/4/2023 9:06:00 PM

correct answers are device configuration-enable the automatic installation of webview2 runtime. & policy management- prevent users from submitting feedback.

R
RAWI
7/9/2023 4:54:00 AM

is this dump still valid? today is 9-july-2023

A
Annie
6/7/2023 3:46:00 AM

i need this exam.. please upload these are really helpful

S
Shubhra Rathi
8/26/2023 1:08:00 PM

please upload the oracle 1z0-1059-22 dumps

S
Shiji
10/15/2023 1:34:00 PM

very good questions

R
Rita Rony
11/27/2023 1:36:00 PM

nice, first step to exams

A
Aloke Paul
9/11/2023 6:53:00 AM

is this valid for chfiv9 as well... as i am reker 3rd time...

C
Calbert Francis
1/15/2024 8:19:00 PM

great exam for people taking 220-1101

A
Ayushi Baria
11/7/2023 7:44:00 AM

this is very helpfull for me

A
alma
8/25/2023 1:20:00 PM

just started preparing for the exam

C
CW
7/10/2023 6:46:00 PM

these are the type of questions i need.

N
Nobody
8/30/2023 9:54:00 PM

does this actually work? are they the exam questions and answers word for word?

AI Tutor 👋 I’m here to help!