Which of the following vulnerability assessment software can check for weak passwords on the network?
Answer(s): A
A password cracker is an application program that is used to identify an unknown or forgotten password on a computer or network resources. It can also be used to help a human cracker obtain unauthorized access to resources. A password cracker can also check for weak passwords on the network and give notifications to put another password.Incorrect Answers:B: Antivirus or anti-virus software is used to prevent, detect, and remove malware. It scans the computer for viruses.C: Anti-spyware software is a type of program designed to prevent and detect unwanted spyware program installations and to remove those programs if installed.D: Wireshark is a free and open-source protocol analyzer. It is used for network troubleshooting, analysis, software and communications protocol development, and education.
Which of the following is NOT true for risk governance?
Answer(s): B
Risk governance is a continuous life cycle that requires regular reporting and ongoing review, not once a year. Incorrect Answers:A, C, D: These are true for risk governance.
You are the project manager of HGT project. You have identified project risks and applied appropriate response for its mitigation. You noticed a risk generated as a result of applying response. What this resulting risk is known as?
Secondary risk is a risk that is generated as the result of risk response. Incorrect Answers:A: A pure risk is a risk that has only a negative effect on the project. Pure risks are activities that are dangerous to complete and manage such as construction, electrical work, or manufacturing.C, D: These terms are not applied for the risk that is generated as a result of risk response.
What are the various outputs of risk response?
Answer(s): C,D,E
The outputs of the risk response planning process are:Risk Register Updates: The risk register is written in detail so that it can be related to the priority ranking and the planned response.Risk Related Contract Decisions: Risk related contract decisions are the decisions to transmit risk, such as services, agreements for insurance, and other items as required. It provides a means for sharing risks.Project Management Plan Updates: Some of the elements of the project management plan updates are:- Schedule management plan- Cost management plan- Quality management plan- Procurement management plan- Human resource management plan- Work breakdown structure- Schedule baseline- Cost performance baselineProject Document Updates: Some of the project documents that can be updated includes: - Assumption log updates- Technical documentation updatesIncorrect Answers:A: Risk priority number is not an output for risk response but instead it is done before applying response. Hence it acts as one of the inputs of risk response and is not the output of it.B: Residual risk is not an output of risk response. Residual risk is the risk that remains after applying controls. It is not feasible to eliminate all risks from an organization. Instead, measures can be taken to reduce risk to an acceptable level. The risk that is left is residual risk. As,Risk = Threat Vulnerability andTotal risk = Threat Vulnerability Asset ValueResidual risk can be calculated with the following formula:Residual Risk = Total Risk - ControlsSenior management is responsible for any losses due to residual risk. They decide whether a risk should be avoided, transferred, mitigated or accepted. They also decide what controls to implement. Any loss due to their decisions falls on their sides.Residual risk assessments are conducted after mitigation to determine the impact of the risk on the enterprise. For risk assessment, the effect and frequency is reassessed and the impact is recalculated.
Which of the following is an output of risk assessment process?
The output of the risk assessment process is identification of appropriate controls for reducing or eliminating risk during the risk mitigation process. To determine the likelihood of a future adverse event, threats to an IT system must be analyzed in conjunction with the potential vulnerabilities and the controls in place for the IT system.Once risk factors have been identified, existing or new controls are designed and measured for their strength and likelihood of effectiveness. Controls are preventive, detective or corrective; manual or programmed; and formal or ad hoc.Incorrect Answers:A: Risk identification acts as input of the risk assessment process.C: This is an output of risk mitigation process, that is, after applying several risk responses. D: Residual risk is the latter output after appropriate control.
Share your comments for ISACA CRISC exam with other users:
passed my first exam last week and pass the second exam this morning. thank you sir for all the help and these brian dumps.
does anyone who attended exam csa 8.8, can confirm these questions are really coming ? or these are just for practicing?
kindly share the dumps
very nice content
passed today
hi can you please upload questions
please upload quetions
i passed my exam thanks to this braindumps questions. these questions are valid in us and i highly recommend it!
are they truely latest
questions appear contemporary.
good to prepare in this site
very helpful to crack first attempt
please upload this exam
please upload the c_activate22 dump questions with answer
q10 - the answer should be a. if its c, the criteria will meet if either the prospect is not part of the suppression lists or if the job title contains vice president
this was on the exam as of 1211/2023
great for prep
i think in question 7 the first answer should be power bi portal (not power bi)
on question 10 and so far 2 wrong answers as evident in the included reference link.
wonderful material
i passed!! ...but barely! got 728, but needed 720 to pass. the exam hit me with labs right out of the gate! then it went to multiple choice. protip: study the labs!
correct answer for question 92 is c -aws shield
great !! it is really good
explanations for the answers are to the point.
how can rea next
question: 128 d is the wrong answer...should be c
thanks for az 700 dumps
thank you for this tableau dumps . it will helpfull for tableau certification
good content
just testing if the comments are real
very helpful for exam preparation
question 11: https://help.salesforce.com/s/articleview?id=sf.admin_lead_to_patient_setup_overview.htm&type=5
i think the answer to question 42 is b not c