During the post-implementation review of an application that was implemented six months ago, which of the following would be MOST helpful in determining whether the application meets business requirements?
- Project closure report and lessons-learned documents from the project management office (PMO)
- User acceptance testing (UAT) results and sign-off from users on meeting business requirements
- Difference between approved budget and actual project expenditures determined post implementation
- Comparison between expected benefits from the business case and actual benefits after implementation