You work as a Project Manager for Company Inc. You have to conduct the risk management activities for a project. Which of the following inputs will you use in the plan risk management process?
Each correct answer represents a complete solution. (Choose three.)

  1. Quality management plan
  2. Schedule management plan
  3. Cost management plan
  4. Project scope statement

Answer(s): B,C,D

Explanation:

The inputs to the plan risk management process are as follows:
Project scope statement: It provides a clear sense of the range of possibilities associated with the project and establishes the framework for how significant the risk management effort may become.
Cost management plan: It describes how risk budgets, contingencies, and management reserves will be reported and accessed.
Schedule management plan: It describes how the schedule contingencies will be reported and assessed. Communication management plan: It describes the interactions, which occurs on the project and determines who will be available to share information on various risks and responses at different times. Enterprise environmental factors: It include, but are not limited to, risk attitudes and tolerances that describe the degree of risk that an organization withstand.
Organizational process assets: It includes, but are not limited to, risk categories, risk statement formats, standard templates, roles and responsibilities, authority levels for decision-making, lessons learned, and stakeholder registers.

Incorrect Answers:
A: It is not an input for Plan risk management process.



Which of the following documents is described in the statement below?
"It is developed along with all processes of the risk management. It contains the results of the qualitative risk analysis, quantitative risk analysis, and risk response planning."

  1. Quality management plan
  2. Risk management plan
  3. Risk register
  4. Project charter

Answer(s): C

Explanation:

Risk register is a document that contains the results of the qualitative risk analysis, quantitative risk analysis, and risk response planning.

Risk register is developed along with all processes of the risk management from Plan Risk Management through Monitor and Control Risks.

Incorrect Answers:
A: The quality management plan is a component of the project management plan. It describes how the project team will implement the organization's quality policy. The quality management plan addresses quality control (QC), quality assurance (QA), and continuous process improvement for the project. Based on the requirement of the project, the quality management plan may be formal or informal, highly detailed or broadly framed.

B: Risk management plan includes roles and responsibilities, risk analysis definitions, timing for reviews, and risk threshold. The Plan Risk Responses process takes input from risk management plan and risk register to define the risk response.

D: The project charter is the document that formally authorizes a project. The project charter provides the project manager with the authority to apply organizational resources to project activities.



You have identified several risks in your project. You have opted for risk mitigation in order to respond to identified risk. Which of the following ensures that risk mitigation method that you have chosen is effective?

  1. Reduction in the frequency of a threat
  2. Minimization of inherent risk
  3. Reduction in the impact of a threat
  4. Minimization of residual risk

Answer(s): D



Which of the following control is used to ensure that users have the rights and permissions they need to perform their jobs, and no more?

  1. System and Communications protection control
  2. Audit and Accountability control
  3. Access control
  4. Identification and Authentication control

Answer(s): C

Explanation:

Access control helps an organization implement effective access control. They ensure that users have the rights and permissions they need to perform their jobs, and no more. It includes principles such as least privilege and separation of duties.

Incorrect Answers:
A: System and Communications protection control is a large group of controls that cover many aspects of protecting systems and communication channels. Denial of service protection and boundary protection controls are included. Transmission integrity and confidentiality controls are also included.

B: Audit and Accountability control helps an organization implement an effective audit program. It provides details on how to determine what to audit. It provides details on how to protect the audit logs. It also includes information on using audit logs for non-repudiation.

D: Identification and Authentication control cover different practices to identify and authenticate users. Each user should be uniquely identified. In other words, each user has one account. This account is only used by one user. Similarly, device identifiers uniquely identify devices on the network.



You are working in an enterprise. Your enterprise owned various risks. Which among the following is MOST likely to own the risk to an information system that supports a critical business process?

  1. System users
  2. Senior management
  3. IT director
  4. Risk management department

Answer(s): B

Explanation:

Senior management is responsible for the acceptance and mitigation of all risk. Hence they will also own the risk to an information system that supports a critical business process.

Incorrect Answers:
A: The system users are responsible for utilizing the system properly and following procedures, but they do not own the risk.
C: The IT director manages the IT systems on behalf of the business owners.
D: The risk management department determines and reports on level of risk, but does not own the risk. Risk is owned by senior management.



Share your comments for ISACA CRISC exam with other users:

R
Rita Rony
11/27/2023 1:36:00 PM

nice, first step to exams

A
Aloke Paul
9/11/2023 6:53:00 AM

is this valid for chfiv9 as well... as i am reker 3rd time...

C
Calbert Francis
1/15/2024 8:19:00 PM

great exam for people taking 220-1101

A
Ayushi Baria
11/7/2023 7:44:00 AM

this is very helpfull for me

A
alma
8/25/2023 1:20:00 PM

just started preparing for the exam

C
CW
7/10/2023 6:46:00 PM

these are the type of questions i need.

N
Nobody
8/30/2023 9:54:00 PM

does this actually work? are they the exam questions and answers word for word?

S
Salah
7/23/2023 9:46:00 AM

thanks for providing these questions

R
Ritu
9/15/2023 5:55:00 AM

interesting

R
Ron
5/30/2023 8:33:00 AM

these dumps are pretty good.

S
Sowl
8/10/2023 6:22:00 PM

good questions

B
Blessious Phiri
8/15/2023 2:02:00 PM

dbua is used for upgrading oracle database

R
Richard
10/24/2023 6:12:00 AM

i am thrilled to say that i passed my amazon web services mls-c01 exam, thanks to study materials. they were comprehensive and well-structured, making my preparation efficient.

J
Janjua
5/22/2023 3:31:00 PM

please upload latest ibm ace c1000-056 dumps

M
Matt
12/30/2023 11:18:00 AM

if only explanations were provided...

R
Rasha
6/29/2023 8:23:00 PM

yes .. i need the dump if you can help me

A
Anonymous
7/25/2023 8:05:00 AM

good morning, could you please upload this exam again?

A
AJ
9/24/2023 9:32:00 AM

hi please upload sre foundation and practitioner exam questions

P
peter parker
8/10/2023 10:59:00 AM

the exam is listed as 80 questions with a pass mark of 70%, how is your 50 questions related?

B
Berihun
7/13/2023 7:29:00 AM

all questions are so important and covers all ccna modules

N
nspk
1/19/2024 12:53:00 AM

q 44. ans:- b (goto setup > order settings > select enable optional price books for orders) reference link --> https://resources.docs.salesforce.com/latest/latest/en-us/sfdc/pdf/sfom_impl_b2b_b2b2c.pdf(decide whether you want to enable the optional price books feature. if so, select enable optional price books for orders. you can use orders in salesforce while managing price books in an external platform. if you’re using d2c commerce, you must select enable optional price books for orders.)

M
Muhammad Rawish Siddiqui
12/2/2023 5:28:00 AM

"cost of replacing data if it were lost" is also correct.

A
Anonymous
7/14/2023 3:17:00 AM

pls upload the questions

M
Mukesh
7/10/2023 4:14:00 PM

good questions

E
Elie Abou Chrouch
12/11/2023 3:38:00 AM

question 182 - correct answer is d. ethernet frame length is 64 - 1518b. length of user data containing is that frame: 46 - 1500b.

D
Damien
9/23/2023 8:37:00 AM

i need this exam pls

N
Nani
9/10/2023 12:02:00 PM

its required for me, please make it enable to access. thanks

E
ethiopia
8/2/2023 2:18:00 AM

seems good..

W
whoAreWeReally
12/19/2023 8:29:00 PM

took the test last week, i did have about 15 - 20 word for word from this site on the test. (only was able to cram 600 of the questions from this site so maybe more were there i didnt review) had 4 labs, bgp, lacp, vrf with tunnels and actually had to skip a lab due to time. lots of automation syntax questions.

V
vs
9/2/2023 12:19:00 PM

no comments

J
john adenu
11/14/2023 11:02:00 AM

nice questions bring out the best in you.

O
Osman
11/21/2023 2:27:00 PM

really helpful

E
Edward
9/13/2023 5:27:00 PM

question #50 and question #81 are exactly the same questions, azure site recovery provides________for virtual machines. the first says that it is fault tolerance is the answer and second says disater recovery. from my research, it says it should be disaster recovery. can anybody explain to me why? thank you

M
Monti
5/24/2023 11:14:00 PM

iam thankful for these exam dumps questions, i would not have passed without this exam dumps.

AI Tutor 👋 I’m here to help!