ISACA CRISC Exam (page: 33)
ISACA Certified in Risk and Information Systems Control
Updated on: 16-Feb-2026

Viewing Page 33 of 361

You are the project manager of HWD project. It requires installation of some electrical machines. You and the project team decided to hire an electrician as electrical work can be too dangerous to perform. What type of risk response are you following?

  1. Avoidance
  2. Transference
  3. Mitigation
  4. Acceptance

Answer(s): B

Explanation:

As the risk is transferred to the third party (electrician), hence this type of risk response is transference. Incorrect Answers:

A: Risk avoidance means to evade risk altogether, eliminate the cause of the risk event, or change the project plan to protect the project objectives from the risk event. Risk avoidance is applied when the level of risk, even after the applying controls, would be greater than the risk tolerance level of the enterprise.

C: Risk mitigation attempts to reduce the probability of a risk event and its impacts to an acceptable level. Risk mitigation can utilize various forms of control carefully integrated together.

D: Risk acceptance means that no action is taken relative to a particular risk; loss is accepted if it occurs.



You are the project manager of GHT project. You have implemented an automated tool to analyze and report on access control logs based on severity. This tool generates excessively large amounts of results. You perform a risk assessment and decide to configure the monitoring tool to report only when the alerts are marked "critical". What you should do in order to fulfill that?

  1. Apply risk response
  2. Optimize Key Risk Indicator
  3. Update risk register
  4. Perform quantitative risk analysis

Answer(s): B

Explanation:

As the sensitivity of the monitoring tool has to be changed, therefore it requires optimization of Key Risk Indicator. The monitoring tool which is giving alerts is itself acting as a risk indicator. Hence to change the sensitivity of the monitoring tool to give alert only for critical situations requires optimization of the KRI.

Incorrect Answers:
A, C, D: These options are not relevant to the change of sensitivity of the monitoring tools.



One of the risk events you've identified is classified as force majeure. What risk response is likely to be used?

  1. Acceptance
  2. Transference
  3. Enhance
  4. Mitigation

Answer(s): A

Explanation:

Force majeure describes acts of God (Natural disaster), such as tornados and fires, and are usually accepted because there's little than can be done to mitigate these risks.

Incorrect Answers:
B: Transference transfers the risk ownership to a third party, usually for a fee. C: Enhance is used for a positive risk event, not for force majeure.
D: Mitigation isn't the best choice, as this lowers the probability and/or impact of the risk event.



You are the project manager of GHT project. You have applied certain control to prevent the unauthorized changes in your project. Which of the following control you would have applied for this purpose?

  1. Personnel security control
  2. Access control
  3. Configuration management control
  4. Physical and environment protection control

Answer(s): C

Explanation:

Configuration management control is a family of controls that addresses both configuration management and change management. Change control practices prevent unauthorized changes. They include goals such as configuring systems for least functionality as a primary method of hardening systems.

Incorrect Answers:
A: The Personal security control is family of controls that includes aspects of personnel security. It includes personnel screening, termination, and transfer.

B: Access control is the family of controls that helps an organization implement effective access control. They ensure that users have the rights and permissions they need to perform their jobs, and no more. It includes principles such as least privilege and separation of duties.

D: Physical and environment protection control are the family that provides an extensive number of controls related to physical security.



You are the project manager for BlueWell Inc. You have noticed that the risk level in your project increases above the risk tolerance level of your enterprise. You have applied several risk responses. Now you have to update the risk register in accordance to risk response process. All of the following are included in the risk register except for which item?

  1. Risk triggers
  2. Agreed-upon response strategies
  3. Network diagram analysis of critical path activities
  4. Risk owners and their responsibility

Answer(s): C

Explanation:

The risk register does not examine the network diagram and the critical path. There may be risks associated with the activities on the network diagram, but it does not address the network diagram directly.

The risk register is updated at the end of the plan risk response process with the information that was discovered during the process. The response plans are recorded in the risk register. In the risk register, risk is stated in order of priority, i.e., those with the highest potential for threat or opportunity first. Some risks might not require response plans at all, but then too they should be put on a watch list and monitored throughout the project. Following elements should appear in the risk register:

List of identified risks, including their descriptions, root causes, and how the risks impact the project objectives
Risk owners and their responsibility
Outputs from the Perform Qualitative Analysis process Agreed-upon response strategies
Risk triggers
Cost and schedule activities needed to implement risk responses Contingency plans
Fallback plans, which are risk response plans that are executed when the initial risk response plan proves to be ineffective
Contingency reserves
Residual risk, which is a leftover risk that remains after the risk response strategy has been implemented Secondary risks, which are risks that come about as a result of implementing a risk response



Viewing Page 33 of 361



Share your comments for ISACA CRISC exam with other users:

Bhuddhiman 7/30/2023 1:18:00 AM

good mateial
Anonymous


KJ 11/17/2023 3:50:00 PM

good practice exam
Anonymous


sowm 10/29/2023 2:44:00 PM

impressivre qustion
Anonymous


CW 7/6/2023 7:06:00 PM

questions seem helpful
Anonymous


luke 9/26/2023 10:52:00 AM

good content
Anonymous


zazza 6/16/2023 9:08:00 AM

question 21 answer is alerts
ITALY


Abwoch Peter 7/4/2023 3:08:00 AM

am preparing for exam
Anonymous


mohamed 9/12/2023 5:26:00 AM

good one thanks
EGYPT


Mfc 10/23/2023 3:35:00 PM

only got thru 5 questions, need more to evaluate
Anonymous


Whizzle 7/24/2023 6:19:00 AM

q26 should be b
Anonymous


sarra 1/17/2024 3:44:00 AM

the aaa triad in information security is authentication, accounting and authorisation so the answer should be d 1, 3 and 5.
UNITED KINGDOM


DBS 5/14/2023 12:56:00 PM

need to attend this
UNITED STATES


Da_costa 8/1/2023 5:28:00 PM

these are free brain dumps i understand, how can one get free pdf
Anonymous


vikas 10/28/2023 6:57:00 AM

provide access
EUROPEAN UNION


Abdullah 9/29/2023 2:06:00 AM

good morning
Anonymous


Raj 6/26/2023 3:12:00 PM

please upload the ncp-mci 6.5 dumps, really need to practice this one. thanks guys
Anonymous


Miguel 10/5/2023 12:21:00 PM

question 16: https://help.salesforce.com/s/articleview?id=sf.care_console_overview.htm&type=5
SPAIN


Hiren Ladva 7/8/2023 10:34:00 PM

yes i m prepared exam
Anonymous


oliverjames 10/24/2023 5:37:00 AM

my experience was great with this site as i studied for the ms-900 from here and got 900/1000 on the test. my main focus was on the tutorials which were provided and practice questions. thanks!
GERMANY


Bhuddhiman 7/20/2023 11:52:00 AM

great course
UNITED STATES


Anuj 1/14/2024 4:07:00 PM

very good question
Anonymous


Saravana Kumar TS 12/8/2023 9:49:00 AM

question: 93 which statement is true regarding the result? sales contain 6 columns and values contain 7 columns so c is not right answer.
INDIA


Lue 3/30/2023 11:43:00 PM

highly recommend just passed my exam.
CANADA


DC 1/7/2024 10:17:00 AM

great practice! thanks
UNITED STATES


Anonymus 11/9/2023 5:41:00 AM

anyone who wrote this exam recently?
SOUTH AFRICA


Khalid Javid 11/17/2023 3:46:00 PM

kindly share the dump
Anonymous


Na 8/9/2023 8:39:00 AM

could you please upload cfe fraud prevention and deterrence questions? it will be very much helpful.
Anonymous


shime 10/23/2023 10:03:00 AM

this is really very very helpful for mcd level 1
ETHIOPIA


Vnu 6/3/2023 2:39:00 AM

very helpful!
Anonymous


Steve 8/17/2023 2:19:00 PM

question #18s answer should be a, not d. this should be corrected. it should be minvalidityperiod
CANADA


RITEISH 12/24/2023 4:33:00 AM

thanks for the exact solution
Anonymous


SB 10/15/2023 7:58:00 AM

need to refer the questions and have to give the exam
INDIA


Mike Derfalem 7/16/2023 7:59:00 PM

i need it right now if it was possible please
Anonymous


Isak 7/6/2023 3:21:00 AM

i need it very much please share it in the fastest time.
Anonymous