ISACA CRISC Exam (page: 1)
ISACA Certified in Risk and Information Systems Control
Updated on: 12-Aug-2025

Viewing Page 1 of 361

Which of the following is the MOST important reason to maintain key risk indicators (KRIs)?

  1. In order to avoid risk
  2. Complex metrics require fine-tuning
  3. Risk reports need to be timely
  4. Threats and vulnerabilities change over time

Answer(s): D

Explanation:

Threats and vulnerabilities change over time and KRI maintenance ensures that KRIs continue to effectively capture these changes.

The risk environment is highly dynamic as the enterprise's internal and external environments are constantly changing. Therefore, the set of KRIs needs to be changed over time, so that they can capture the changes in threat and vulnerability.

Incorrect Answers:
A: Risk avoidance is one possible risk response. Risk responses are based on KRI reporting, but is not the reason for maintenance of KRIs.

B: While most key risk indicator (KRI) metrics need to be optimized in respect to their sensitivity, the most important objective of KRI maintenance is to ensure that KRIs continue to effectively capture the changes in threats and vulnerabilities over time. Hence the most important reason is that because of change of threat and vulnerability overtime.

C: Risk reporting timeliness is a business requirement, but is not a reason for KRI maintenance.



You are the project manager of a HGT project that has recently finished the final compilation process. The project customer has signed off on the project completion and you have to do few administrative closure activities. In the project, there were several large risks that could have wrecked the project but you and your project team found some new methods to resolve the risks without affecting the project costs or project completion date. What should you do with the risk responses that you have identified during the project's monitoring and controlling process?

  1. Include the responses in the project management plan.
  2. Include the risk responses in the risk management plan.
  3. Include the risk responses in the organization's lessons learned database.
  4. Nothing. The risk responses are included in the project's risk register already.

Answer(s): C

Explanation:

The risk responses that do not exist up till then, should be included in the organization's lessons learned database so other project managers can use these responses in their project if relevant.

Incorrect Answers:
A: The responses are not in the project management plan, but in the risk response plan during the project and they'll be entered into the organization's lessons learned database.

B: The risk responses are included in the risk response plan, but after completing the project, they should be entered into the organization's lessons learned database.

D: If the new responses that were identified is only included in the project's risk register then it may not be shared with project managers working on some other project.



You are the project manager of GHT project. You have identified a risk event on your project that could save $100,000 in project costs if it occurs. Which of the following statements BEST describes this risk event?

  1. This risk event should be mitigated to take advantage of the savings.
  2. This is a risk event that should be accepted because the rewards outweigh the threat to the project.
  3. This risk event should be avoided to take full advantage of the potential savings.
  4. This risk event is an opportunity to the project and should be exploited.

Answer(s): D

Explanation:

This risk event has the potential to save money on project costs, so it is an opportunity, and the appropriate strategy to use in this case is the exploit strategy. The exploit response is one of the strategies to negate risks or threats appear in a project. This strategy may be selected for risks with positive impacts where the organization wishes to ensure that the opportunity is realized. Exploiting a risk event provides opportunities for positive impact on a project. Assigning more talented resources to the project to reduce the time to completion is an example of exploit response.

Incorrect Answers:
A, C: Mitigation and avoidance risk response is used in case of negative risk events, and not in positive risk events. Here in this scenario, as it is stated that the event could save $100,000, hence it is a positive risk event. Therefore should not be mitigated or avoided.

B: To accept risk means that no action is taken relative to a particular risk; loss is accepted if it occurs. But as this risk event bring an opportunity, it should me exploited and not accepted.



You are the project manager of a large construction project. This project will last for 18 months and will cost $750,000 to complete. You are working with your project team, experts, and stakeholders to identify risks within the project before the project work begins. Management wants to know why you have scheduled so many risk identification meetings throughout the project rather than just initially during the project planning. What is the best reason for the duplicate risk identification sessions?

  1. The iterative meetings allow all stakeholders to participate in the risk identification processes throughout the project phases.
  2. The iterative meetings allow the project manager to discuss the risk events which have passed the project and which did not happen.
  3. The iterative meetings allow the project manager and the risk identification participants to identify newly discovered risk events throughout the project.
  4. The iterative meetings allow the project manager to communicate pending risks events during project execution.

Answer(s): C

Explanation:

Risk identification is an iterative process because new risks may evolve or become known as the project progresses through its life cycle.

Incorrect Answers:
A: Stakeholders are encouraged to participate in the risk identification process, but this is not the best choice. B: Risk identification focuses on discovering new risk events, not the events which did not happen.
D: The primary reason for iterations of risk identification is to identify new risk events.



You are the risk official in Bluewell Inc. You are supposed to prioritize several risks. A risk has a rating for occurrence, severity, and detection as 4, 5, and 6, respectively. What Risk Priority Number (RPN) you would give to it?

  1. 120
  2. 100
  3. 15
  4. 30

Answer(s): A

Explanation:

Steps involving in calculating risk priority number are as follows:
-Identify potential failure effects
-Identify potential causes
-Establish links between each identified potential cause
-Identify potential failure modes
-Assess severity, occurrence and detection
-Perform score assessments by using a scale of 1 -10 (low to high rating) to score these assessments.
-Compute the RPN for a particular failure mode as Severity multiplied by occurrence and detection.
RPN = Severity * Occurrence * Detection
Hence,
RPN = 4 * 5 * 6
= 120
Incorrect Answers:
B, C, D: These are not RPN for given values of severity, occurrence, and detection.



Viewing Page 1 of 361



Share your comments for ISACA CRISC exam with other users:

nSiva 9/22/2023 5:58:00 AM

its useful.
UNITED STATES


Ranveer 7/26/2023 7:26:00 PM

Pass this exam 3 days ago. The PDF version and the Xengine App is quite useful.
SOUTH AFRICA


Sanjay 8/15/2023 10:22:00 AM

informative for me.
UNITED STATES


Tom 12/12/2023 8:53:00 PM

question 134s answer shoule be "dlp"
JAPAN


Alex 11/7/2023 11:02:00 AM

in 72 the answer must be [sys_user_has_role] table.
Anonymous


Finn 5/4/2023 10:21:00 PM

i appreciated the mix of multiple-choice and short answer questions. i passed my exam this morning.
IRLAND


AJ 7/13/2023 8:33:00 AM

great to find this website, thanks
UNITED ARAB EMIRATES


Curtis Nakawaki 6/29/2023 9:11:00 PM

examination questions seem to be relevant.
UNITED STATES


Umashankar Sharma 10/22/2023 9:39:00 AM

planning to take psm test
Anonymous


ED SHAW 7/31/2023 10:34:00 AM

please allow to download
UNITED STATES


AD 7/22/2023 11:29:00 AM

please provide dumps
UNITED STATES


Ayyjayy 11/6/2023 7:29:00 AM

is the answer to question 15 correct ? i feel like the answer should be b
BAHRAIN


Blessious Phiri 8/12/2023 11:56:00 AM

its getting more technical
Anonymous


Jeanine J 7/11/2023 3:04:00 PM

i think these questions are what i need.
UNITED STATES


Aderonke 10/23/2023 2:13:00 PM

helpful assessment
UNITED KINGDOM


Tom 1/5/2024 2:32:00 AM

i am confused about the answers to the questions. do you know if the answers are correct?
KOREA REPUBLIC OF


Vinit N. 8/28/2023 2:33:00 AM

hi, please make the dumps available for my upcoming examination.
UNITED STATES


Sanyog Deshpande 9/14/2023 7:05:00 AM

good practice
UNITED STATES


Tyron 9/8/2023 12:12:00 AM

so far it is really informative
Anonymous


beast 7/30/2023 2:22:00 PM

hi i want it please please upload it
Anonymous


Mirex 5/26/2023 3:45:00 AM

am preparing for exam ,just nice questions
Anonymous


exampei 8/7/2023 8:05:00 AM

please upload c_tadm_23 exam
TURKEY


Anonymous 9/12/2023 12:50:00 PM

can we get tdvan4 vantage data engineering pdf?
UNITED STATES


Aish 10/11/2023 5:51:00 AM

want to clear the exam.
INDIA


Smaranika 6/22/2023 8:42:00 AM

could you please upload the dumps of sap c_sac_2302
INDIA


Blessious Phiri 8/15/2023 1:56:00 PM

asm management configuration is about storage
Anonymous


Lewis 7/6/2023 8:49:00 PM

kool thumb up
UNITED STATES


Moreece 5/15/2023 8:44:00 AM

just passed the az-500 exam this last friday. most of the questions in this exam dumps are in the exam. i bought the full version and noticed some of the questions which were answered wrong in the free version are all corrected in the full version. this site is good but i wish the had it in an interactive version like a test engine simulator.
Anonymous


Terry 5/24/2023 4:41:00 PM

i can practice for exam
Anonymous


Emerys 7/29/2023 6:55:00 AM

please i need this exam.
Anonymous


Goni Mala 9/2/2023 12:27:00 PM

i need the dump
Anonymous


Lenny 9/29/2023 11:30:00 AM

i want it bad, even if cs6 maybe retired, i want to learn cs6
HONG KONG


MilfSlayer 12/28/2023 8:32:00 PM

i hate comptia with all my heart with their "choose the best" answer format as an argument could be made on every question. they say "the "comptia way", lmao no this right here boys is the comptia way 100%. take it from someone whos failed this exam twice but can configure an entire complex network that these are the questions that are on the test 100% no questions asked. the pbqs are dead on! nice work
Anonymous


Swati Raj 11/14/2023 6:28:00 AM

very good materials
UNITED STATES